List Your Equipment  /  Dealer Login

Construction Backlog Grows 4 Percent in First Quarter

Mon May 23, 2011 - National Edition
Construction Equipment Guide


Associated Builders and Contractors (ABC) reported May 17 that its Construction Backlog Indicator (CBI) for the first quarter of 2011 averaged 7.3 months, a 4 percent increase from 7.1 months during the fourth quarter of 2010, and up from 6.1 months, or an increase of 21 percent, from one year ago. CBI is a forward-looking indicator that measures the amount of construction work under contract to be completed in the future.

"While the commercial and industrial construction industry is no longer in deep decline, meaningful recovery remains elusive, with CBI still below levels associated with vigorous nonresidential construction activity," said Associated Builders and Contractors Chief Economist Anirban Basu. "However, crisis conditions have abated and the indicator is moving in the right direction. CBI is now 33 percent above its historic low point of 5.5 months registered in January 2010.

"The expectation is that the U.S. economy will fall short of growing 3 percent in 2011. At the same time, other macroeconomic factors, including sharp increases in construction materials prices, have the potential to reverse the stabilization in activity that ABC presently observes," Basu said.

"A decline in backlog associated with the infrastructure category is likely a reflection of an ongoing reduction in the influence of federal stimulus funding in a number of segments, including highway and street, and conservation and development. Given the expected reduction in infrastructure investment by state and local governments, further decline in backlog in the infrastructure category is likely," said Basu.

"The improvement in commercial construction-related backlog is precisely what ABC observed and forecasted in its previous report, and we anticipate that this segment will continue to show signs of life and growth in the months ahead," Basu said. "However, given tougher lending standards and high vacancy rates in a number of commercial categories, stakeholders should not anticipate any burst of activity this year."

Regional Highlights

· The Northeast, led by recovery in financial services and technology, and the Middle States, led by growth in activity related to natural resources and industrial production, have experienced significant backlog expansion in recent quarters.

·The South continues to report the lengthiest backlog of any major region, with backlog rising by more than a month, up from 7 months to 8.2 months, over the past two quarters. Over the past four quarters, backlog is up by 1.75 months.

·Despite recent growth, the Middle States continue to experience the smallest backlog on average, largely because this region of the country experienced the sharpest reduction in backlog during the worst of the economic downturn.

Analysis

"With investment in power generation and natural resource exploration having taken a leadership role in the nation’s economic expansion to date, regions that are more natural resource intensive have generally experienced the largest increases in construction backlog. This helps explain the significant improvement in backlog in the South and Middle States since the fourth quarter of 2009," said Basu. "In contrast, much of the western United States is associated with disproportionately high unemployment and largest state fiscal shortfalls, which explains the general lack of improvement since the end of 2009."

Industry Highlights

·Only one of three major industry segments tracked by ABC experienced an increase in backlog — the commercial construction sector.

·Backlog in the infrastructure category has declined for three consecutive quarters and is now approaching levels consistent with the pre-federal stimulus period.

·Backlog in the heavy industrial category has been nearly unchanged over the past three quarters. Slower investment in this category may at least be partially attributable to a surge in construction materials prices, which may have delayed plans for plant expansion in certain contexts.

Analysis

"What CBI indicates is that there is a rotation in construction spending taking place, with infrastructure-related spending slowly slipping as stimulus monies are spent down and commercial construction gradually stabilizing along with the broader economy. This pattern will likely continue going forward, but overall construction volume is positioned to decline over the next several months before stabilizing later this year or sometime in 2012," Basu said. "If construction materials prices are better behaved going forward, the recovery in commercial and heavy industrial construction may accelerate. However, infrastructure-related construction is largely dependent upon government budgetary decisions and for now the focus remains largely upon government cost-cutting as opposed to accelerating investment."

Highlights by Company Size

·During the first quarter of 2011, backlog rose for all categories of firm size.

·As has been the case for many quarters, the larger the firm, the larger the average backlog.

·Average backlog for the smallest firms, those with revenues below $30 million per annum, now stands at 6.4 months, the highest quarterly reading on record.

Analysis

"Backlog continues to expand among the smallest, most fragile construction firms. This is largely attributable to the broadening of the construction recovery beyond the infrastructure segment. Backlog may also be stabilizing for this group due to high failure rates among competitors, who correspondingly cede market share to surviving firms. Backlog for firms in the second smallest category, those with revenues between $30 million and $50 million per annum, is roughly unchanged from year-ago levels, suggesting that for many contractors the recovery is far from vigorous," said Basu. "Interestingly, backlog continues to rise for the largest firms on average despite the gradually diminished impact of federal stimulus spending."




Today's top stories

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Muddy Water Dredging Christens Marlin Class Dredge

Indiana Officials Mark Start of 2024 Construction Season, Promote Safety

Leica Geosystems Launches its First Machine Smart Antenna — Leica iCON gps 120








aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA