W.Va. High Court Asked to Reconsider Wind Farm Approval

Fri September 11, 2009 - Northeast Edition
Tim Huber


CHARLESTON, W.Va. (AP) Opponents of a 124-turbine wind farm proposed for southeastern West Virginia urged the state Supreme Court on Sept. 2 to consider anew whether regulators correctly approved the project.

Mountain Communities for Responsible Energy and a Greenbrier County couple are challenging the state Public Service Commission (PSC) decision in February to permit Beech Ridge Energy LLC to start construction of the $300 million project. In giving its OK, the commission said Beech Ridge had met all pre-construction conditions spelled out in an August 2006 ruling. The court has already upheld the 2006 permit.

Opponents appealed to the Supreme Court after the PSC rejected requests that it reconsider.

The 186-megawatt wind farm is to stretch from Greenbrier to Nicholas counties. The project also includes a transmission line.

Lawyer Brad Stephens, who represents Mountain Communities for Responsible Energy, told the court the commission had exceeded its authority in several instances, including approving Beech Ridge’s decommissioning plans. The group contends the plan doesn’t set aside enough money to remove the project if it fails.

“What the PSC has set up here and validated in its orders,’’ Stephens said, “it’s insufficient to ensure that these things can be taken down.’’

Jeffrey Eisenbeiss, who is also fighting the wind farm in court, cited similar problems, arguing among other things that the commission should have required a federal permit allowing the incidental killing of bats by the turbines.

“The PSC abused and exceeded its authority,’’ Eisenbeiss said.

Justice Robin Davis warned Eisenbeiss and Stephens that she’s skeptical, even though she opposes wind farms.

“Quite frankly, I don’t like these wind plants,’’ she said. “But we have to follow the law.’’

Davis noted Beech Ridge complied with more than two dozen things the PSC required after an earlier appeal to the court. “It seems like they’ve done what we asked them to do.’’

Lawyers for Beech Ridge and the commission agreed.




Today's top stories

HIgh Reach Excavators Raze Former Jail Site

OSHA COVID Safety Rules Give Workplace Flexibility to Transportation Construction Firms

Case to Host Live Virtual Event Detailing Technology, Options, Advantages of Excavators Outfitted With Machine Control

Husqvarna Construction Launches Next Generation Battery Power Cutter

Cat 'Fundamentals of Equipment Economics' Course Improves Profitability

Curb Roller Manufacturing Debuts Lynx Modular Roller Screed at World of Concrete

Performance-Matched Attachments Now Available for Kubota's SCL1000 Stand-On Track Loader

Farmington Bay Constructors Begin 750M Project








ceg-logo ceg-logo ceg-logo ceg-logo ceg-logo