Historic Bridge Updated in Unusual Project

Wed June 13, 2012 - National Edition
Wilson Ring - ASSOCIATED PRESS


MONTPELIER, Vt. (AP) - A historic Vermont bridge is going to be updated with a technique that seems like something only a superhero could accomplish: Engineers will cut the 350-foot bridge in two lengthwise, push the two sides apart, widen them and put it back together.

As far as anyone involved in the project has been able to determine, it’s the first time such a technique has been tried on such a large bridge and after 15 months of preparation, engineers are now getting ready to separate the sides, move one 300,000-pound truss 10 feet away from the other and then reattach the sides. Once the steel and concrete has been added, motorists crossing the bridge won’t have to worry about meeting a truck coming the other way.

The so-called Pennsylvania truss bridge, which carries U.S. Route 2 across the Winooski River about 10 miles east of Burlington, was built in 1929, two years after an epic flood washed out a covered bridge there. The bridges are marked by the crisscrossing I-beams that form a latticework that creates a steel canopy above the road surface.

It was marvel of its time, but by the bridge’s 60th birthday in 1989, Vermont officials had recognized that it needed to be modernized. The two travel lanes were a total of 20 feet across, barely wide enough for two cars to pass; there is no shoulder, no room for bicyclists or pedestrians; and the steel and the supports were showing their age.

“I travel that road every day, twice a day,” said Vermont Transportation Structures Project Manager Carolyn Carlson, who started working on the Richmond bridge in 1989. “Driving on it before when it was 20 feet (from) rail to rail, you’d find it very nerve-racking.”

Still, state and federal officials wanted to keep the historic look of the bridge _ three such bridges are left in the state and the Richmond one is the only over on a major roadway. It took decades to decide on the unusual course of action.

The project’s cost, an estimated $16 million, is more than double that of building a new bridge. At first, officials were reluctant to undertake the more expensive option, but as time went on it became clear it could work.

“When you are dealing with a historic resource, you don’t look at it as extra money,” said Scott Newman, the historic preservation officer for the Vermont Agency of Transportation.

Two federal laws require that the significance of historic structures be taken into account when planning transportation projects as long as the alternative is “prudent and feasible,” Newman said.

“The bar for establishing whether something is prudent or feasible is very high,” he said. “There’s a thumb on the scale in favor of the preservation of the resource. We are very careful about that.”

It’s not clear who came up with the idea of cutting the bridge in two and widening it, said Carlson.

Construction on the project began in the winter with the installation of a temporary bridge. Now, the 1929 bridge is being supported by beams set in the river and the two sides are to be separated in the next few days. The downstream truss will slide on bearings, pulled and pushed simultaneously by a series of interconnected jacks.

The separating, winching and refastening is only supposed to take a day, but it will be another year before traffic is rolling again on the new bridge.

Over her 27 years at the Vermont Transportation Agency, Carlson estimated she’s overseen the construction of 100 bridges. But the Checkered House Bridge is special.

“The bridges that have the challenges are the unique ones. Everyone (engineers) has a bridge that they say, when it’s built, ’I can retire,’” she said.

This is hers, but she has no plans to retire just yet.




Today's top stories

Caltrans, Crews Working to Repair Highway Landslides

NAPA Urges Drivers to 'Watch For Us' During National Work Zone Awareness Week

Landscapers, Contractors, Dealers Can 'Test Before They Invest' in Equipment in Equip Expo's 30-Acre Outdoor Demo Yard

Terex Utilities Announces Availability of TL45 On Mini Tracked Carrier for Lifting in Restricted Access Job Sites

Arizona Chip Factory Will Expand With $6B in New Funds

John Deere Launches Nationwide Search for First-Ever Chief Tractor Officer

UDOT to Implement Digital Construction Technology

New $140M Biogas Facility for SacSewer Coming to Sacramento








aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA