Becco Crews Demolish Bird Creek Bridges

The crews didn’t exactly blow up the truss bridges, but rather set the charges and dropped them straight down.

Fri July 22, 2016 - West Edition #15
Lori Tobias


ODOT photo.Before photos — bridge at 56th and the two truss bridges over Bird Creek.
ODOT photo.Before photos — bridge at 56th and the two truss bridges over Bird Creek.
ODOT photo.Before photos — bridge at 56th and the two truss bridges over Bird Creek.
 ODOT photo. Before photos — bridge at 56th and the two truss bridges over Bird Creek. ODOT photo.The expansion, which stretches 1 mi. (1.6 km) from 56th Street North to 66th Street North, will open the highway from four lanes in each direction to six.
 ODOT photo. Becco Contractors Inc. of Tulsa won the bid for the job and began work in July 2015. It included the removal of two truss bridges over Bird Creek originally built in 1960. 
 ODOT photo. The crews didn’t exactly blow up the truss bridges, but rather set the charges and dropped them straight down.
 ODOT photo.Traffic in the most recent demolition on Bird Creek was shut down for only 15 minutes. It took place on a Sunday morning when traffic volume was low.
 ODOT photo.Six other bridges were not truss bridges, but were high maintenance and/or structurally deficient, and were demolished by using heavy equipment to lift off the concrete deck and beams.
 ODOT photo.Other equipment on the job includes cranes for the bridgework, earthmoving equipment and asphalt pavers.

Construction crews recently demolished the last of eight bridges as part of a $45 million Oklahoma Department of Transportation project to expand U.S. 169 in Owasso. The expansion, which stretches 1 mi. (1.6 km) from 56th Street North to 66th Street North, will open the highway from four lanes in each direction to six.

“We're making really good progress on the project,” said Kenna Carmon, ODOT division eight public information officer.

Becco Contractors Inc. of Tulsa won the bid for the job and began work in July 2015. It included the removal of two truss bridges over Bird Creek originally built in 1960.

“The Bird Creek bridges were in very poor condition,” said ODOT construction engineer Mark Zishka. “We had to regularly go out and make repairs on the trusses. They were high maintenance bridges that we wanted to get off the system as soon as possible. Our maintenance crews were doing maintenance and often it came right before rush hour and created a lot of problems for commuters.”

The crews didn't exactly blow up the truss bridges, but rather set the charges and dropped them straight down. The tricky part came in getting the charges set just right, Zishka said.

“We have the two southbound bridges built and half of the northbound bridges,” he said. “There wasn't much room for error. If the charges hadn't been set correctly they could have fallen into the new bridges.”

An earlier bridge demolition took place last December and went off without a hitch.

“Generally what they will do is traffic is maintained until they are ready to detonate those charges,” Zishka said. “Then they shut the road down, set the charges and make sure the roadway is clear. Once they determine the roadway is clear of debris from the charges, they will open it back up to traffic.”

Traffic in the most recent demolition on Bird Creek was shut down for only 15 minutes. It took place on a Sunday morning when traffic volume was low, Carmon said.

The other six bridges were not truss bridges, but also were high maintenance and/or structurally deficient, and were demolished by using heavy equipment to lift off the concrete deck and beams. Other equipment on the job includes cranes for the bridgework, earthmoving equipment and asphalt pavers.

The biggest trial in completing the project is keeping the traffic flowing, Zishka said.

“We basically set it up to maintain two lanes of traffic in each direction during construction, and to build the different phases in a way that allows up to keep two lanes of traffic moving. The average daily traffic is 58,000 vehicles a day. For a four-lane highway, that's a lot of traffic. We get a lot of congestion in the morning. We have six lanes to the south that we finished five years ago to increase capacity. We're slowly moving north into the Owasso area, which is where the commuter traffic comes from.”

Keeping traffic flowing smoothly is something of a “puzzle,” Carmon said. “We have to remove a little bit here and there in order to put it all back together. So we're making really good progress right now with getting this last bit of the old out and being able to put the new in place.”

The project is progressing as expected with some portions even ahead of schedule, Zishka said.

“These new bridges will carry six lanes in each direction,” he said. “The northbound Bird Creek bridge carries the 56th Street onramp and creates a safer merge. Previously, it was a tight squeeze to try to merge. Commuters will definitely appreciate the new bridges.”

The project is set for completion in by spring 2017.


Today's top stories

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Muddy Water Dredging Christens Marlin Class Dredge

Indiana Officials Mark Start of 2024 Construction Season, Promote Safety

Leica Geosystems Launches its First Machine Smart Antenna — Leica iCON gps 120


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA