Mich. Regulators Refuse to Grant Permit for Road Planned Near Mine

Thu January 17, 2013 - Midwest Edition
John Flesher - AP ENVIRONMENTAL WRITER


TRAVERSE CITY, Mich. (AP) Michigan officials said Jan. 3 they won’t grant a permit for a new road near a nickel and copper mine under construction in the Upper Peninsula because of federal regulators’ concerns about damage to wetlands and wildlife habitat.

The Marquette County Road Commission wants to build the 21-mi. (33.8 km)-long linkup between a rural road near the Rio Tinto Eagle Mine and U.S. 41. Rio Tinto originally sought the project, which would provide a convenient route for trucks hauling ore from the mine to a processing mill in Humboldt Township.

The project would affect nearly 26 acres of wetlands and require building 22 stream crossings, according to an application filed with the Michigan Department of Environmental Quality. The DEQ issues permits to fill wetlands under the federal Clean Water Act, but the U.S. Environmental Protection Agency can object — and did so in this case.

EPA said the Marquette commission should consider less harmful alternatives and that the local agency’s plan to compensate for ecological damage wasn’t adequate.

Construction of the road “would have significant direct and indirect impacts on high quality wetland and stream resources, as well as on wildlife,” Susan Hedman, administrator of EPA’s regional office in Chicago, said in a Dec. 4 letter to DEQ Director Dan Wyant that affirmed the opposition it initially raised last April.

Under the law, DEQ had 30 days after receiving the letter to satisfy the EPA. Wyant said the time frame was too short and the issues too complex to resolve them by the deadline, so his agency couldn’t issue the permit.

“It was a tough call,” Wyant told The Associated Press in a phone interview. While raising environmental risks, the project would promote economic development, public safety and access to outdoor recreation, he said.

“You try to balance all that,” he said. “We felt the applicant had reached that balance; EPA did not.”

The road commission could ask the U.S. Army Corps of Engineers to issue the permit, “but all indications are that [the road] will not be built,” Wyant said.

Rio Tinto spokesman Dan Blondeau said the DEQ’s decision will not delay development of the mine. Construction is scheduled for completion this year and production of nickel and copper should begin in early 2014, he said.

The decision on the road was disappointing, he said. “It was our preferred route, but we’re pleased to have certainty and clarity going forward.”

The company likely will transport its ores on an existing roadway network that runs along the northern end of Marquette before reaching southward to U.S. 41 west of town, he said.




Today's top stories

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Muddy Water Dredging Christens Marlin Class Dredge

Indiana Officials Mark Start of 2024 Construction Season, Promote Safety

Leica Geosystems Launches its First Machine Smart Antenna — Leica iCON gps 120








aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA