# Rebuilding U.S. 70 for Its Interstate Future

- **Published:** 2026-11-19
- **Edition:** Southeast
- **Source:** Construction Equipment Guide
- **Authors:** Larry Bernstein – CEG CORRESPONDENT
- **URL:** https://www.constructionequipmentguide.com/rebuilding-us-70-for-its-interstate-future/72826
- **Tags:** Arizona, Infrastructure, North Carolina

## Summary


## Article

U.S. 70 was developed in 1926 and is one of the original American highways. It runs nearly 2,400 mi. between Arizona and North Carolina.

The route passes through several of North Carolina's major cities, including the state capital, Raleigh, and connects two military bases. In addition to serving as a hurricane evacuation route, the road is used to move freight, carry vacationers to the Crystal Coast beaches and connect to rural areas.

A section of the route is being updated and will become Interstate 42 (I-42). To achieve that title, NCDOT is undertaking 16 projects to ensure the route meets the standards. One current project is in James City.

## Project Scope

Situated on the Neuse River in East-Central North Carolina, James City is bisected by U.S. 70. The current ADT on Route 70 in the area is 53,000, and it's projected to reach 68,000 in 2030. Trucks make up approximately 7 percent of the traffic, with much of the truck traffic traveling between Raleigh and the port in Morehead City.

The project covers a 5.1-mi. stretch of U.S. 70. Upon project conclusion, the stretch will be a “6-lane divided highway with a 46-ft. wide grass median and cable guide rail.”

The scope includes converting five “...conventional intersections into interchanges by taking U.S. 70 over these cross streets and providing access via ramps. These five interchanges will become new highway exits for the future Interstate 42.”

The team also is building and realigning service roads.

“Traffic will be able to use the service road that's adjacent to U.S. 70 eastbound and travel the whole length of the five-mile corridor and never get on the interstate,” Wendi Johnson, GFT resident engineer, told Construction Equipment Guide. “Westbound traffic will be able to do the same, but there are some historical areas that we can't go through, so the service road won't tie in completely.”

GFT is serving as the state's engineering inspector.

The scope also includes installation of multiple roundabouts. Johnson noted that traffic volumes are high enough that if traditional ramps were installed to enter that cross street, traffic signals would have been required. There are hurricanes in the area that can lead to power outages so not having to on power for traffic signals is very useful.

## Small Footprint

The Neuse River is north of the project, while the North Carolina Railroad is to the south.

“We were limited to the existing footprint, which includes significant commercial development,” Johnson said.

So, how can they increase the number of travel lanes (the scope includes adding ramp lanes)?

“Nothing could remain in place,” Johnson said.

Forty-one businesses have been relocated, and about 100 remain in the corridor.

Then, there are the utilities which had to be relocated. Johnson noted the site required the relocation of multiple power lines, gas, fiber optics, water and sewer.

The area also included twelve contaminated sites. The contamination stemmed from petroleum, pesticides, or dry-cleaning solvents.

“Depending upon what type of contaminant it is, a different remediation is required to address the issue,” Johnson said.

Part of the stormwater system is sealed because it's going through these contaminated areas.

The project has 22 wetland buffers, streams and other environmentally permitted areas. “Each of those sites requires specific ways that construction is done and erosion control is used to mitigate those sites,” Johnson said.

As part of the project, the team is installing 80,000 linear ft. of new storm drain and 1,000 storm drain boxes.

The area has highly compressible, unstable soils. Johnson and the team estimated it would take eight months to a year for settlement to occur, and they could build the overpasses.

The contractor, Balfour Beatty, used lightweight cellular concrete rather than traditional fill, which reduced the settlement time to just 90 days.

“Lightweight cellular concrete is a mixture of cement, water and a foaming agent, which sometimes includes fly ash,” said Johnson. “It creates a product that looks and feels like Styrofoam. It's used as a replacement for traditional borrowed dirt material. It's lighter than the traditional borrow material and therefore causes less settlement and it's similar in strength to dirt.”

The contractor had a batch plant on site.

“They brought the material in by tankers. After batching it, they extruded it by a hose,” Johnson said.

Johnson noted that maintenance of traffic is another challenge.

The team is utilizing future ramps to run U.S. 70 traffic.

Johnson explained the traffic sequence.

“We're using RCIs [reduced conflict intersections] to control traffic, so if you're on a side street and you need to get onto U.S. 70, you go up the ramp, turn right, and then go down and make a U-turn.”

Helping the public understand this sequence has required significant communication and education.

## Extenuating Circumstances

The project is being delivered via the design-build method. Johnson said that one of the main reasons is that the state was seeking an innovative team, particularly for a solution for the highly compressible soils.

The contract was awarded at $203 million. However, NCDOT added $9.1 million in work (some curb and gutter). The design-build team filed an early delay claim, with a $22.8 million cost escalation. The price currently stands at $234.9 million. Much of the escalation is due to the jump in prices since the project was awarded in 2019.

Construction on the project began in Spring 2022. The original completion date was late 2027. Johnson expects the completion date will be pushed back. She attributes this to multiple factors.

“The early stages of this project, such as design and right-of-way acquisition, occurred during COVID-19 and lockdowns. It was very difficult for right-of-way acquisition to begin because it required meeting with people.”

Utility relocation, railroad permitting, and staffing shortages also negatively impacted the schedule.

When the U.S. 70 James City project is completed, it will be one more step to transforming a section of the route to interstate status. I-42 will help freight move through the state, deliver vacationers to the beach and improve connectivity to military bases.

## Photos

![NCDOT is undertaking 16 projects to ensure the U.S. 70 meets standards. One current project is in James City.](https://dmt55mxnkgbz2.cloudfront.net/1205x0_s3-72826-S-172_26-LB-1_JPG-233e460c7a8031629e4f149182d137fc.jpg)
*Photo credit: NCDOT photo*

![The project covers a 5.1-mi. stretch of U.S. 70.](https://dmt55mxnkgbz2.cloudfront.net/1205x0_s3-72826-S-172_26-LB-2-b1035eb3de58f4c5927a8c54d140c013.jpg)
*Photo credit: NCDOT photo*

![Rebuilding U.S. 70 for Its Interstate Future photo 3](https://dmt55mxnkgbz2.cloudfront.net/1205x0_s3-72826-S-172_26-LB-3-b3c8f11d2b617b182e13fce9439a6ec6.jpg)
*Photo credit: NCDOT photo*

![The five interchanges will become new highway exits for the future Interstate 42.](https://dmt55mxnkgbz2.cloudfront.net/1205x0_s3-72826-S-172_26-LB-4-477ec876f92993cf30df55e9c90b060c.jpg)
*Photo credit: NCDOT photo*

![The price currently stands at $234.9 million.](https://dmt55mxnkgbz2.cloudfront.net/1205x0_s3-72826-S-172_26-LB-5-733adcca163f6bf38cf032d9b65a3070.jpg)
*Photo credit: NCDOT photo*

![The project is being delivered via the design-build method.](https://dmt55mxnkgbz2.cloudfront.net/1205x0_s3-72826-S-172_26-LB-6-5b1f0d24dfb0df76cf721542de976079.jpg)
*Photo credit: NCDOT photo*