List Your Equipment  /  Dealer Login

Kraemer North America Sets Final Spans On $56M Seattle Project

Tue June 29, 2021 - West Edition #14
Lori Tobias – CEG Correspondent


The bridge project is funded by the nine-year, $930 million Levy to Move Seattle, approved by voters in 2015.
The bridge project is funded by the nine-year, $930 million Levy to Move Seattle, approved by voters in 2015.
The bridge project is funded by the nine-year, $930 million Levy to Move Seattle, approved by voters in 2015. The bridge includes a bridge slope of 4.3 percent, except between the Sound Transit mezzanine and the NE 100th St. level, which is 8.1 percent. 
 Kraemer North America is building a pedestrian-bicycle bridge over I-5 in a north Seattle neighborhood that now stretches over both the southbound and express lanes of I-5.
 The massive western bridge span weighs more than 400,000 pounds and connects to the 200,000-pound eastern bridge segment installed above the northbound lanes of I-5 and to ramps built in 2020. The weight of the new bridge — 400,000 lbs. — is twice the weight of an Argentinosaurus (the largest dinosaur ever discovered), or the equivalent weight of 56 Asian Elephants, 30 T-rexes or three 737 jets.
 The newly constructed Northgate Pedestrian and Bicycle Bridge is 1,900 ft. in length and spans 10 lanes of I-5 in the Northgate neighborhood.  The installation of the steel spans required the closure of I-5 on two separate occasions. The stretch of Interstate sees 220,000 vehicles daily in both directions, making the closures one of the biggest challenges of the job.
 The 125-foot span above the northbound lane and the 234-foot span over the southbound lane was installed over the course of two weekends in June.  The new bridge lands at North Seattle College on the west side and at 1st Ave. NE and NE 100th St., near the future light rail station, on the east side.
 Nine other spans feature concrete girders and were fabricated at Concrete Tech, also in Tacoma, Wash. Four other spans were cast in place.

Crews with Kraemer North America general contractor recently set the final two of 16 steel spans on a $56 million project to create a pedestrian-bicycle bridge over I-5 in the north Seattle neighborhood of Northgate.

The bridge project is funded by the nine-year, $930 million Levy to Move Seattle, approved by voters in 2015.

"The massive western bridge span weighs more than 400,000 pounds and now stretches over both the southbound and express lanes of I-5 just south of NE Northgate Way," said Darrell Bulmer, spokesman of Seattle Department of Transportation [SDOT]. "It connects to the 200,000-pound eastern bridge segment installed above the northbound lanes of I-5 and to ramps built last year.

"For trivia buffs, 400,000 pounds is twice the weight of a Argentinosaurus [the largest dinosaur ever discovered], or the equivalent weight of 56 Asian elephants, 30 T-rexes, or three 737 jets."

The Northgate Pedestrian and Bicycle Bridge is 1,900 ft. in length and spans 10 lanes of I-5 in the Northgate neighborhood. The 125-ft. span above the northbound lane was installed over a weekend in June; the 234-ft. span over the southbound lane was set the following weekend. The installation of the steel spans required the closure of I-5 on two separate occasions. The stretch of Interstate sees approxiately 220,000 vehicles daily in both directions, making the closures one of the biggest challenges of the job.

"We were allowed to shut down I-5 for only 4.5 hours in each direction," said Eric Strauch, SDOT project manager. "The two spans were fabricated off-site in Tacoma. The span over the northbound lanes was able to be transported as one unit out of Tacoma. The bigger southbound span was assembled in Tacoma, cut into four pieces and transported to the site."

Crews assembled that span in the median between I-5 northbound and the Express Lanes, where a wide flat shoulder served as the staging area. The contractractor opted to fabricate the span offsite then cut it into pieces in order to meet legal load requirements, according to Strauch.

"When you look at it, the bridge is complicated with curves and angles," he said. "It would have been very difficult to construct on site. So the contractor did the full fabrication in Tacoma and provided us with a superior product."

The spans were moved into place by remotely controlled, self-propelled transporters, then lifted by a 650-ton mobile crane. A 500-ton mobile crane and 350-ton crawler crane were also used on the job.

The two steel spans were fabricated at Jesse Engineering in Tacoma.

"Those were our final two spans to put in place," said Strauch. "There is still a lot of electrical and handrail work. Our goal is to have it open by October 2."

Nine other spans feature concrete girders and were fabricated at Concrete Tech, also in Tacoma. Four other spans were cast in place, said Bulmer.

"This became part of a project to connect neighborhood biking/walking facilities," Bulmer said. "It not only connects two communities, but also brings together networks for biking and walking as they intersect with other modes of transportation, such as light rail or buses."

Northgate Community

The Northgate neighborhood is a major residential and employment destination that continues to grow, and with the completion of Sound Transit's Link light rail station in 2021, is poised to become one of the region's most active transit hubs.

Currently, this stretch of I-5 divides the neighborhood, making travel on foot or bicycle from one side to the other a journey of at least 25 minutes.

"The Northgate Pedestrian/Bike Bridge will improve access to communities, services and opportunities on the east and west sides of I-5 in Northgate and Licton Springs, helping knit together a historically divided area," according to the project website. "It'll also reduces travel time for people walking and biking between the east and west sides of I-5. When complete, the bridge will help connect the neighborhood's thriving job and retail centers with the rest of the city and region.

The new bridge lands at North Seattle College on the west side and at 1st Ave. NE and NE 100th St., near the future light rail station, on the east side.

The project consists of four main parts:

  • Bridge spans over I-5;
  • Western approach between North Seattle College and wetland area, connecting to College Way N and N 100th St.;
  • Eastern approach between I-5 and 1st Ave NE at NE 100th St., near the King County Transit Center;
  • Multi-use path along 1st Ave. NE;

The bridge also complies with 2010 ADA Standards and includes:

  • A bridge slope of 4.3 percent, except between the Sound Transit mezzanine and the NE 100th St. level, which is 8.1 percent. This section has ADA-compliant handrail grips and 1.8 percent-slope landings every 30 ft. to provide resting places.
  • Elevator access via the Northgate Station Garage, including where the bridge connects to the Northgate Link light rail station, during normal hours of operation.
  • Curb ramps along 1st Ave. NE and NE 100th St., where the bridge spur lands.
  • Accessible pedestrian signals at the intersection of 1st Ave. NE and NE 100th St., which will offer push-button activation, audible signals and vibrations to indicate when it's safe to cross the street. CEG



Today's top stories

Growing Interest in Construction Careers Among Younger People Means Jobs Filled, Deadlines Met

Larry Young Paving Tackles Grade-Separated Interchange in Texas

Caltrans, Crews Working to Repair Highway Landslides

FIRSTGREEN Industries Launches ROCKEAT Electric Skid Steer Loader

'Tiltrotator Effect' Increases as Energy Consumption Goes Down

VIDEO: Birmingham, Ala., Awarded $14.5M Fed Grant to Revitalize Its 'Black Main Street'

Pettibone Celebrates 75th Anniversary of Cary-Lift

Fay Preps Way for Pittsburgh International Airport Modernization Project


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA