Hunter Industries Progresses On I-37 DDI

Hunter Industries Ltd. is making progress on TxDOT's $40 million Interstate 37 Project in San Antonio, TX.

- West Edition #24
Irwin Rapoport – CEG Correspondent

Hunter Industries Ltd. is making progress on the Texas Department of Transportation’s (TxDOT) $40 million Interstate 37 Diverging Diamond Interchange (DDI) Project in southeast San Antonio.
TxDOT photo
Hunter Industries Ltd. is making progress on the Texas Department of Transportation’s (TxDOT) $40 million Interstate 37 Diverging Diamond Interchange (DDI) Project in southeast San Antonio.
Hunter Industries Ltd. is making progress on the Texas Department of Transportation’s (TxDOT) $40 million Interstate 37 Diverging Diamond Interchange (DDI) Project in southeast San Antonio.   (TxDOT photo) Since mobilizing, Hunter Industries’ crews have concentrated on safety, quality and communication while beginning roadway and utility work.   (TxDOT photo) TxDOT is using a phased approach that allows motorists to continue traveling through the interchange while crews complete the improvements.   (TxDOT photo) A broad range of equipment is being deployed to handle the project’s roadway, bridge, drainage and utility work.   (TxDOT photo)

Hunter Industries Ltd. is making progress on the Texas Department of Transportation's (TxDOT) $40 million Interstate 37 Diverging Diamond Interchange (DDI) Project in southeast San Antonio.

The contractor is converting the existing I-37/SE Military Drive interchange to a DDI designed to improve traffic flow, reduce congestion and enhance safety.

The federally funded project began in September 2026 and is expected to be completed in spring 2028. The nearly 2-mi. construction zone extends along I-37 from Southeast Military Drive to Interstate 410.

“This project is a significant investment in transportation infrastructure designed to improve traffic operations, reduce travel times, alleviate congestion and enhance mobility and safety throughout the project area,” Jonathan Cotto, a TxDOT spokesman, told Construction Equipment Guide.

“Once complete, the improvements are projected to improve the flow of traffic, particularly at the I-37/SE Military Drive interchange, and reduce travel times on I-37 between Pecan Valley and I-410 northbound by 46 percent and southbound by 81 percent, and the I-37/SE Military Drive interchange via the I-37 southbound exit DDI by 90 percent, compared against the 'no build' condition if no improvements were constructed by 2028.”

TxDOT has embraced the DDI design as a way to improve traffic operations and safety at highway interchanges throughout the state. The existing I-37 interchange was identified as a strong candidate for the conversion.

“The grade-separated, signalized DDI at I-37 temporarily moves crossroad traffic on SE Military Drive to the left side of the road through a series of crossovers within the interchange,” Cotto said. “This design eliminates left-turn conflicts and makes it easier to access or exit from I-37. This shift also allows vehicles to make free-flowing left turns without crossing traffic, enhancing safety, mobility, access and efficiency for all users.”

The existing interchange handles approximately 28,900 vehicles daily. In addition to the DDI conversion, the project includes a new bypass ramp, a southbound frontage road that transitions into an auxiliary main lane and a 10-ft.-wide shared-use path for bicyclists and pedestrians.

Project Improvements

Project planning began in 2016. In early 2025, TxDOT decided to pursue the DDI design. A public meeting was held later that year and environmental clearance was secured.

Kimley-Horn designed the project, which also includes construction of a bypass ramp over the interchange and a 250-ft.-long, one-lane asphalt frontage road along southbound I-37. The frontage road will transition into an auxiliary main lane that ends at the I-410 exit ramp. Shared-use paths measuring 10 ft. wide will be constructed in both directions.

The roadway configuration also will change. The existing section of I-37 south of State Loop 13 (SL 13) has two northbound and two southbound lanes, with inner and outer shoulders separated by a grassy median.

Under the completed configuration, the section between SL 13 and the southbound entrance ramp at SL 13 will have three southbound frontage road lanes, along with two northbound and two southbound highway lanes.

Between SL 13 and the I-410 ramps on the southbound side, the highway will have two mainline lanes and an auxiliary lane. The northbound side will retain two highway lanes.

Construction Under Way

Since mobilizing, Hunter Industries' crews have concentrated on safety, quality and communication while beginning roadway and utility work. Activities include excavating sections of pavement to access underground utilities and removing aging concrete infrastructure along the roadway and drainage structures that will be replaced.

Over the coming year, crews will turn their attention to the bypass bridge, including construction of its bents and abutments, and the southbound I-37 frontage road that will connect with the mainline.

Demolition work is being performed with Cat 420F excavators equipped with hydraulic hammers to break up existing concrete. Loaders then remove the demolished material. Kubota mini excavators equipped with buckets are used to excavate beneath the pavement and reach underground infrastructure.

Crews have adequate room to operate equipment and move safely through many areas of the construction zone. Where work takes place adjacent to active traffic, cones provide separation between construction activities and motorists.

“One of the biggest construction challenges is maintaining traffic operations while major roadway, bridge, drainage and utility work are taking place in a heavily traveled interchange and roadway,” Cotto said. “The contractor must carefully attend to the phasing of construction activities so we can all minimize disruptions, ensure the safety of the public and the workers. The project is progressively moving forward steadily in accordance with the construction schedule.”

TxDOT also approved a stockpile yard to help Hunter Industries organize and stage equipment and materials needed for the work.

“[We] can install and station all their equipment and materials that will be used for this project to help with the timeframe of the project and avoid delays,” Cotto said.

The contractor has divided the work into four phases, each containing three to four steps. A broad range of equipment is being deployed to handle the project's roadway, bridge, drainage and utility work.

The fleet includes hydraulic excavators, Kubota mini excavators, Cat 420F backhoes, dozers, motor graders, wheel loaders, articulated dump trucks, water trucks, soil compactors and rollers. Crews also are using milling machines, asphalt pavers, concrete paving equipment, crane trucks, vacuum excavation equipment for utility work, foundation drill rigs, bucket trucks for electrical and traffic signal installations, sweepers and traffic control vehicles.

Phased Construction

Maintaining traffic throughout construction is a central consideration in the project's schedule. TxDOT is using a phased approach that allows motorists to continue traveling through the interchange while crews complete the improvements.

“This project is being constructed through a phased approach that allows traffic to remain operational while major improvements are completed,” Cotto said. “The work generally begins with utility relocations, drainage improvements, earthwork, and construction of new pavement areas outside the existing traffic lanes.

“As those elements are completed, traffic is shifted to newly constructed sections so crews can reconstruct existing roadway areas, modify intersections, install traffic signals, lighting and signage, and ultimately implement the DDI crossover configuration. Final activities include pavement markings, landscaping, testing of traffic signal systems and project close-out.”

Addressing unexpected conditions also requires coordination among the project team.

“A common challenge in any project is addressing unforeseen issues not identified in the plans,” Cotto said. “Clear communication between the designer, engineer and contractor is essential to resolving these issues efficiently and keeping the project on schedule. The DDI configuration itself does not have a specific expiration date and can remain functional for several decades, as long as it continues to meet traffic demands and receives routine maintenance.

“Concrete pavement and bridge structures are typically designed for a service life of approximately 50 to 75 years, while asphalt surfaces generally require rehabilitation or resurfacing every 10 to 20 years, depending on traffic volumes and environmental conditions,” he added. “Traffic signals, lighting systems, pavement markings and other operational components have shorter maintenance and replacement cycles, generally ranging from 7 to 25 years. All will be maintained by routine checkups.”

Several Hunter Industries crews and subcontractor employees are working on the project each construction day as the team advances through the initial stages of the interchange conversion.



Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.



Today's top stories

Rebuilding U.S. 70 for Its Interstate Future

Construction Equipment Guide's Richard McKeon Retires

Joey Martin Welcomes Customers to Low Country Heavy Equipment Sale

VIDEO: Volvo EC550 Assists Allens Demolition in Myrtle Beach

Colonels Island Terminal's Expansion Reaches Milestone

Sonsray's V.I.P. Championship Supports Cancer Research

KSM Names Colin Brown Chief Digital & Technology Officer

Suffolk Lands $100M Contract to Build Cottonwood Canyons Transit Center Award





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.