Gulfport Eyes Major Tourism Boost With $93M Aquarium

Mon August 27, 2018 - Southeast Edition #18
Cindy Riley – CEG Correspondent


The aquarium property consists of multiple parcels of land acquired by the city of Gulfport specifically for construction of the new aquarium campus. One piece of property was occupied by a church, while another featured a bar/restaurant. An old Masonic Lodge still sits on the northwest corner of the land, and is set to be demolished at the end of the project. It currently serves as a construction office. (Roy Anderson Corp photo)
The aquarium property consists of multiple parcels of land acquired by the city of Gulfport specifically for construction of the new aquarium campus. One piece of property was occupied by a church, while another featured a bar/restaurant. An old Masonic Lodge still sits on the northwest corner of the land, and is set to be demolished at the end of the project. It currently serves as a construction office. (Roy Anderson Corp photo)
The aquarium property consists of multiple parcels of land acquired by the city of Gulfport specifically for construction of the new aquarium campus. One piece of property was occupied by a church, while another featured a bar/restaurant. An old Masonic Lodge still sits on the northwest corner of the land, and is set to be demolished at the end of the project. It currently serves as a construction office. (Roy Anderson Corp photo)
 The world-class $93 million Mississippi Aquarium will serve as a major tourist attraction when it opens in Gulfport in early 2020. (PGAV Destinations rendering) The notice to proceed was issued in late January 2018, with work starting shortly thereafter. (Roy Anderson Corp photo)
 There are so many elevation changes throughout the property that grading will be key to make sure the site drains like it should, and doesn’t affect the animals. (Roy Anderson Corp photo) At the end of the day, contractors will have just under 1,000 yds. of dirt to actually remove from the project, according to RAC senior project manager Geoffrey Knesal. (Roy Anderson Corp photo) Multiple cranes are being used on the project for driving piles, working on the main building and constructing smaller support buildings and exhibits. Workers also are using forklifts, track hoes, backhoes, bulldozers, mini-excavators, dirt packers, fusion machines for life support systems pipe and man lifts. (Roy Anderson Corp photo) Many hours are spent on inspections, coordination meetings and calls, etc. to ensure construction is not only per plans and specs, but also as the ownership group requires it to be. (Roy Anderson Corp photo) The aquarium design team includes Mississippi-based Eley Guild Hardy Architects and PGAV Destinations of St. Louis, Mo. Roy Anderson Corp (RAC) is serving as the project’s general contractor. (Roy Anderson Corp photo) A custom transparent tunnel is surrounded by water and a large viewing window. The tunnel is supported by a cast-in-place ledge that it rests on and there are massive steel and concrete supports on the inside floor and above the top of the tunnel to keep it from floating up to the top of the tank, when the tank is filled with water. (PGAV Destinations rendering) A unique item to be installed at the main entry of the property consists of three sail icons that will be the trademark image of the new facility. (PGAV Destinations rendering)

As the future home to alligators, river otters, river fish, dolphins, stingrays and shorebirds, the world-class $93 million Mississippi Aquarium will serve as a major tourist attraction when it opens in Gulfport in early 2020. Containing one million gallons of both salt and fresh water and sitting on 5.8 acres, the aquarium will feature more than 80,000 sq. ft. of exhibits, and was designed to create an appreciation for the coastal environment through interactive learning programs.

“Mississippi Aquarium is bringing the sights, sounds and vibrant wildlife of Mississippi and beyond to the Mississippi Gulf Coast,” said David Kimmel, president and CEO of Mississippi Aquarium. “Our mission revolves around three pillars — education, conservation and community. These three values are applied to every aspect of Mississippi Aquarium.”

Kimmel noted that the highly anticipated structure will serve many purposes.

“Mississippi Aquarium's impact will be transforming by attracting visitors, being a catalyst for private sector development and job growth, promoting and enhancing marine research and creating educational awareness. Our community leaders see Mississippi Aquarium as the lynchpin to other projects being developed in downtown Gulfport.

“Mississippi Aquarium will be an iconic landmark symbolizing the resilience of the people of the Mississippi Gulf Coast and the commitment of Gulfport's City leaders to its continued growth and development.”

Those involved in the planning believe the new aquarium will elevate Gulfport, the Mississippi Gulf Coast and the state to a family-friendly premier tourism destination.

Significant private sector development from hotels, entertainment and restaurants would be attracted, benefiting all of Mississippi for many years, Kimmel said, citing Chattanooga, Tenn., as an example of significant private sector development that follows an aquarium investment.

The acrylic panels for Mississippi Aquarium, the windows to the habitats, recently arrived from overseas. They are currently being stored at the Port of Gulfport, awaiting installation.

With so many features, one of the most anticipated additions, according to Kimmel, will be the tunnel.

“This is a clear acrylic tube our visitors will walk through while viewing marine mammals. I'm also excited about our large viewing window, which is approximately 32 by 25 ft. and 16 inches thick, and weighing more than 40 tons. It will allow our visitors to see the complete strata of the gulf, portraying animals from the gulf and beyond.

“Mississippi Aquarium's 12 habitats are designed in a campus environment where visitors will be surrounded by both indoor and outdoor habitats. The aquarium's landscape will contain over 50 different species of plants and represent native plant species from all seven physiographic regions of Mississippi.”

The aquarium's exterior habitats will be 1,600 ft. long, the equivalent of four-and-a-half football fields. The landscape will be a natural food source for birds and butterflies. In addition, every drop of water will be filtered 16 times per day.

Hundreds of jobs are being created during construction, with more than 100 aquarium employees on staff once work is complete. With an average 487,000 visitors expected each year, the facility will reportedly be self-sustaining, and operate at no cost to the taxpayer, upon opening. Kimmel said it's extremely rewarding to see construction under way, knowing that crews are making steady progress.

“Every day, I see all of our hard work get a little bit closer to reality,” he said.

Kimmel added there is still much to be done before the ribbon can be cut.

“Constructing the aquarium is only one piece of bringing it to life. Right now, our staff is finalizing our animal acquisition plans and writing all of the policies and procedures necessary not only to operate the aquarium, but to do so in accordance with the various accreditations we will be seeking from the Association of Zoos and Aquariums, Alliance of Marine Mammal Parks and Aquariums, International Marine Animal Trainers' Association and America Humane.”

The aquarium design team includes Mississippi-based Eley Guild Hardy Architects and PGAV Destinations of St. Louis, Mo. Roy Anderson Corp (RAC) is serving as the project's general contractor. According to RAC senior project manager Geoffrey Knesal, the work being carried out is far from routine.

“This is very specialized, including many details and methods not used on normal, general construction. Quality is of the utmost importance, since some structures will be retaining hundreds of thousands of gallons of water. The life-support systems are critical, as well, since these are the systems that will be keeping the aquatic life alive during operation.”

The notice to proceed was issued in late January 2018, with work starting shortly thereafter. Deep pile foundations, dirt work and storm drainage activities have already been completed. Main building shallow foundations also are finished. Currently, cast-in-place concrete structures are being built, and underground life-support systems piping is being installed.

The aquarium property consists of multiple parcels of land acquired by the city of Gulfport specifically for construction of the new aquarium campus. One piece of property was occupied by a church, while another featured a bar/restaurant. An old Masonic Lodge still sits on the northwest corner of the land, and is set to be demolished at the end of the project. It currently serves as a construction office.

Early work involved building the waterfront property's elevation from 18 to 25 ft. As part of an early release package, a separate contractor mobilized and completed some site utility and storm drainage infrastructure.

“They also brought in thousands of yards of clay to surcharge the site, in preparation for the loads/weights of the new construction,” said Knesal. “After settlement was achieved and the ground was stable, the same contractor removed some of the dirt that was brought in to get the top of the building pads to 25-feet elevation. We began construction from that point.”

So far, weather has not been much of a factor.

“A certain number of rain days are accounted for in each month, and to-date, we have not surpassed the allotted number of rain/weather days per month, so weather has not adversely affected the schedule. Anything is possible in South Mississippi, though, so we continue to monitor rain/weather days, and provide a report at the end of each month.”

According to Knesal, finishing the main exhibit building's structure will be a major milestone.

“The entire structure is cast-in-place concrete. Once that is complete, it will allow many more trades to begin work in this main building. Permanent power is always a big milestone, as well, and is set to occur in spring 2019.”

According to Knesal, one of the construction challenges involves the custom transparent tunnel surrounded by water and a large viewing window.

“The tunnel is unique in that there is not another aquarium in the country where guests can walk through the middle of a tank with water on all sides of them. Some aquariums have tunnels on the ground level, but none that are suspended where water is on top, bottom and both sides of the guest as they walk through the middle of the tank.

“The tunnel is supported by a cast-in-place ledge that it rests on. There are also massive steel and concrete supports on the inside floor and above the top of the tunnel to keep it from floating up to the top of the tank, when the tank is filled with water. The cast-in-place walls must be completed first, then the cast-in-place ledge will be completed. Then, the acrylic tunnel will be brought in and set on the ledges with a crane through the roof of the main building.”

Knesal noted that crews cannot complete the roof until the acrylic is all set.

“Then we have to build a cast-in-place/steel ledge above the tunnel to keep it from floating up. Lastly, two 3,000-pound plates must be brought in and set at each end of the tunnel and bolted to the floor to keep the bottom from floating up and 'pancaking' against the top of the tunnel. Engineering and installation of these tunnel supports has probably been the most difficult single item we have experienced yet on the project.”

A lot of grading will be performed at the end of the project.

“There are so many elevation changes throughout the property that grading will be key to make sure the site drains like it should, and doesn't affect the animals,” said Knesal, adding, “at the end of the day, we have just under 1,000 yards of dirt to actually remove from the project. This is due to all of the dirt we are displacing when digging foundations and deep exhibit pools.”

Multiple cranes are being used on the project for driving piles, working on the main building and constructing smaller support buildings and exhibits. Workers also are using forklifts, track hoes, backhoes, bulldozers, mini-excavators, dirt packers, fusion machines for life support systems pipe and man lifts.

As for some of the main materials being utilized, “There's a lot of concrete being used for this project, approximately 8,000 yards. The smaller buildings are using concrete masonry units [CMU], structural steel, steel joists and decking and metal studs for their structures. The exteriors of the buildings are either metal panels or stucco. Interiors will consist of metal stud framing and drywall with wall tile or paint finishes on the walls. Floor finishes include VCT, carpet, sealed concrete, polished concrete, hard tile, and fluid-applied flooring.”

Knesal said attention to detail is critical during construction.

“Quality has been a very important part of the work. When dealing with water retaining structures that support actual life, everything must be perfect, or it puts the lives of the animals in danger. A lot of additional time has been spent making sure all components are installed as the construction documents call them to be installed.

“Many hours are spent on inspections, coordination meetings and calls, etc. to ensure construction is not only per plans and specs, but also as the ownership group requires it to be, since they will be operating the facility after we leave and will ultimately be responsible for the lives of the animals. The ownership team provides a lot of knowledge on how some things need to be installed that may not be reflected in the actual construction documents, which helps our team with the end goal of turning over an aquarium facility that operates exactly as the owner needs it to.”

A unique item to be installed at the main entry of the property consists of three sail icons that will be the trademark image of the new facility.

“These sails will be built in descending height, with the tallest standing approximately 65-feet tall, which is 90 feet above sea level, since these will sit at elevation 25 feet. It was very important to the ownership team and the mayor of the city of Gulfport, to create a structure that will stand as the defining symbol of the Mississippi Aquarium for many years to come. These sail icons will have their own deep-pile foundations, with a very large cast-in-place pile cap. They will sit in a pool of water as guests enter the property, and will look like sailboat sails full of wind.”

As crews make progress each day, momentum continues to build.

“Locally to the Mississippi Gulf Coast and statewide, people are asking daily, 'How soon will it be opening?'” said Kimmel. “The community is extremely supportive. Not only are they excited about the aquarium, but how it's already impacting the economic development in Gulfport.”

(This story also can be found on Construction Equipment Guide's website at www.constructionequipmentguide.com.)




Today's top stories

Growing Interest in Construction Careers Among Younger People Means Jobs Filled, Deadlines Met

Larry Young Paving Tackles Grade-Separated Interchange in Texas

Caltrans, Crews Working to Repair Highway Landslides

FIRSTGREEN Industries Launches ROCKEAT Electric Skid Steer Loader

'Tiltrotator Effect' Increases as Energy Consumption Goes Down

VIDEO: Birmingham, Ala., Awarded $14.5M Fed Grant to Revitalize Its 'Black Main Street'

Pettibone Celebrates 75th Anniversary of Cary-Lift

Fay Preps Way for Pittsburgh International Airport Modernization Project


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA