Contractor Will Pay $3M to Fix Leaks at Hudson Yards 7 Train Station

The MTA contractor who repeatedly bungled waterproofing at the 6-month-old station will pay another contractor an estimated $3 million to fix it.

Tue March 22, 2016 - Northeast Edition
Construction Equipment Guide


The MTA contractor who repeatedly bungled waterproofing at the 6-month-old station will pay another contractor an estimated $3 million to fix it.
The MTA contractor who repeatedly bungled waterproofing at the 6-month-old station will pay another contractor an estimated $3 million to fix it.

The website DNAinfo is reporting that The newest stop on the 7 train is leaking — and now the MTA contractor who repeatedly bungled waterproofing at the 6-month-old station will pay another contractor an estimated $3 million to fix it, MTA officials said Monday.

Despite a “robust quality control process,” Yonkers Contracting Company — which the MTA hired in 2010 for waterproofing, excavating and mining work at the 34th Street-Hudson Yards station — failed to fix recurring problems with leaks at the station, MTA Capital Construction President Michael Horodniceanu said Monday at an MTA committee meeting.

Leaks, mold growth, bathroom flooding, broken escalators and visible water damage have become common sights at the $2.4 billion station since it opened in September, news outlets reported last week.

“The fact that we have leaks is evident that the waterproofing system is not performing as intended,” Horodniceanu said at the meeting.

Yonkers Contracting tried to fix the waterproofing problems after the MTA first became aware of issues at the unopened station back in 2012, but each time the repairs proved temporary, Horodniceanu said.

A “specialty leak-remediation contractor,” Sovereign Hydroseal, hired by the MTA will start fixing the leakage problems Friday, he said.

Yonkers Contracting, which is paying for the work, will clean and replace tiles affected by the leaks, he added.

“There are issues that have apparently happened during construction, and that is clearly something we're very displeased with,” he added.

A spokeswoman for Yonkers Contracting on Tuesday said work at the station was performed by a subcontractor, noting that the company has brought in another subcontractor to "remedy the situation."

"We're working with the MTA to resolve the issue," she added.

The 1.5-mile extension of the 7 train line and the construction of the new station cost $2.42 billion and was paid for mostly by the city, according to the MTA. The transit agency chipped in $53 million.

MTA board members and Department of Transportation officials at the meeting Monday expressed dismay over the scope of the problems at the station.

“This [station] was spanking new,” board member Jonathan Ballan said, suggesting a task force be formed to address the board about the leakage issues. “The level of surprise and disappointment cannot be overstated.”

To read the full article, click here.




Today's top stories

Waukesha Water's $286M Pipeline Meets Federal Requirements

Case Introduces Factory-Fit Machine Control for Dozers

Longwall Expansion Under Way in Walker County

Trimble Announces TSC5 Field Data Controller for Land, Construction Surveying

Top 10 Big Ticket Equipment Items Sold at Orlando 2021

Long-Awaited Smithfield Gateway Project Begins in Pennsylvania

Great People, Equipment Spur Success for N.C. Contractor

Koss Construction Keeps I-555 Job On Track


 






ceg-logo ceg-logo ceg-logo ceg-logo ceg-logo