Looking Back — Clement Brothers Company Inc. Builds Carter Dam

Mon May 13, 2019 - Northeast Edition #10
Edgar A. Browning – Special to CEG


Clement Brothers Company Inc. of Hickory, N.C., held a $15.4 million contract to construct the Corps of Engineers Carter Dam Project in Murry County, Ga. The dam is 445 ft. high, then the highest dam east of the Mississippi River, and 2,050 ft. long. The dam was built on the Coosawattee River.

CEG

A Northwest 180-D shovel with a 4-1/2 cu. yd. dipper loads a fleet of Euclid R-35 rear dump trucks on April 22, 1967. The contractors used a total of five Northwest 180-D shovels on the Carter Dam project to load a fleet of 29 Euclid R-35 trucks. A total of 12.4 million cu. yds. of rock and 1.8 million cu. yds. of earth were moved.
(HCEA: Euclid Collection photo)
A Northwest 180-D shovel with a 4-1/2 cu. yd. dipper loads a fleet of Euclid R-35 rear dump trucks on April 22, 1967. The contractors used a total of five Northwest 180-D shovels on the Carter Dam project to load a fleet of 29 Euclid R-35 trucks. A total of 12.4 million cu. yds. of rock and 1.8 million cu. yds. of earth were moved. (HCEA: Euclid Collection photo)

A loaded Euclid R-35 rear dump travels a haul road overlooking the Carter Dam site on May 15, 1965.
(HCEA: Euclid Collection photo)
A loaded Euclid R-35 rear dump travels a haul road overlooking the Carter Dam site on May 15, 1965. (HCEA: Euclid Collection photo)

Three unidentified project officials are photographed in front of one of the Euclid R-35 trucks.
(HCEA: Euclid Collection photo)
Three unidentified project officials are photographed in front of one of the Euclid R-35 trucks. (HCEA: Euclid Collection photo)




Today's top stories

Filling the Labor Pool — Post-Pandemic, Construction Industry Wants Workers to Jump in

Reed & Reed Leads Twin Bridges in Vermont to Mid-Summer Completion

Granite Construction, Mahaffey Drilling Fix Railroad Issue in Encintas

Texas Women in Construction — Sherry McGee: HOLT CAT

OSHA COVID Safety Rules Give Workplace Flexibility to Transportation Construction Firms

Spanning the Potomac: Three-Quarter-Billion-Dollar Bridge Replacement Under Way

Reconstruction Begins On Century-Old Border Crossing Span Over St. John River

Doosan, Trimble Announce Factory-Installed Machine Control Solution for Crawler Excavators


 






ceg-logo ceg-logo ceg-logo ceg-logo ceg-logo