Crews Overcome Obstacles on Montana Bridge

The project, also known as the Heron Bridge Replacement, features a new, sturdier bridge on Heron Road.

Mon February 20, 2017 - West Edition
Chuck Harvey


Montana Department of Transportation photo. Montana’s $13.5 million Cabinet Gorge Replacement Project is progressing despite discovery of a huge boulder obstruction by workers drilling under the Columbia River.
Montana Department of Transportation photo. Montana’s $13.5 million Cabinet Gorge Replacement Project is progressing despite discovery of a huge boulder obstruction by workers drilling under the Columbia River.
Montana Department of Transportation photo. Montana’s $13.5 million Cabinet Gorge Replacement Project is progressing despite discovery of a huge boulder obstruction by workers drilling under the Columbia River.  Montana Department of Transportation photo.
The boulder slowed foundation work on the bridge that will cross the Clark Fork of the river in Sanders County, Mont. Montana Department of Transportation photo. The project features a new, sturdier bridge on Heron Road.  Montana Department of Transportation photo. The bridge site is located about 1.5 mi. (2.4 km) south of Montana state Route 200 and 3.6 mi. (5.8 km) east of the Montana-Idaho state line. Montana Department of Transportation photo.
Work began on Sept. 9, 2015. Tentative completion is due in October 2017. Montana Department of Transportation photo
The existing bridge will remain in place until the new bridge is ready for traffic, then the old bridge will be taken down.

Montana's $13.5 million Cabinet Gorge Replacement Project is progressing despite discovery of a huge boulder obstruction by workers drilling under the Columbia River that slowed foundation work on the bridge that will cross the Clark Fork of the river in Sanders County, Mont.

The project, also known as the Heron Bridge Replacement, features a new, sturdier bridge on Heron Road. The bridge site is located about 1.5 mi. (2.4 km) south of Montana state Route 200 and 3.6 mi. (5.8 km) east of the Montana-Idaho state line.

Work began on Sept. 9, 2015. Tentative completion is due in October 2017.

The bridge will provide an improved connection to the town of Heron, 3 mi. (4.9 km) from the Idaho border.

The existing bridge is a deck truss structure with a 360-ft. (110 m) main span, two 100-ft. (30.5 m) back spans, seven 15-ft. (4.6 m) timber approach spans on the south end of the bridge and two 15-ft. timber approach spans on the north side.

The new Cabinet Gorge Bridge features a 375-ft. (114.3 m)-long steel plate girder main span with approach section of 275-ft. (84 m) on the south end and 110 ft. (33.5 m) on the north end. It will carry two lanes of traffic instead of just one lane on the existing bridge.

The existing bridge will remain in place until the new bridge is ready for traffic, then the old bridge will be taken down.

The new bridge is unique as it is one of the longest steel plate girder structures west of the Mississippi River. The structure is slender compared to other large span steel plate girder structures as it carries a narrow two lane rural road across the reservoir.

“The narrow section of the bridge contributed to lateral instability challenges that had to be addressed through design and are uncommon in steel structures of this span length,” said Robert Vosen, construction engineer for Missoula District, Montana Department of Transportation.

Foundation work for the bridge was under way when crews encountered one or two boulders at a depth of about 60 ft. (18 m) below the water surface near the south upstream river pier. Thickness of the obstruction varied from 12 ft. (3.7 m) to 26 ft. (8 m), making shaft drilling impossible at the location.

The construction team worked out a plan to avoid the unexpected obstruction so a deep foundation could be installed.

“A large 25-foot-plus boulder was encountered when working on the planned eight-foot drilled shaft,” Vosen said. “Additional boulders were also found. The obstruction problem was resolved with a re-design and a new work method was implemented.”

Vosen added, “Seven 16-inch diameter macro-piles are now being installed. Each pile is approximately 190 feet in length. The macro-pile will be filled with rebar and grout.”

The length in delay of project work caused by the huge boulder was still under evaluation in December 2016, but work was proceeding.

Contractor for the new bridge project is Dick Anderson Construction of Helena, Mont. Selected as low bidder for the work, the company is a general contractor and construction management company with 40 years of experience with commercial, civil, industrial, residential, energy and bridge projects.

Tami Hembree is the engineering project manager for Montana Department of Transportation, Missoula District.

Currently two subcontractors are at work on the project: Condon-Johnson & Associates Inc. of Oakland, Calif., and Layne Christensen Co. of Mission Woods, Kan. Other subcontractors scheduled to work on the project include Zublin Corporation of Atlanta, Ga.; Grizzly Steel Inc. of Whitehall, Mont.; Lippert Excavation & Pipeline Inc. of Sandpoint, Idaho; and Mountain West Holding Co. of Billings, Mont.

The number of workers on the job will vary during the project, but currently about seven are on duty each day including laborers and equipment operators.

“These numbers will likely increase when work on the superstructure begins in the spring and summer,” Vosen said.

Crews building the bridge will construct two 12-ft. -wide lanes for crossing on a roadway with a 30-ft. (9 m) curb to curb width.

Besides having a wider roadway, the new bridge will be built to handle heavier vehicles. It will not be load restricted, allowing legal loads to cross safely.

It also will provide a crossing that will have a long useful life compared to the existing bridge that is reaching the end of its functional life.

“With a wider and non-load restricted bridge at this location traffic is likely to increase, which could provide an economic advantage to the community of Heron on the other side of the bridge,” Vosen said.

He said bridge foundation work has resumed and workers are currently in the process of drilling and installing the third of seven 16-in. (40.6 cm) diameter rotary drilled steel pipe piles inside of an 8-ft. (2.4 m) diameter steel casing.

Heavy Equipment

On site is an IMT IFI 18 dual rotary drill rig; a 200-ton (181.4 t) Kobelco CK2000 lattice boom crane; a 100-ton (90.7 t) Manitowoc 10000 lattice boom crane; a forklift; a loader; an end dump; and a man lift. Barges are currently being used for additional work platforms.

Workers will pour 2,620 cu. yds. (2,003 cu m) of concrete during the course of the project. Commercial plant mix paving grade asphalt 64-28 is planned at 869 tons (788 t).

Additional soil will be needed to create grade for the new bridge.

“Some of the excavation required to build the new grade is under the presently traveled road,” Vosen said. “For the contractor's convenience and at their cost, a small amount of material was brought in to build a small section of the new grade. Some of the excavation under the presently traveled road may be hauled off site for the contractor's convenience and at their expense.”

Existing Bridge Is More Than 60 Years Old

The original Cabinet Gorge Reservoir Bridge was constructed in 1952. As a truss bridge it has increased maintenance and inspection costs compared to the new steel girder bridge replacing it.

It has a total length of 694.9 ft. (211.8 m) and a deck width of 18 ft. (5.5 m).

The bridge is posted with a 12-ton (11 t) load limit and has only a single lane.

The bridge is built at an elevation of 2,220 ft. (677 m).

A Safe, Solid, Long-Lasting Bridge Is Vital

The Columbia River's 310-mi. (499 km)-long Clark Fork is crossed by only two other bridges in the general area of the Cabinet Gorge Bridge.

One is located in the town of Noxon, Mont., and is a three span through truss bridge built in 1922. It is approximately 13 mi. (21 km) upstream and southeast of the Cabinet Gorge (Heron) Bridge.

Downstream travelers will find a bridge crossing the Clark Fork near the town of Clark Fork, Idaho, approximately 12 mi. (19 km) to the northwest.

So with few crossings in the area and other bridges aging, the new Cabinet Gorge Bridge will be an important crossing that is designed to last.

Many more bridges can be found upstream crossing Clark Fork in Montana. But they are some distance from Cabinet Gorge.

The Columbia River is the largest river by volume in Montana. It drains an extensive region of the Rocky Mountains in western Montana and northern Idaho in the watershed of the Columbia River.

The river flows northwest through a long valley at the base of the Cabinet Mountains and empties into Lake Pend Oreille in the Idaho Panhandle. The Clark Fork is a Class I river for recreational purposes in Montana from Warm Springs Creek to the Idaho border.—CEG




Today's top stories

Growing Interest in Construction Careers Among Younger People Means Jobs Filled, Deadlines Met

Larry Young Paving Tackles Grade-Separated Interchange in Texas

Caltrans, Crews Working to Repair Highway Landslides

FIRSTGREEN Industries Launches ROCKEAT Electric Skid Steer Loader

'Tiltrotator Effect' Increases as Energy Consumption Goes Down

VIDEO: Birmingham, Ala., Awarded $14.5M Fed Grant to Revitalize Its 'Black Main Street'

Pettibone Celebrates 75th Anniversary of Cary-Lift

Fay Preps Way for Pittsburgh International Airport Modernization Project


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA