Rhode Island Department of Transportation (RIDOT) crews have been busy working on various projects across the state. Here is a pictorial roundup of some of these recent projects.

Workers are installing new catch basins and drainage pipes, and continue demolition of old Carolina Bridges components in Charlestown/Richmond.
Workers are installing new catch basins and drainage pipes, and continue demolition of old Carolina Bridges components in Charlestown/Richmond.  

Workers install drainage pipes, catch basins and electrical conduit.
Workers install drainage pipes, catch basins and electrical conduit.  

Crews install new curbing, perform drainage work and make electrical upgrades for LED lighting around the roundabouts on Diamond Hill Road, from Industrial Road to Bear Hill Road and Angell Road.
Crews install new curbing, perform drainage work and make electrical upgrades for LED lighting around the roundabouts on Diamond Hill Road, from Industrial Road to Bear Hill Road and Angell Road.  

RIDOT crews recently worked on replacing the Lafayette Road South bridge.
RIDOT crews recently worked on replacing the Lafayette Road South bridge.  

Crews were busy prepping parts of the old Baker Pines bridge in Richmond for concrete repair and replacement on Route 3 under I-95 and finishing median barrier work.
Crews were busy prepping parts of the old Baker Pines bridge in Richmond for concrete repair and replacement on Route 3 under I-95 and finishing median barrier work.  

Crews install guardrail and plant grass behind a barrier on Route 102.
Crews install guardrail and plant grass behind a barrier on Route 102.  

RIDOT crews are scheduled to relocate the temporary median barrier from the Cowesett Road overpass to Exit 11 in Warwick.
RIDOT crews are scheduled to relocate the temporary median barrier from the Cowesett Road overpass to Exit 11 in Warwick.  

Route 6/10 Interchange Reconstruction, Providence: crews continue building the retaining walls for the Route 10 North to Route 6 West flyover bridge approach, performing utility work on Westminster Street over Route 10, and forming and pouring the concrete bridge barriers on the Plainfield Street Bridge on Route 6 East.
Route 6/10 Interchange Reconstruction, Providence: crews continue building the retaining walls for the Route 10 North to Route 6 West flyover bridge approach, performing utility work on Westminster Street over Route 10, and forming and pouring the concrete bridge barriers on the Plainfield Street Bridge on Route 6 East.  




Today's top stories

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Muddy Water Dredging Christens Marlin Class Dredge

Indiana Officials Mark Start of 2024 Construction Season, Promote Safety

Leica Geosystems Launches its First Machine Smart Antenna — Leica iCON gps 120


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA