List Your Equipment  /  Dealer Login

Link-Belt 298 Crane Logs 12,000 Hours at East Side Access Job

A Link-Belt 250 ton (226.79 t) 298 HSL lattice crawler crane gets the job done in a "tricky" situation.

Wed August 14, 2013 - National Edition
Link-Belt Cranes


A Link-Belt 250 ton (226.79 t) 298 HSL lattice crawler crane has logged nearly 12,000 hours at the East Side Access job site located in the Queens borough of New York City. The project will connect four tunnels running under the East River from Harold Interlocking in Queens, N.Y, west, to a new terminal located directly below the existing Grand Central Station in Manhattan.

"While excavation in the launch shaft took place, the material and dump body averaged about 50,000 pounds lbs. as we threaded the load through the struts. You have to understand, we have three levels of struts placed 15 ft. apart for trench support at this location. Through the struts we lowered a 100 ton truck crane, a PC600 large excavator and 45 ton rough terrain with the 298," said Kevin Dillon, operator engineer of G.T.F., a joint venture company created for the project. "Believe me, it was tricky, but the 298 worked well. In that type of situation you want control over the loads, and that is what we had."

In order to bore the four tunnels, a German built Herrenknecht 22 ft. 6 in. (6.8 m) diameter slurry tunnel-boring machine worked around the clock, boring more than 11,000 ft. (3, 352.8 m) in total for each of the four tunnels. The 298 kept the two Herrenknechts running to supply the two boring machines as they work during three, eight-hour shifts for seven straight months of non-stop boring. The boring units could not be stopped once boring commenced, so a non-stop schedule was required. This led to the 12,000 hours of logged time over a 22 month period.

The Link-Belt 298 proved to be a reliable rig during its constant use at the job site, according to the company. The crane lowers ventilation tubing, additional tracks for the Herrenknecht, pre-cast liner segments and electrical pipelines as much as 70 ft. (21.3 m) below ground. Some of the largest picks required of the 298 HSL came at the conclusion of the tunnel boring process when 110,000 lb. (49,895.2 kg) lifts were required. Using a five-part line, the crew and operator pulled out the 110,000 lb. (49,895.2 kg) trailing gear and a 98,000 lb. (44,452.1 kg) lift of duct work that swung 230 degrees for loading once at ground level.

The crew replaced the 1.1 in. (2.8 cm) auxiliary hoist line at 10,000 hours as a preventative measure. The crane was inspected every three months by the crew and also by the New York City Department of Buildings. The three companies that compose G.T.F. are Granite Construction in Watsonville, Calif.; Traylor Brothers in Evansville, Ind.; and Frontier-Kemper in Evansville, Ind. The three companies were contracted to build the $730 million Queens Bored Tunnels project with primary access from the busy, Harold Interlocking Yard.

Ron Albers, project equipment manager said, "We expect to use the 298 here for another 6 months before going to another job site."

This story also appears on Crane Equipment Guide.




Today's top stories

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

Volvo CE Continues to Perform, Transform During Slower Q1 2024

American Bridge Co. Leads Conn.'s East Haddam Swing Bridge Project

Pettibone Celebrates 75th Anniversary of Cary-Lift

Common Ground Alliance Hosts Conference & Expo in Colorado On Preventing Utility Damages

Going Beyond Diversity: Star Equipment's Rental Advantage

Volvo CE Launches Updated L30, L35 Compact Wheel Loaders


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA