Lower Shore Resurfacing Projects Under Way in Maryland

Crews are milling, resurfacing and restriping this 6-mi. (9.65 km) section, working 7 a.m. to 7 p.m. Monday through Friday to complete the project by mid-April.

April 19, 2016 - Northeast Edition
Construction Equipment Guide

Crews grind old pavement during the Coastal Highway (MD 528) resurfacing project.
Crews grind old pavement during the Coastal Highway (MD 528) resurfacing project.

The Maryland Department of Transportation's State Highway Administration (SHA) is resurfacing two major highways on the lower eastern shore. Work is under way on westbound U.S. 50 (Ocean Gateway) between White Richardson Road and Walston Switch Road just east of Salisbury in Wicomico County.

Crews are milling, resurfacing and restriping this 6-mi. (9.65 km) section, working 7 a.m. to 7 p.m. Monday through Friday to complete the project by mid-April. Up to 28,000 vehicles travel this stretch of U.S. 50 each day on average, with significantly higher volumes during the summer beach season.

Once the U.S. 50 work is complete, SHA will move to U.S. 113 (Worcester Highway) in Worcester County, where 5.3 mi. (8.5 km) will be resurfaced in both directions between MD 90 (Ocean City Expressway) and the Delaware state line. More than 14,000 vehicles travel this stretch of U.S. 113 each day.

SHA awarded contracts to Allan Myers of Fallston for both projects. The U.S. 50 contract is valued at $1.9 million; the U.S. 113 work is valued at $3.8 million (estimated) and is being performed under a $10.3 million, multi-location area wide contract.

SHA is also paving 4.7 mi. (7.56 km) of MD 528 (Coastal Highway) from MD 90 to the Delaware line in Ocean City. This work began in mid-March and will be completed by Memorial Day.

SHA scheduled these locations early in the paving season to minimize public impacts — all three major resurfacing projects are time-sensitive due to increased summer traffic volumes. Crews may work extended hours and weekends as permitted to complete the work.

For more information, visit www.md511.org.


Today's top stories

Route 61 Project Eliminates Deadly Curve

Medico Construction Equipment Celebrates New Facility

Sales Auction Company Holds 17th Annual Spring Sale

Big Crowd Descends On New Auction Facility in Uncasville

Demo & Dig Days Events Draw Northeast Operators

UConn Receives Volvo L20 to Grow Construction Education

Columbus Bypass Project Advances Along 6 Mi. of I-10

Faster Where It Counts: How Excavator Cycle Time Shapes Jobsite Productivity


 





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.



39.96118 \\ -82.99879 \\ Columbus \\ OH \\ US \\ 43215