List Your Equipment  /  Dealer Login

RIDOT Begins $715.6M in RhodeWorks Projects; Largest Season in Agency History

Wed July 03, 2019 - Northeast Edition #14
Lori Tobias – CEG Correspondent


RIDOT is entering its second full year of construction on the $410 million Route 6-10 Interchange Project to replace seven out of nine structurally deficient bridges in the interchange.
(RIDOT photo)
RIDOT is entering its second full year of construction on the $410 million Route 6-10 Interchange Project to replace seven out of nine structurally deficient bridges in the interchange. (RIDOT photo)
RIDOT is entering its second full year of construction on the $410 million Route 6-10 Interchange Project to replace seven out of nine structurally deficient bridges in the interchange.
(RIDOT photo) Following numerous traffic pattern shifts last fall, construction continued through the winter with demolition of old bridge sections, earthwork and foundation work for new bridges.
(RIDOT photo) The projects in the RhodeWorks program include a combination of bridge repair, replacement and preservation activities on 177 bridges.
(RIDOT photo) “We have another banner year for construction, with hundreds of millions of dollars of construction underway and scores of new, well-paying jobs rebuilding Rhode Island,” said Rhode Island Gov. Gina Raimondo.
(RIDOT photo) When possible, RIDOT is implementing traffic changes on weekends, when traffic is lighter.
(RIDOT photo) Construction includes the critical “missing move” to connect Route 10 North to Route 6 West.
(RIDOT photo) Work is being done on the Victory Highway Bridge over I-95 in West Greenwich, R.I.
(RIDOT photo) The need for the numerous projects comes largely as many of the highways reach about the 50-year mark and older simultaneously, said RIDOT spokesman Charles St. Martin.
(RIDOT photo) RIDOT kicked off the largest transportation construction season in the history of the agency in April, touting 77 new and ongoing projects valued at $715.6 million.
(RIDOT photo)

The Rhode Island Department of Transportation (RIDOT) kicked off the largest transportation construction season in the history of the agency in April, touting 77 new and ongoing projects valued at $715.6 million. The projects in the RhodeWorks program include a combination of bridge repair, replacement and preservation activities on 177 bridges.

"We have another banner year for construction, with hundreds of millions of dollars of construction underway and scores of new, well-paying jobs rebuilding Rhode Island," said Rhode Island Gov. Gina Raimondo. "We're delivering on the promises in RhodeWorks to pull us out of the bottom of lists that talk about poor roads and bridges and move us toward a day when we'll rank among the top states in the country with a well-maintained transportation system."

RIDOT director Peter Alviti Jr. described the projects as "another major down payment on our comeback story to deliver a safe, high-quality transportation system."

The need for the numerous projects comes largely as many of the highways reach about the 50-year mark and older simultaneously, said RIDOT spokesman Charles St. Martin.

"A lot of the projects involve Interstate bridges and highway bridges," St. Martin said. "Some of it has been overlooked, but some of it is because the highway system was constructed at about the same time. So, they are all becoming due at the same time. They are starting to get past their service lives and need rehabilitation.

"We're pretty much entering the fourth year of the Rhodeworks Program, a 10-year program. We are in the implementation stage of the plan. Last year was a busy construction season. This year is busy, if not busier."

RIDOT is managing the numerous projects using a project management model which involves assigning project managers to each project. Each project is reviewed for traffic impacts, the impacts on the community and how they interplay with each other.

When it makes sense the project work zones are scheduled to coincide with each other so that traffic is shifted only once.

"We have a project starting in Bristol that will involve a bridge closure," St. Martin said. "We're making sure work is done this year so when we have the bridge closure next year, we'll detour on the parallel state road we are working on this year. We picked our closure time so one follows the other. That's just an example, but we are doing that in many locations. When we get to each individual project, we have frequent meetings to discuss how the project is going to run, traffic implementation and what steps we have to take. We have a business outreach person who gets out into the community and talks about things that are coming their way. They also do it on the construction side. The media office also looks at impacts. What do we need to help get the word out? What motorists can expect of those impacts? It's a multi-prong approach to outreach to make sure motorists are as aware as they can be for the work that is coming."

When possible, RIDOT also is implementing traffic changes on weekends, when traffic is lighter, giving them the chance to observe and tweak the pattern if necessary."

Projects on the 2019 construction season include:

  • Route 6-10 Interchange Project: RIDOT is entering its second full year of construction on this $410 million project to replace seven out of nine structurally deficient bridges in the interchange. Construction includes the critical "missing move" to connect Route 10 North to Route 6 West. Following numerous traffic pattern shifts last fall, construction continued through the winter with demolition of old bridge sections, earthwork and foundation work for new bridges.
  • Route 37 Bridges: In the fall RIDOT will begin repairs on 15 bridges on Route 37 from Post Road in Warwick to the Pontiac Avenue interchange. The project will make improvements to ease congestion and improve safety at the Pontiac Avenue interchange ($58.9 million).
  • I-95 Bridges: This year RIDOT will have seven large bridge projects on the I-95 corridor including the bridges carrying the highway over Centerville Road and Toll Gate Road in Warwick ($25.3 million), the Kingston Road Bridge at the Route 138 interchange in Hope Valley ($21.3 million), the I-95 Corridor Bridges project for bridges over Roosevelt Avenue and East Street in Pawtucket ($19.1 million), the Victory Highway Bridge (Route 102) over I-95 at Exit 5 ($19 million), The Wood River Valley Bridge north of Exit 2 at the Hopkinton/Richmond line ($16.8 million), the Oxford Street Bridge, between Exits 18 and 19 in Providence ($10.1 million), and the Baker's Pine Bridge at Exit 4 in Richmond ($9.4 million).
  • I-295 bridges over Plainfield Pike on the Johnston/Cranston line: The $22.6 million project is one of many large-scale bridge projects under way this year as part of Gov. Raimondo's RhodeWorks program to bring Rhode Island's roads and bridges into a state of good repair. Three out of the four bridges in this project, called I-295 Bridges Contract 1, are rated as structurally deficient. Built between 1968 and 1969, they carry 82,000 vehicles per day. In addition to the two bridges that carry I-295 north and south over Plainfield Pike, RIDOT also is repairing two bridges just south of the Plainfield Pike intersection which pass over an aqueduct for the Providence Water Supply Board. This buried 90-in. diameter pipe carries much of the water used by Rhode Island residents.
  • I-295 Bridges: In addition to the bridges project at Plainfield Pike, RIDOT has two other major projects along this highway corridor. They include the $42.6 million I-295 Bridges Contract 2 project, replacing four bridges over Routes 6 and 6A in Johnston, and the Cumberland I-295 Corridor Bridges that carry the highway over Scott and Leigh roads in Cumberland ($20.1 million). CEG



Today's top stories

Growing Interest in Construction Careers Among Younger People Means Jobs Filled, Deadlines Met

Larry Young Paving Tackles Grade-Separated Interchange in Texas

Caltrans, Crews Working to Repair Highway Landslides

FIRSTGREEN Industries Launches ROCKEAT Electric Skid Steer Loader

'Tiltrotator Effect' Increases as Energy Consumption Goes Down

VIDEO: Birmingham, Ala., Awarded $14.5M Fed Grant to Revitalize Its 'Black Main Street'

Pettibone Celebrates 75th Anniversary of Cary-Lift

Fay Preps Way for Pittsburgh International Airport Modernization Project


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA