List Your Equipment  /  Dealer Login

$78M Widening Project Progresses in Las Vegas

Wed December 05, 2018 - West Edition #25
Cindy Riley – CEG Correspondent


In February, officials broke ground on the $78 million project, which will improve reliability, connectivity and mobility.
(Nevada Department of Transportation photo)
In February, officials broke ground on the $78 million project, which will improve reliability, connectivity and mobility. (Nevada Department of Transportation photo)
In February, officials broke ground on the $78 million project, which will improve reliability, connectivity and mobility.
(Nevada Department of Transportation photo) The main equipment fleet consists of scrapers, bulldozers, wheel loaders, water trucks, water-pulls, blades, soil compactors and on-highway Class 8 trucks for grading operations. Trenchers, excavators, cranes and forklifts are being used for installing reinforced concrete box culvert.
(Nevada Department of Transportation photo) Completed work consists of temporary detour crossovers, tortoise fencing, site work, placement of some reinforced concrete box culvert, partial pipe installation and some electrical work.
(Nevada Department of Transportation photo) The project calls for about 700,000 cu. yds. of dirt, which is enough to fill 210 Olympic-sized swimming pools.
(Nevada Department of Transportation photo) Materials being used during construction include 36,000 cu. yds. of concrete; 100,000 tons of aggregate base; 100,000 tons of asphalt paving; 37,000 tons of decorative rock; 6.7 million lbs. of reinforcing steel; 10,000 lineal ft. of reinforced concrete pipe; and 25,000 cu. yds. of MSE wall backfill.
(Nevada Department of Transportation photo) Construction crews in Nevada are making steady progress as they widen and upgrade a 6-mi.-long stretch of U.S. Highway 95 in Las Vegas. 
(Nevada Department of Transportation photo)

Construction crews in Nevada are making steady progress as they widen and upgrade a 6-mi.-long stretch of U.S. Highway 95 in Las Vegas. In February, officials broke ground on the $78 million project, which will improve reliability, connectivity and mobility.

"Northwest Las Vegas is one of the fastest-growing, rapidly-developing sections of southern Nevada, attracting new businesses, visitors and residents in record numbers," said Tony Illia, spokesman for the Nevada Department of Transportation (NDOT). "U.S. Highway 95 serves as the area's primary transportation corridor, linking together homes and schools, shopping centers and churches. This project will relieve congestion, improve efficiency and enhance safety, while providing capacity for future growth and economic development."

Funding availability, safety concerns, increased congestion and future planned development make now the right time to perform the work, which is taking place between Ann and Kyle Canyon roads. The city saw a 73 percent residential growth over the last decade, bringing its current population to about 465,000. According to the U.S. Census Bureau, the city's percentage increase was fifth highest in the nation among cities with more than 100,000 people.

Illia said landscaping also will play an important role during construction.

"State highways should reflect the land and people. Landscaping serves a functional role, too, beyond aesthetics. Decorative rock, for example, keeps fugitive dust from becoming airborne, which could compromise air quality and run afowl of federal standards. It additionally helps prevent soil erosion," he said. "We use native shrubs and trees such as cacti, yucca and other drought-tolerant indigenous plants found within Nevada's natural topography."

According to Jenica Keller, NDOT senior project manager, "Traffic through the area is expected to more than double over the next two decades. Freeway capacity, configurations and a lack of carpool lanes are currently causing travel delays at interchange on and off-ramps. We are improving capacity by adding another travel lane in each direction for reduced travel time. Meanwhile, the addition of a new Kyle Canyon Road interchange will greatly enhance efficiency and safety by eliminating dangerous left-handed turns across two lanes of high-speed traffic.

"This project is the result of intensive partnering efforts with the city of Las Vegas and Clark County Regional Flood Control District, whose involvement and contributions led to the addition of 11,200 feet of concrete box storm drainage and 400 feet of open channel between the ‘Centennial Bowl' interchange and Grand Teton Drive. The partnership also helped produce carpool drop ramps at Elkhorn Drive and a new Kyle Canyon Road interchange, whose architectural design element reflect the socio-cultural history of the nearby Spring Mountains National Recreation Area with ice age-era fossils, indigenous plant life and native animals. Native plants dislocated by construction are being saved and replanted upon completion."

Abid Sulahria, NDOT project engineer, also noted that the project has not experienced any significant setbacks, to date.

"It is on budget, with strong community support. Construction remains on track to finish by mid-2019."

The crew's biggest concern involves constructing two interchange bridges, one northbound, the other southbound. Darren Keser, project manager of general contractor Las Vegas Paving Corp., said workers are building one structure at a time, due to the project's contractual time frames.

"The challenges lie with having a crossover-type detour during construction, which keeps traffic near the work zone, as opposed to being re-routed far away. As such, constant worker awareness and safety diligence are required."

Construction began in early 2018. Completed work consists of temporary detour crossovers, tortoise fencing, site work, placement of some reinforced concrete box culvert, partial pipe installation and some electrical work. In addition, the southbound bridge at Kyle Canyon Road and U.S. Highway 95 is almost built.

Keser said expanding the highway from four to six lanes and building carpool access ramps involves traffic control, excavation, storm drain, electrical, aggregate base, paving, striping and signs. Work on the diverging diamond interchange is being done without much traffic, making work much easier.

"We still need to complete the Elkhorn Road carpool drop ramp, including mechanically stabilized earth walls, plus we have to finish the northbound bridge at the Kyle Canyon Road interchange, along with landscaping."

The condition of the property before work began was natural with brush.

"We first had to install desert tortoise fencing prior to any work occurring, while having employees undertake desert tortoise training," said Keser. "The desert tortoise is a threatened species, protected under the U.S. Endangered Species Act and Nevada Administrative Code 503.080. We also salvaged hundreds of native cacti and yuccas that will be replanted once construction is complete."

The project calls for about 700,000 cu. yds. of dirt, which is enough to fill 210 Olympic-sized swimming pools. The main equipment fleet consists of scrapers, bulldozers, wheel loaders, water trucks, water-pulls, blades, soil compactors and on-highway Class 8 trucks for grading operations. Trenchers, excavators, cranes and forklifts are being used for installing reinforced concrete box culvert.

Materials being used during construction include 36,000 cu. yds. of concrete; 100,000 tons of aggregate base; 100,000 tons of asphalt paving; 37,000 tons of decorative rock; 6.7 million lbs. of reinforcing steel; 10,000 lineal ft. of reinforced concrete pipe; and 25,000 cu. yds. of MSE wall backfill.

Keser said the elements have not been a factor, so far.

"Although there have been a few windy days, weather has not been much of an issue."

As work progresses, crews will place decorative rock using wheel loaders, as well as truck-mounted conveyor belts for hard-to-reach areas.

"The Intelligent Transportation Systems are being installed by a subcontractor. Their success, however, hinges around us first completing the site grading. Barrier rail placement, meanwhile, is done with a special barrier rail machine, with hand ties where necessary."

Workers also will place 11,200 ft. of concrete box storm drainage and 400 ft. of open channel in one section of the project.

"Storm drainage placement is demanding, due to the culvert box size and location alongside U.S. Highway 95," said Keser. "Construction entails deep trench excavations and working around existing utilities, while performing under tight project schedule deadlines. You name it, and we have it on this task."

CEG




Today's top stories

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Tennessee's Pugmill Systems LLC Expands Its Product Offerings to Include Concrete Plants

ASCENDUM Machinery Opens New Savannah, Ga., Facility

FEMA Repaying Vermont $22M for Cleanup Costs Due to July 2023 Floods


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA