Flatiron Constructors to Build New Minn. Bridge

Thu September 20, 2007 - National Edition
Construction Equipment Guide


The joint venture of Flatiron Constructors of Longmont, Colo., and Manson Construction of Seattle, Wash., has been selected as the firm to rebuild the I-35W bridge in downtown Minneapolis. The winning proposal was determined using the state’s design-build, best value procurement model which combines a technical proposal score with a pricing component. In this instance, an A plus B provision was also incorporated into the formula requiring proposers to bid a total number of days to complete the project with each day being valued at $200,000.

Flatiron Constructors was awarded the highest technical proposal score (91.47), bid the highest price ($233,763,000) and also included the greatest number of days (437) to complete the project.

Three other bids were reviewed.

The least expensive price proposal came from Ames/Lunda ($178,489,561), the firm that also received the lowest technical score (55.98). C.S. McCrossan bid $176.9 million and received a score of 65.91 and Walsh Construction/American Bridge bid $219 million with a score of 67.88




Today's top stories

Blalock Crews Build TDOT's $67M Newport Bypass

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Equip Expo's Summer Giveaway Offers a Chance for Lifetime Trade Show Registration, Gift Card, Hotel Stay

Tennessee's Pugmill Systems LLC Expands Its Product Offerings to Include Concrete Plants

ASCENDUM Machinery Opens New Savannah, Ga., Facility








aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA