List Your Equipment  /  Dealer Login

VIDEO: Payment Dispute Stops Construction on Project

Multiple subcontractors have left or are threatening to leave the project because they’re owed money.

Thu September 08, 2016 - Midwest Edition
Construction Equipment Guide


A state agency wrote to the project's developer telling them to fix the problem within 30 days.
A state agency wrote to the project's developer telling them to fix the problem within 30 days.

Local Indiana TV News affiliate WISH is reporting that a payment dispute is stopping construction on an I-69 construction project.

Bloomington's mayor said the project might not be done until May of 2018. He's now calling on Gov. Pence to take action.

A Bloomington-based construction firm called Crider and Crider walked off the job because a company called Isolux Corsan owes them $2.3 million dollars, according to state leaders.

A state agency wrote to the project's developer telling them to fix the problem within 30 days. The letter said multiple subcontractors have left or are threatening to leave the project because they're owed money.

Bloomington Mayor John Hamilton said he originally expected the work to do be done by next month.

“I'm not against trying public-private partnerships. But if it's not working, the responsibility of government is to step in, fix it and get people back to work here so everybody's safe and we get our economy humming again,” Hamilton said.

Hamilton blames the construction for traffic jams and accidents on SR 37, which is being worked on as part of the project, including a semi-crash Wednesday morning that closed all lanes and caused at least one injury.

Isolux Corsan did not respond to an email from 24-Hour News 8 asking why they didn't pay the workers. When 24-Hour News 8 called the project developer, I-69 Development Partners LLC, an employee told a reporter to email Isolux Corsan.

Gov. Mike Pence's office did not immediately respond to a request for comment from 24-Hour News 8. Neither did Crider and Crider.

Source: WISH


Today's top stories

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Muddy Water Dredging Christens Marlin Class Dredge

Indiana Officials Mark Start of 2024 Construction Season, Promote Safety

Leica Geosystems Launches its First Machine Smart Antenna — Leica iCON gps 120


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo