List Your Equipment  /  Dealer Login

Foundation Work Complete on $136.6M Iowa Courthouse

Wed April 29, 2020 - Midwest Edition #9
Lori Tobias – CEG Correspondent


Foundation work on a new $136.6 million federal courthouse in Des Moines is under way.
Foundation work on a new $136.6 million federal courthouse in Des Moines is under way.
Foundation work on a new $136.6 million federal courthouse in Des Moines is under way.
 Excavators, loaders, dozers, graders, rollers and dump trucks are being used on the project.
 Contractors broke ground on the project last August, with anticipated completion set for fall of 2022. Augered pier work is complete with pile cap installations. Early work packages for the deep footings and site utilities was started in March. Set on the west bank of the Des Moines River, the 229,000-sq.-ft., 6-floor building will replace the existing U.S Courthouse and a leased courthouse annex in downtown Des Moines.

Foundation work on a new $136.6 million federal courthouse in Des Moines is under way with augered pier work complete and pile cap installations and early work packages for the deep footings and site utilities started in March.

Contractors broke ground on the project last August, with anticipated completion set for fall of 2022. Set on the west bank of the Des Moines River, the 229,000-sq.-ft., 6-floor building will replace the existing U.S Courthouse and a leased courthouse annex in downtown Des Moines. It will provide nine courtrooms and 13 chambers and will house:

  • The Southern District of Iowa Judiciary
  • Southern District of Iowa Bankruptcy
  • U.S. Probation and Pretrial Services
  • U.S. Marshals Service
  • Eighth Circuit Court of Appeals, including a satellite library
  • GSA building management space
  • Trial preparation space for the Federal Public Defenders and the U.S. Attorneys

The building features cast-in-place concrete, precast concrete panels and glass and will incorporate "the latest requirements for sustainability, operational excellence, and state-of-the-art security and communication technology," said Alison Kohler, regional public affairs officer of U.S. General Services Administration. "The building is designed and constructed to achieve a LEED Gold level certification."

Mack Scogin of Merrill Elam Architects in Atlanta, in a joint venture with Neumann Monson Architects of Des Moines, is the design team for the project. Jacobs Technology was awarded the contract for construction manager as Agent.

Amenities include the use of natural light through public spaces and public artwork commissioned specifically for the project.

In addition to many pieces of light equipment, most of the equipment on site is for earthmoving activities, Kohler said.

"These include excavators, loaders, dozers, graders, rollers and dump trucks. There will be at least one tower crane for the project," she said.

One of the biggest challenges of the project was finding a site and maintaining public support, Kohler said. The GSA worked with the community by sharing its progress and plans, engaging in regular conversation and moving forward with the public toward the project completion.

The courthouse will sit on a vacant lot previously occupied by the YMCA, which was demolished in 2015. The GSA purchased the lot for $6.5 million.

John Jarvey, chief judge of the Southern District of Iowa, said there had been an exhaustive search but some prospective sites were eliminated because they were priced far above the appraised value, according to the Associated Press.

"The riverfront site is outside the floodplain, environmentally clean and ready to build on," Jarvey said. "This project deserves this place in the community. It's an important community function and this is the right site for the federal courthouse."

The next milestone on the project is the selection of artists for the Art in Architecture program.

"The GSA Art in Architecture Program oversees the commissioning of artworks for new federal buildings nationwide," according to the GSA website. "These artworks enhance the civic meaning of federal architecture and showcase the vibrancy of American visual arts. Together, the art and architecture of federal buildings create a lasting cultural legacy for the people of the United States.

"GSA reserves one-half of one percent of the estimated construction cost of each new federal building to commission project artists. A panel composed of art professionals, civic and community representatives, the project's lead design architect, and GSA staff meets to discuss opportunities for artists to participate in the building project. This panel reviews a diverse pool of artist candidates and nominates finalists for GSA to evaluate. Artists who receive federal commissions work with the project architects and others as members of a design team to ensure that the artworks are meaningfully integrated into the overall project." CEG




Today's top stories

Demolition Crews Bring Down Largest Span of Baltimore's Collapsed Key Bridge

Webber Working to Complete $300M Texas Interchange Project

Value in Remanufacturing Construction Equipment: Reduce Cost, Downtime, Carbon Footprint

Flo Engineering Restoring Access to Critical Highway in California

Volvo Masters Crowns Its Winners

Why a Robust Attachment Portfolio Can Enhance Your Versatility, Expanding Job Opportunities

ADOT Dedicates I-10 Tunnel to Late Engineer Dean Lindsey

Meta Plans to Build $800M Next-Generation Data Center in Montgomery, Ala.


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA