Utah I-15 Corridor: A Custom Design Job

Usage of the latest technology is one of the key factors in meeting a very tight deadline.

Thu March 21, 2013 - National Edition
Jeff Winke


The Utah County I-15 Corridor Expansion (I-15 CORE) project began in April 2010 and was deadlined for an end of 2012 completion — an unprecedented 35 month schedule. A joint venture company, called Provo River Constructors (PRC), was selected by the Utah Department of Transportation (UDOT) to design and build the I-15 CORE. PRC is led by Fluor Company, Dallas, Texas; Ames Construction Company, Minneapolis, Minn.; Ralph L. Wadsworth Construction Company, Draper, Utah; Wadsworth Brothers Construction Company, Draper, Utah; and includes at least 30 other subcontractors.

“This design-build project is massive … requires 1,500 workers, and we’re using the latest technology throughout,” said Scott MacKenzie, survey manager of PRC. “We probably have the largest number of Trimble systems in use at one job site in the world.”

“We’re using Trimble survey equipment to collect site data, Trimble software to create the site plan digital model, Trimble GCS900 Grade Control Systems on all of our blades and dozers, and Trimble PCS900 Paving Control Systems for all the finished paving,” said Jarred Rico, assistant survey manager of PRC. “The technology is invaluable on a project like this. We’re more efficient, productive, and managing a safer worksite.”

According to the PRC managers, the technology is helping them stay ahead of schedule. “Our crews are working 24/7 to meet the tight schedule we have,” MacKenzie said. “There is no good manual way to accomplish everything we’re doing on this project. We’re very happy with the Trimble systems and can’t imagine working without them on this project.”

PRC built the digital model from the job site and design data collected at the site.

“Fortunately the Trimble technology allows us to build and adjust the digital model as we progress along the 24-mile route,” said MacKenzie. “We encounter soil changes, differing community standards from city to city, and a lot of conditions that weren’t on the plans, so we have to survey and send the changes into the model builders for the most current plan that we work from.”

Over the years much of the existing road had been resurfaced multiple times. They wouldn’t use a profile, but would mill an inch or so off the existing road and then add a lift of fresh asphalt. This road is heavily used so UDOT determined that I-15 needed to be reconstructed and widened.

When completed, the freeway will have up to six travel lanes in each direction, plus on-ramps and exit lanes. The inside and outside shoulders will be generous concrete-paved emergency shoulders. “This will be a big highway,” said Rico.

In building the road, PRC first laid an average of 1 ft. (.31 m) of select granular borrow or crushed stone aggregate, which needed to be imported to the site. Then 6 in. (15 cm) of smaller, open graded base was placed on top. Since the subbase had been graded with a motor grader using a Trimble GCS900 Grade Control System, PRC felt confident it could accurately place the gravel layers.

On top of the gravel subbases, PRC then placed a 3 in. (7.6 cm) layer of a lean mixture of hot mix asphalt (HMA) using a pair of pavers equipped with Trimble PCS900 Paving Control Systems to pave 24-ft. (7.3 m) wide strips.

“Because we used Trimble PCS900 paving systems on the asphalt base, we not only ensured that we used the proper amount of HMA, but we also saved on concrete yields because the concrete use is a direct reflection of the thickness, quality and consistency of the asphalt,” stated Rico. “Not having to use wire line, just for starters, saves a lot of labor, accidents, and rewiring. Plus, there’s a higher level of confidence using the technology.”

Using the Trimble systems also allowed PRC to monitor and document its progress. The company checks its work every 10 ft. (3 m) to ensure quality.

“Our production is faster and our end-result quality is better,” MacKenzie said. “As long as the system and paver are running right and we maintain the confirmation checks, we can complete whole sections and not have to do any grinds.”

The project calls for placing anywhere from 10.5 to 12.5 in. (26.7 to 31.8 cm) of concrete. UDOT required PRC to stand behind the wearability of this heavily-traveled road. PRC will be issuing a four-year-warranty.

With a massive and complex project such as I-15 CORE, communication is critical. Errors not only can be costly, but they can eat up time.

“We’re using the Trimble Connected Community, which is a web-based service that allows us to communicate in real time with our people and machines on the site,” says Rico. “I can literally sit at a desk somewhere and make changes to the digital site plan and send it out to everyone on the site. It eliminates the cost and time of driving out to the job site, and locating every rod, total station, and machine to plug in a change.”

Connected Community is a centralized information management system designed to wirelessly connect people, sites, and devices in real time. It provides a two-way data synchronization backbone.

“I-15 CORE is a custom design project so there are changes and adjustments that need to be made at all times,” MacKenzie stated. “It would be a nightmare to have to function without the Connected Community — when you think of trying to manually trying to get changes out to 80-some GPS machine systems and data collectors on the site, we wouldn’t be as far along as we are.”

MacKenzie said that he’s quite satisfied that the 24-mi. (38.6 km) I-15 CORE project is moving ahead quickly and will meet its aggressive timeline.

“My number one concern all along is safety,” said MacKenzie. “The project has been very safe and being able to use the automation that Trimble provides helps keep workers off the grade and out of harm’s way.”

“Also,” Rico added, “when you look at the volume of information collected, processed, and relied on every day, we wouldn’t be able to produce the level of quality as quickly as we have without the help of technology.”

When the last of the 2.8 million sq. yds. (2.1 million sq m) of concrete paving is placed as the wear surface there will likely be plenty to celebrate.




Today's top stories

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

ASCENDUM Machinery Opens New Savannah, Ga., Facility

FEMA Repaying Vermont $22M for Cleanup Costs Due to July 2023 Floods

Mecalac Holds Road Shows at Case Power in Miami, Orlando


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA