List Your Equipment  /  Dealer Login

GDOT Crews Pour New Spans for SR 400 Project

Thu February 15, 2024 - Southeast Edition #4
CEG


Each span took approximately eight hours to slide into place.
Photo courtesy of Georgia Department of Transportation
Each span took approximately eight hours to slide into place.
Each span took approximately eight hours to slide into place.   (Photo courtesy of Georgia Department of Transportation) Early in February, construction crews began working on a new deck for the new Kimball Bridge Road bridge, part of the $55 million SR 400 Bridge Replacements project in Fulton County.   (Photo courtesy of Georgia Department of Transportation) Contractors were awarded the contract in May 2022 and work is expected to be completed between April and June 2024.   (Photo courtesy of Georgia Department of Transportation) Bridges are being replaced and widened to accommodate the future express lanes along SR 400. The new bridges will be replaced with taller, wider structures, which will feature multiuse paths and sidewalks.   (Photo courtesy of Georgia Department of Transportation) The SR 400 Bridge Replacement Project will see a new Kimball Bridge Road, Pitts Road and Roberts Drive bridges constructed over SR 400.   (Photo courtesy of Georgia Department of Transportation) The old Kimball Bridge Road bridge was demolished in June 2023.   (Photo courtesy of Georgia Department of Transportation)

Construction crews working for the Georgia Department of Transportation reached a crucial milestone on one of the more significant construction projects in the state.

During the first week of January, crews began executing the beginning of a new deck for the new Kimball Bridge Road bridge, according to the Georgia Department of Transportation.

Each span was poured and took approximately eight hours to slide into place.

Photo courtesy of Georgia Department of Transportation

This work is part of the GDOT's $55 million SR 400 Bridge Replacements project — taking place in Fulton County — where the Kimball Bridge Road, Pitts Road and Roberts Drive bridges over SR 400 are being replaced.

Contractors were awarded the contract in May 2022 and work is expected to be completed between April and June of 2024.

"The new bridges will provide operational and local road improvements in advance of the major express lanes construction," said Georgia DOT Design-Build Project Manager Rick O'Hara.

The Pitts Road, Roberts Drive and Kimball Bridge Road bridges over SR 400 — which are more than 50 years old and nearing their end of lives — are being replaced and widened to accommodate the future express lanes along SR 400, according to project details. The new bridges will be replaced with taller, wider structures which will feature multiuse paths and sidewalks.

  • The Kimball Road Bridge will be replaced with a raised profile, increased from two to four lanes with a median, a multi-use path on the north side and a sidewalk on the south side. There is a local agreement with the city of Alpharetta for bridge aesthetics.
  • The Pitts Road Bridge is being replaced and widened with a raised profile to allow for a 12-ft. multi-use path on the south side, a sidewalk on the north side, as well as interior barrier walls on both the north and south sides separating pedestrians from the two travel lanes. There is a local agreement with the city of Sandy Springs for bridge aesthetics.
  • The Roberts Drive Bridge will undergo a similar reconstruction, with an interior barrier wall on the south side separating pedestrians from the travel lanes.

This project is impacting traffic. The Kimball Bridge Road bridge was closed to traffic on May 8, 2023, and the Pitts Road bridge was closed to traffic on June 12, 2023. Detours have been established until the bridges re-open in June 2024.

The Roberts Drive bridge is under construction with the new structure being built alongside the existing structure, with completion expected on May 22, 2024.

The design-build project "was pulled forward as part of the phased delivery of the planned SR 400 Express Lanes," stated the project web page.




Today's top stories

Blalock Crews Build TDOT's $67M Newport Bypass

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Equip Expo's Summer Giveaway Offers a Chance for Lifetime Trade Show Registration, Gift Card, Hotel Stay

Tennessee's Pugmill Systems LLC Expands Its Product Offerings to Include Concrete Plants

ASCENDUM Machinery Opens New Savannah, Ga., Facility


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA