Recycling Key Part of Arizona's Broadway Curve Project

Tue January 10, 2023 - West Edition #2
ADOT


Crews use equipment to break each piece into sizes no larger than 24 in. Those pieces are used as fill to build up approaches for new bridges.
(Photo courtesy of ADOT.)
Crews use equipment to break each piece into sizes no larger than 24 in. Those pieces are used as fill to build up approaches for new bridges. (Photo courtesy of ADOT.)
Crews use equipment to break each piece into sizes no larger than 24 in. Those pieces are used as fill to build up approaches for new bridges.
(Photo courtesy of ADOT.) Asphalt millings, concrete, metal and steel are the most common types of waste, but the project team has future plans for all of them for the Broadway Curve.
(Photo courtesy of ADOT.) “We reuse as much as we can so nothing goes to waste,’ said Kole Dea, senior resident engineer of the Arizona Department of Transportation. (Photo courtesy of ADOT.) In summer 2021, crews removed the rubberized asphalt from the surfaces of I-10 and U.S. 60 in the project area. That work created 1.3 million sq. yds. of millings, which are being used as the base layer for temporary haul roads in the project area. (Photo courtesy of ADOT.) The I-10 Broadway Curve Improvement Project runs along 11 mi. of I-10 between Loop 202 and I-17 near Phoenix Sky Harbor International Airport. 
(Photo courtesy of ADOT.)

Reduce, reuse and recycle: They're key to protecting natural resources and lessening the amount of trash in local landfills. They're also an important part of the Interstate 10 Broadway Curve Improvement Project.

"We reuse as much as we can so nothing goes to waste,' said Kole Dea, senior resident engineer of the Arizona Department of Transportation. "If something can't go back into the project, then it's recycled."

Asphalt millings, concrete, metal and steel are the most common types of waste, but the project team has future plans for all of them.

Asphalt Millings

When construction began in summer 2021, crews removed the rubberized asphalt from the surfaces of I-10 and U.S. 60 in the project area. That work created 1.3 million sq. yds. of millings, which are being used as the base layer for temporary haul roads in the project area. Millings provide a strong base for trucks and equipment to drive on, and they reduce dust — another plus for the environment. Millings also can be mixed in with dirt to build embankments that will support the roadway. Outside of the project area, ADOT uses millings on its maintenance roads in unpaved areas.

Concrete

As walls and other concrete structures are taken down to make way for new construction, they're broken up so they can serve a new purpose. Crews are using equipment to break each piece into sizes no larger than 24 in.Those pieces are used as fill to build up approaches for new bridges and can be used to fill in holes or otherwise supplement unstable materials in the project area.

Metal, Steel

Metal and steel products are major components of highway infrastructure, inside and out. In addition to what locals can see, they're also being used to reinforce concrete girders and other structures and strengthen walls on the highway. Steel rebar and other materials are broken down and taken to a recycling facility. Reusable construction debris recycled steel is as strong and durable as new steel made from iron ore.

ADOT works in compliance with state and federal regulations to ensure reused materials do not pose a threat to the environment. Careful testing confirms that the paint stripes on milled asphalt don't contain lead, and that old pipes or bridge structures are free from asbestos.

As new roadways, ramps and bridges take shape throughout the Broadway Curve work zone, construction crews are taking into account how important the infrastructure from the past is to building for the future.

This story also appears on Aggregate Equipment Guide.




Today's top stories

Jobseekers Leveraging Career Market for In-Demand Skilled Trades

Value in Remanufacturing Construction Equipment: Reduce Cost, Downtime, Carbon Footprint

Buckley, PennDOT Restore I-95 to Usefulness in Philly

Meta Plans to Build $800M Next-Generation Data Center in Montgomery, Ala.

Demolition Crews Bring Down Largest Span of Baltimore's Collapsed Key Bridge

Flo Engineering Restoring Access to Critical Highway in California

Webber Working to Complete $300M Texas Interchange Project

Bobcat Installs Innovative Stationary Fuel Cells From HyAxiom at Two of Its Facilities


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA