List Your Equipment  /  Dealer Login

Spanning the Potomac: Three-Quarter-Billion-Dollar Bridge Replacement Under Way

Thu June 17, 2021 - Northeast Edition #13
Brenda Ruggiero – CEG Correspondent


 Columns rise from the water at Pier 46. Pile driving continues at Pier 41. Aerial view of onsite concrete batch plant. The Virginia approach roadway construction. The concrete transport barge moves into position. View from the Maryland Bridge Abutment. Crews install rebar at Pier 46. Pier 55 footing placement. Tandem pick of footing tub at Pier 44.

The construction of a new Potomac River crossing from Charles County, Md., to King George County, Va., is well under way for the Maryland Transportation Authority (MDTA).

Thousands of Marylanders depend on the Nice/Middleton Bridge daily for work, business and recreation. With one narrow lane in each direction, problems include frequent congestion and traffic issues.

Funding for the construction of the new bridge was announced on Nov. 21, 2016, by Maryland Gov. Larry Hogan, who noted that the completion date would be seven years sooner than the legislatively mandated plan.

"With this announcement, I am extremely proud to officially dedicate more than $760 million dollars to fully fund a new Potomac River bridge and finally replace the Governor Harry W. Nice Memorial Bridge," said Hogan.

"From the start, our administration has consistently taken every step necessary to expeditiously push forward with this much-needed replacement project and going forward we will continue to push to ensure it's completed as fast and efficiently as possible. Simply put, Marylanders deserve better than the daily congestion caused by the current bridge and with the construction of this new bridge, they will finally get it."

The new bridge is being built north of and parallel to the existing 1.7-mi. bridge and will include two lanes of traffic in each direction and a barrier-separated bicycle and pedestrian path.

MDTA was able to reduce the initial $1 billion price tag of the project by more than $200 million by taking a practical design approach to the new bridge.

"By right-sizing the bridge design, we're able to deliver an affordable new bridge and do it years sooner," said Transportation Secretary and MDTA Chairman Pete K. Rahn.

The new span reportedly will have a 100-year service life. It will double the vehicle capacity with four 12-ft.-wide lanes, replacing the old bridge's two 11-ft.-wide lanes. In addition, safety will be improved by the installation of a barrier-separated median between east- and westbound lanes, the addition of 2-ft. shoulders and other improvements that meet current safety standards.

Lane-shifting safety issues at toll booths will be eliminated by replacing them with all-electronic tolling. Tall ships will be able to pass beneath its 135-ft. clearance.

Notice to proceed for the $462,957,000 design-build construction project was given on March 17, 2020, and the start of major construction (pile driving) was on July 17.

Plans are to have the bridge open to traffic in early 2023.

According to John Sales, public affairs manager, all of the MDTA's projects and services are funded through tolls paid by the customers who use the MDTA's facilities.

The MDTA is self-sufficient and receives no gas tax, motor vehicle fees or other revenue in the Transportation Trust Fund. The MDTA facilities are fully financed, operated, maintained, improved and protected with toll revenues paid by customers using those facilities.

The project is a joint design-build venture with Maryland ties: SKANSKA USA CIVIL (65 percent), Corman-Kokosing (20 percent) and McLean Contracting (15 percent).

The Skanska-Corman-McLean (SCM) Joint Venture Project Director is Thomas Fulton and the Maryland Transportation Authority (MDTA) Project Director is MDTA Director of Project Development Brian Wolfe.

Sales reported that the SCM team comprises three of the largest local marine contractors in the Chesapeake Bay region, with both local and national experience building complex bridge projects over water.

"Completed in 1940, the existing bridge is structurally reaching the end of its useful life," Sales said. "The new span's four, 12-foot-wide lanes with two-foot shoulders will double capacity and improve safety, while enhancing emergency response and maintenance/inspection activities."

The Harry W. Nice/Senator Thomas "Mac" Middleton Bridge project replaces the existing 1.9-mi., two-lane continuous truss bridge that carries U.S. 301 over the Potomac River and connects Charles County, Md., to King George County, Va.

The project will provide a new, four-lane span that will be aligned with the existing roadway approaches in Maryland and Virginia.

According to Sales, the design leveraged a combination of prestressed concrete girders in the low- and high-level approach spans with haunched steel girders over the main channel. The substructure and foundations vary from pile bents to concrete columns and caps on waterline footings.

The full scope includes roadway design and construction, structural design and construction of the replacement bridge and any and all other incidental structures specifically required for this project and hydraulic analysis, design, approvals and construction. It also includes temporary and permanent signing, lighting and pavement marking design and construction; roadside landscape planting; stormwater management landscape planting; coordination, design and construction of utility relocations; pavement engineering; geotechnical engineering; subsurface exploration; storm water management design, approvals, construction and as-built certification; and erosion and sediment control design, implementation and approvals (including NPDES approvals).

Also in the contract are engineering studies and reports required to meet the contract or permit requirements or to address any comments from MDTA or other agencies related to meeting or modifying the contract or permit requirements; general coordination with MDTA; additional data collection (including surveying, geotechnical, etc.); environmental compliance and permit activities (including obtaining permits as described in the contract and implementing mitigation measures); community relations and public outreach; traffic control design, implementation and maintenance including the preparation of a transportation management plan; maintenance of project site(s) including mowing, watering and dust control; and obtaining all required permit modifications from the appropriate regulatory agencies for any additional impacts to roadside trees, stormwater management, erosion and sediment control, or any other impacts not authorized by the original permits and approval.

Implementation of any required mitigation or remediation for additional impacts not included in the permit or due to any non-compliance with the permit conditions are also included, as well as ITS design and construction; electronic tolling related work and demolition of the existing Nice/Middleton Bridge.

"Construction on the water is a dynamic environment that presents significant opportunities and unique challenges unlike those associated with land-based construction," Sales said. "The risk and complexity of working in the water are heightened by the project's two-mile length and water depths of up to 80 feet. Notwithstanding, safe execution of every element of work is always our top priority."

He noted that the project was established with an aggressive construction schedule in order to open the new bridge in early 2023.

"Construction began in March of 2020 at the onset of the COVID-19 pandemic," he said. "A year into construction, we're on pace to meet our deadline."

Sales stated that operationally, another challenge is boaters speeding through the work zone, throwing off large wakes that put workers in danger.

"Due to a proactive campaign led by MDTA and through cooperation and partnership with the Maryland Department of Natural Resources and the United States Coast Guard, we've successfully established a six-knot speed limit half a nautical mile north and south of the project," he said. "The team has worked with marine law enforcement agencies to establish a police presence on the water and implemented a multifaceted ‘Make No Wake' public education campaign to help keep bridge construction workers safe throughout the corridor."

Sales stated that the project is currently the largest bridge project in the state of Maryland.

"The project is unique in that this two-mile long bridge spans two state lines, which requires collaboration and cooperation from two state and local government agencies and many additional stakeholders such as utility providers," he said.

The construction is unique in that the bridge provides a navigable main channel envelope, which provides 135 ft. of vertical clearance in deep water areas for tall ships navigating the Potomac River.

Materials from the demolished bridge will be used to create an artificial fish reef. In addition, MDTA and SCM are partnering with the Potomac River Fisheries Commission and Maryland Department of Natural Resources to fund oyster seeding in the lower Potomac River basin.

The first of 33 pier footing bathtub forms was set on March 3. Nicknamed "bathtubs" because they create giant tubs when placed, the form was lifted by a high-capacity floating crane from a barge and placed atop a set of previously-driven piles.

Following the crane movement, the bathtub was lowered into its final position and supported by hanger system. Next, the holes in the tub were sealed and filled with rebar and concrete to serve as a platform for bridge columns rising from the river to support the deck of the future bridge.

Form-placing work started in mid-February and will finish by the end of the summer. The forms weigh as much as 195 tons (the weight of 135 average-weight cars) and measure 30 ft. wide by as long as 52 ft. (the size of a small house).

The bathtubs serve as the bottom and side forms for pile caps that will support the columns of the new bridge. Within the tubs, construction of the pile caps involves setting steel rebar cages and pouring concrete to complete the foundations. This innovative forming method reduces both construction time and environmental impact as compared with traditional cofferdam construction that has been used to build bridges for centuries.

There are currently 16 cranes on site for the project, with 14 of them on the water. Additional cranes are anticipated over the coming months.

The largest crane, an 888 Ringer, has a lift capacity of more than 500,000 lbs.

There are six tugboats, one crew boat and nine passenger boats assigned to the project.

It also includes 26 football-field sized barges that are used for concrete placement, lay down, materials delivery and other jobs.

Various earthwork equipment also is being used and 60,000 cu. yds. of concrete is being batched on site.

Total steel, both reinforcing and structural, totals 18 million lbs., which is equal to 4,378 average-weight cars, according to the USEPA 2020 Automotive Trends Report.

Major subcontractors on the job include Coastal Precast for foundations, waterline footings, drainage troughs and girders; DT Read for rebar and stay-in-place forms; Interlock Steelworkers for girder erection; Chaney Enterprises for concrete supply; Bryant-Ritter Hewitt Electric Corporation for electrical and Intelligent Transportation Systems; and RN'G Construction for project-wide signage.

The project includes a large number of cranes that are a mix of owned and leased. Some of these include a Manitowoc 888 Ringer, CJV owned; two Manitowoc 4100 Ringers, CJV partner owned; two Liebherr LR1300 300T crawlers, CJV partner owned; a Manitowoc 14000, CJV partner owned; a 140T Whirley, CJV partner owned; two Liebherr LR1200 275-ton crawler cranes, leased from Bay Crane; a Liebherr LR1160 160-ton crawler crane, leased from Bay Crane; and two Manitowoc 999 cranes, leased from WO Grubb.

Six tugboats are leased, one crew boat is leased, nine passenger boats are a combination of owned and leased, and 31 barges are a combination of owned and leased.

The project employs roughly 500 employees including MDTA, SCM and subcontractors and suppliers.

Due to the location of the bridge, the project includes its own dedicated concrete batch plant. Concrete is transported from a Treyco Dry Batch Plant capable of producing up to 175 cu. yds. per hour and mixed in trucks before being deposited onto a series of conveyor systems that transport the concrete from land to water.

Concrete from the conveyors is placed into a series of transport barges, each outfitted with six agitators capable of carrying 90 cu. yds. of concrete. These transport barges are then moved out to the point of placement, where the concrete is transferred into a remixer and then pumped through a placing boom to the intended final location.

This project is anticipated to support an estimated 1,180 jobs per year over five years. CEG




Today's top stories

Blalock Crews Build TDOT's $67M Newport Bypass

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Equip Expo's Summer Giveaway Offers a Chance for Lifetime Trade Show Registration, Gift Card, Hotel Stay

Tennessee's Pugmill Systems LLC Expands Its Product Offerings to Include Concrete Plants

ASCENDUM Machinery Opens New Savannah, Ga., Facility


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA