List Your Equipment  /  Dealer Login

HC Bridge Maine Completes Beam Installation in Illinois

Wed November 19, 2008 - Midwest Edition
Construction Equipment Guide


HC Bridge Maine LLC — a firm specializing in the development of hybrid-composite structural alternatives that can be used for accelerated bridge construction and offer a long service life — recently announced that construction has been completed on the High Road Bridge over Long Run Creek in Lockport Township, Ill., three months ahead of schedule.

The innovative structure, now open to traffic at High Road, is the first permanent highway installation of hybrid composite beams (HCBs), developed by the HC Bridge Company LLC.

The existing High Road Bridge, constructed in 1935, had outlived its useful service life and was categorized as both structurally deficient and functionally obsolete. To reduce future maintenance costs, the new replacement structure, designed by Teng & Associates Inc. of Chicago, utilized a new type of bridge technology — HCB — that provides an extended service life with minimal or no maintenance to the bridge girders.

HCBs are comprised of three main sub-components — an FRP shell, compression reinforcement and tension reinforcement. The compression reinforcement consists of concrete that is pumped into an arch conduit within the beam shell. The tension reinforcement consists of high-strength steel prestressing strands that run along the bottom flanges of the beam shell. All of this is encapsulated in a fiber reinforced plastic shell protecting the beam from salt corrosion and providing added structural capacity.

Byron Danley, vice president of transportation for Teng & Associates Inc., stated that his company is always looking for innovative solutions to the problems facing its clients.

“As our infrastructure ages and our nation’s bridges are rapidly deteriorating, the hybrid composite beams provide a good alternative to traditional beams (steel or concrete) at a lower initial and life-cycle cost due to their durability and corrosion resistance,” said Danley. “The best route to reducing the growing backlog of deteriorated bridges is to embrace new technologies like HCBs that provide longer lives for new bridges.”

The superstructure for this 57-ft. (17.4 m), single-span bridge is comprised of six 42-in. (106 cm) deep HCBs spaced at 7.3-ft. (2.2 m) centers, supporting a conventional 8-in. (20 cm) thick reinforced concrete deck. According to John Hillman, president of HC Bridge, despite the use of the innovative framing system, the bridge was constructed exactly the same way as a conventional concrete or steel bridge.

The HCBs inherently are stronger, lighter and more corrosion resistant than the traditional concrete or steel beams, providing real advantages to the Lockport Township Highway Department.

Manufactured by Harbor Technologies Inc., of Brunswick, Maine, the HCBs weigh approximately one-tenth of what a typical precast concrete beam weighs for the same span length.

This lighter weight reduced shipping and erection costs. As a result, all of the beams for the bridge were shipped on one truck instead of what would have taken six trucks using competing methods, and they were erected using a 30-ton (27 t) crane instead of a large 150 to 200-ton (136 to 181 t) crane that would have been required for precast concrete beams. Construction of the High Road Bridge was conducted by Herlihy Mid-Continent Company of Romeoville, Ill.

In an effort to promote this new technology, Lockport Township Highway Commissioner Jack Waxweiler worked with the Illinois Department of Transportation to secure a $250,000 award grant from the Federal Highway Administration (FHWA) through the Innovative Bridge Research and Design (IBRD) Program. Established by FHWA, IBRD provides discretionary funding to local government agencies to help facilitate innovation in advancing the technology for construction of our nation’s bridge infrastructure.

As part of the IBRD program and prior to installation in the High Road Bridge, the HCBs designed and constructed for the High Road Bridge underwent extensive testing at the Advanced Engineered Wood and Composite (AEWC) Center at the University of Maine, located in Orono.

A prototype HCB was subjected to half a million cycles of fatigue loading, prior to being loaded to the code-specified, factored loads for both bending and shear. After maintaining perfectly linear elastic behavior under these loadings, an attempt was made to load the beam to failure. Even at the maximum capacity of the hydraulic ram, which was 290,000 lbs. (131,500 kg) or 4.4 times the bridge design load, the HCB remained linear elastic and did not fail.

According to Robert Lindyberg, P.E., assistant director for Boatbuilding and Composites University of Maine AEWC Center, these tests validated the strength set forth by the Illinois Department of Transportation.

“The success of this project validated the innovative nature of the product itself and its performance,” said Lindyberg. “As a result, HCBs are now being considered for bridges in Maine.”

Waxweiler stated that the project was extremely efficient.

“The beams worked out really well,” he said. “It only took 90 minutes to set six beams. For traditional steel beams, this erection process would have taken a lot longer and required the use of heavier equipment. Instead, the HCBs arrived in one truck, which is much more economical. The bridge construction finished ahead of schedule, and the HCBs are certainly part of this success.”

Waxweiler also noted that he is confident that HCB technology will reduce the maintenance and repair needed.

According to Art Haggerty, senior project manager of Herlihy Mid-Continent Company, the lightweight nature of the beams worked well with the flow of the project. The crew was able to use a small hydraulic picker to set the beams, eliminating the need to bring in a large crane.

“We were able to set the beams easily in conjunction with the rest of our work,” Haggerty said. “At first, we had reservations about attaching our bridge deck forming system to the smooth gel coat finished exterior of the hybrid beams. Also, we were unsure of how the hybrid beams would react when concrete was poured loading the overhangs. However, the beams’ tough exterior and rigid construction accepted our standard deck forming system with very little trouble and the deck pour resulted in deflections well within acceptable limits.”

Haggerty added that Herlihy prides itself on bringing ingenuity into projects and he is confident that the HCB technology has advanced the state of bridge construction.

“This project demonstrates the constructability of this technology,” he said. “This project was a big success — resulting in a high quality bridge that was finished under budget and ahead of schedule.”

Ralph Anderson, Illinois state bridge engineer, said that Illinois is very interested in expanding the use of the hybrid composite beams for future bridge projects.

“Illinois, like most states, has hundreds of short-span bridges that will need replacement in the near future,” said Anderson. “I expect this technology will provide an economical option that will greatly benefit the citizens of Illinois.”

Although this is the first highway installation of the HCB, the technology has undergone extensive testing and development during the last 12 years. The first live load test of a full scale HCB bridge was conducted at the Transportation Technology Center Inc. (TTCI) near Pueblo, Colo., in November 2007. During these tests, a prototype HCB Bridge was subjected to a battery of tests consisting of a full-size locomotive pulling 26 heavy axle load coal cars. The loads used in the railroad bridge were approximately seven times as heavy as the design loads for the High Road Bridge. After carefully studying the data collected from these tests, the Association of American Railroads plans to conduct endurance testing at TTCI beginning in October 2008.

HC Bridge Company LLC specializes in the development and commercialization of composite bridge technology that accelerates bridge construction and provides structures designed to offer service lives beyond 100 years.




Today's top stories

Blalock Crews Build TDOT's $67M Newport Bypass

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Equip Expo's Summer Giveaway Offers a Chance for Lifetime Trade Show Registration, Gift Card, Hotel Stay

Tennessee's Pugmill Systems LLC Expands Its Product Offerings to Include Concrete Plants

ASCENDUM Machinery Opens New Savannah, Ga., Facility








aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA