List Your Equipment For Free  /  Seller Login

Alaska’s Ketchikan Viaduct Gets Facelift

Wed September 22, 2010 - West Edition
Rebecca Ragain


Tourists visiting Alaska know the town of Ketchikan as one of the first northbound stops along the Inside Passage cruise route. Ketchikan is also the transportation hub and government center for the southern part of the Alaska Panhandle.

Whereas the must-see area for out-of-town visitors is historic Creek Street, where old wooden shops overlook the salmon-laden creek, locals spend much of their time traveling the main traffic corridor through town, Tongass Avenue, which becomes Tongass Highway to the north and south.

The Tongass Avenue Viaduct, constructed in the 1950s, is in the midst of receiving much-needed improvements. In February, contractor SECON began the second phase of work to rehabilitate approximately 1,000 ft. (305 m), 23 spans, of the viaduct, which sees average daily traffic of 17,700 vehicles.

The scope of the $7.5-million, federally-funded project involves repairing and rehabilitating spalled and delaminated concrete on both the superstructure and substructure of the viaduct.

In addition, long-term corrosion prevention will be installed in the form of cathodic protection systems, including metalized zinc on the underside of deck panels and deck beams, pre-fabricated zinc jacket systems on existing piles and selected pile caps, and zinc ingot anodes on piles below the tidewater level.

“There are many areas of delaminated concrete and corrosion of the reinforcing steel in the substructure and bridge deck that require reconstruction and repair to avoid load limiting of the structure,” said Alaska Department of Transportation and Public Facilities Chief Communications Officer, Roger Wetherell, in an email.

According to Wetherell, major equipment used for this project consists of the work platform and enclosure, negative air and heating systems, sand blasting and containment equipment, and arc-spray metalizing equipment.

As of early September, nine spans of the viaduct had been rehabilitated, leaving the remaining 14 to be completed by the scheduled end date of mid-March. Thus far, the primary challenge has been scheduling work around the tides, said Wetherell.

This is the final phase of rehabilitation planned for the Tongass Avenue Viaduct. Future improvements will involve the outright replacement of existing viaduct sections wherever practicable.

SECON is currently working on additional Tongass roadway improvements, to the north and south of the Tongass Avenue Viaduct, for the Alaska DOT and PF: a $1.3 million job, awarded in January, to replace aging guardrails on South Tongass Highway; and a $8.7 million contract, awarded in April, to reconstruct approximately two miles of North Tongass Highway.

Juneau-based SECON is a grading, paving, drainage, water and sewer contractor and a subsidiary of Colaska, which was formed in 1999 when French transportation construction giant, Colas SA, bought SECON. Other Colaska subsidiaries include Exclusive Paving, a heavy civil, utility, and highway construction firm in Fairbanks, and AGGPRO, providing concrete and aggregate in Juneau and Anchorage.




Today's top stories

Kokosing Works On $101M I-81 Widening Project in Virginia

VIDEO: Fourth Generation Leads Company Into Second Century

Case 580EV Electric Backhoe Loader Wins Good Design Award

VIDEO: Maryland Approves $75M Contract for Consortium to Manage Key Bridge's Rebuild

Illinois Tollway $534M I-490 Project Continues

Feds Award $25M Grant to Transform Jersey City's 12th Street Corridor at Holland Tunnel

Bobcat Showcases New Backhoe Loader, Essential Construction Equipment, Attachments at World of Concrete 2025

Federal Funds Totaling $25.8M Slated to Replace Readsboro Bridge in Southern Vermont