List Your Equipment  /  Dealer Login

State Sees 'Roads to Prosperity' Fire Up Coalfields Expressway Project

Wed July 31, 2019 - Northeast Edition
Brenda Ruggiero – CEG Correspondent


More than 100,000 ft. of surface drainage pipe (free drain base trench and outlet pipe) will be installed. In addition, more than 228,000 ft. of striping will be completed and more than 104,000 cu. yds. of concrete will be installed.
More than 100,000 ft. of surface drainage pipe (free drain base trench and outlet pipe) will be installed. In addition, more than 228,000 ft. of striping will be completed and more than 104,000 cu. yds. of concrete will be installed.
More than 100,000 ft. of surface drainage pipe (free drain base trench and outlet pipe) will be installed. In addition, more than 228,000 ft. of striping will be completed and more than 104,000 cu. yds. of concrete will be installed. The project is unique in the fact that it will complete several miles of expressway involving mountainous terrain by utilizing concrete pavement.  
 Kokosing Construction Company is the contractor for the project, for a dollar amount of $33,234,283.51. According to the Coalfields Expressway website, the project’s purpose is to provide a multi-lane expressway connecting I-64/I-77 (the WV Turnpike) at Beckley, W.Va., and U.S. 23 at Slate, Va. A paving project on the Coalfields Expressway in West Virginia began at the end of February. The project involves a nearly 9-mi. stretch of road between Mullens, which is in Wyoming County, and Slab Fork, which is in Raleigh County. The contractor will have a batch plant setup on the project.

A paving project on the Coalfields Expressway in West Virginia began at the end of February. It involves a nearly 9-mi. stretch of road between Mullens, which is in Wyoming County, and Slab Fork, which is in Raleigh County.

Kokosing Construction Company is the contractor for the project, for a dollar amount of $33,234,283.51.

It is estimated that the project will be completed by Oct. 25, 2019. The bid date was Sept. 18, 2018. The contract was awarded on Oct. 2 and notice to proceed was given on Oct. 30.

Kokosing personnel includes Jon Turton, project superintendent, and Daniel Balser, project engineer. The WVDOH project supervisor is Joe A. Pack.

"This is a nonreinforced concrete paving project," said Terra L. Goins, West Virginia Division of Highways, assistant district engineer, construction. "The contractor will cut the existing roadbed of Coalfields Expressway to final grade and install concrete pavement from Slab Fork to Mullens."

In addition, she noted that some surface drainage will be installed or cleaned and the signage, guardrail and markings will be installed.

"Challenges include final grading of the mass earth jobs that have been completed previously; and as with all construction jobs, weather could become a challenge in installing the concrete to complete the job on time," Goins said. "There also will be some coordination that will need to take place between the contractors who are completing the exiting project and the current project."

She noted that the project is unique in the fact that it will complete several miles of expressway involving mountainous terrain by utilizing concrete pavement.

"It has been a few years since we have utilized concrete paving for a section of roadway within the District," she said.

Goins explained some of the background of the project, which started in Feb. 2017 with West Virginia Gov. Jim Justice kicking off the "Save Our State Tour" at the beginning of the Coalfields Expressway Project to explain his vision for West Virginia's roadways.

"He said at the time that he would build the road if the state would go with him," Goins said. "The state voted in October for the governor's Roads to Prosperity Program. It is exciting to see Governor Justice's vision come to fruition. Governor Justice, DOT Secretary Tom Smith, the Coalfields Expressway Authority [executive director Richard Browning], many engineers, contractors and WVDOH personnel have worked tirelessly in an effort to see this section open for the public use. It is scheduled to be completed this year. The governor's leadership with the Roads to Prosperity Program made the funds available to allow the culmination of years of work on this section of the Coalfield's Expressway to be completed."

The project will involve 8.86 mi. of mainline. This includes four lanes, covering five previous mass earth jobs, along with 1.01 mi. of two lane for the Mullens Connector portion.

More than 100,000 ft. of surface drainage pipe (free drain base trench and outlet pipe) will be installed. In addition, more than 228,000 ft. of striping will be completed and more than 104,000 cu. yds. of concrete will be installed.

Goins reported that no subcontractor requests have been received to date.

Major equipment for the job includes a Cat 335 excavator; Cat 740 and 745 articulating trucks; a Cat 16H grader; a Cat D8 dozer with GPS grade control; a Cat D6N dozer with GPS grade control; a sheeps foot roller; and a belly pans and scrapers.

She noted that the contractor will have a batch plant setup on the project.

"I am excited to have the opportunity to be a part of the governor's vision for the Coalfields Expressway construction project and to see this section of roadway utilized by the public," she said.

According to the Coalfields Expressway website, the project's purpose is to provide a multi-lane expressway connecting I-64/I-77 (the WV Turnpike) at Beckley, W. Va., and U.S. 23 at Slate, Va. It will be about 65 mi. long in West Virginia and 50 mi. long in Virginia, providing a corridor through the Appalachian Mountains.

The need for the expressway reportedly involves existing roadway conditions, safety and economic opportunities. CEG




Today's top stories

Crews Complete Covington, Georgia Community Project

Volvo Trucks Continues Electromobility Leadership: Ten New Locations Join Certified EV Dealership Network

Chicago Bears Announce Plans for New Enclosed Stadium

North Causeway Bridge Offers Innovation, Congestion Relief for Fort Pierce, Fla., Motorists

VIDEO: Connecticut Officials Celebrate Rapid Reopening of I-95 Bridge After Destructive Fire

Hundreds of Communities in Massachusetts to Benefit From $375M in Infrastructure Funds

Boston's Transit, Bicycle Riders Likely to Get More Space On Back Bay Streets in 2024

ProLift Rigging Company Opens New Full-Service Branch in Northern Virginia


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA