List Your Equipment  /  Dealer Login  /  Create Account

Questions Linger Over Release of Incentives for DeSoto Project

Wed June 20, 2007 - Southeast Edition
Construction Equipment Guide


HERNANDO, Miss. (AP) A June 1 deadline for developers to secure land and financing for the Riverbend Crossing project in DeSoto County has passed but there are questions whether requirements were met to qualify for $173 million in state incentives.

Officials with the Mississippi Development Authority were not saying whether the deadline was a major issue. There also was disagreement over exactly what the developer had to do before the deadline.

Phillips Development Co., of Newport Beach, Calif., expects to start moving dirt for $2.7 billion Riverbend Crossing before winter, officials said.

The 4,600-acre site is just north of Tunica County’s Casino Center. The project calls for a movie-themed entertainment park, hotels, golf courses and up to 9,500 homes spread around a series of lakes.

Two corporations, Entergy and Prudential, are the major players in the Riverbend deal, with area holdings exceeding 4,000 acres (1,618 ha).

Chris Gouras, a public finance consultant with the project, told The Clarion-Ledger newspaper that Phillips Development had spent approximately $7.5 million to acquire 60 acres near Walls. He said talks are ongoing on the remaining property.

Bill Phillips, the company president, told The Commercial Appeal newspaper that Riverbend backers believed the incentive bill passed by Mississippi lawmakers last summer did not mean they were to acquire the land and start construction by June 1.

Phillips said they believe the bill called for development to begin by June 1 and that requirement had been met.

“We’ve been moving ahead for six months hot and heavy,” Phillips said. “We’re excited about continuing on. Our goal is to start construction within the next 45 to 60 days.”

State Sen. Doug Davis, R-Hernando, who has pushed the project along with other community leaders, said, “Obviously, we all wish the project was further along than it is today, but we are where we are. I am satisfied this project is progressing.”

State Rep. John Mayo, D-Clarksdale, whose district includes part of the site, said he believed legislators intended for physical construction to begin by June 1.

“I’ve been told they’re moving dirt,” Mayo said June 1. “If they’re moving dirt, I feel like that would satisfy the deadline the Legislature set.”

The site is unpopulated, primarily planted in row crops, between U.S. 61 and the Mississippi River levee, just north of the Tunica County line.

Phillips said he spent the previous week with lawyers working on project financing.

“It’s a complicated process,” he said.

Phillips said he believes MDA officials “understand what we’re going through and all the work that’s under way.”

Davis said the “fall back” provisions that protect taxpayers remain intact — private capital must be invested before state incentives kick in.

“I would hate to see the state lose a project of this magnitude on a technicality. If they’re as close as I believe they are, I would hate to see them lose it on a technicality,” Davis said.




Today's top stories

DOT Pauses 'Buy America' Provision to Provide Relief to Already Strained Industry

Pennsylvania Contractor Takes Delivery of First Doosan DD100 Dozer

Wirtgen Slipform Pavers Bring Numerous Innovations, World Premiere to bauma 2022

Granite Tackles California Congestion Issue With $700M '101 in Motion' Project

Blanchard Machinery CEO, President Joe Blanchard Passes at Age 60

Alabama's Bank Independent to Build $60M, Four-Story Muscle Shoals Complex

Hitachi's Sam Shelton Retires After 27 Years With Company

Former Owner of Highway Equipment Company Dies, 84








ceg-logo ceg-logo ceg-logo ceg-logo ceg-logo
39.04690 \\ -77.49030 \\ Ashburn \\ VA