List Your Equipment  /  Dealer Login

Michigan Experiments With Paving Longevity

Wed May 15, 2019 - Midwest Edition #10
Lori Tobias – CEG Correspondent


Work proceeds on the reconstruction of I-69 in Flint, Mich. The state Department of Transportation is using this and other road projects to test the longevity and costs of pavement set at various depths.
(Michigan DOT photo)
Work proceeds on the reconstruction of I-69 in Flint, Mich. The state Department of Transportation is using this and other road projects to test the longevity and costs of pavement set at various depths. (Michigan DOT photo)
Work proceeds on the reconstruction of I-69 in Flint, Mich. The state Department of Transportation is using this and other road projects to test the longevity and costs of pavement set at various depths.
(Michigan DOT photo)
 A dozer clears ground during the reconstruction of I-69.
(Michigan DOT photo) Cement-treated permeable base is laid down during the experiment to test the longevity and cost of 30-year pavement design along I-69.
(Michigan DOT photo)
 Rebar is placed on westbound I-69. 
(Michigan DOT photo) Work crews pave eastbound I-69 in Flint.
(Michigan DOT photo)

The Michigan Department of Transportation began work this spring on the fourth in a series of experimental pavement projects designed to determine if thicker pavement equals a longer lifespan.

The experiments grew out of Public Act 175, which was passed by the state legislature in 2015 and established the Roads Innovation Task Force. Two projects on I-131 near Grand Rapids are complete, a third on I-69 in Flint is nearing completion and work on I-475, also in Flint, recently got under way.

The projects compare 20-year concrete vs. 30-year concrete; 20-year hot mix asphalt (HMA) vs. 30-year HMA and 20-year HMA vs. 50 year.

The differences between the stretches of road are in the depth of the poured material.

"Primarily, as far as any construction project goes, you start with a good foundation," said Curtis Bleech, MDOT statewide pavement engineer. "That's the principle — start with good foundation that is very well-drained.

"Another thing we are doing is a long-term evaluation to see if the longer life pavement costs less than the 20-year design. The thicker pavement is the longer life. What we actually have is four sections, four pavements, and for each one we are trying our standard design and the longer design."

The pavements are designed to withstand the impact of not only ice and snow, but of rain, as well. The thicker foundations must be drainable so that frost heave doesn't damage them. MDOT will monitor the stretches of pavement, recording the maintenance activities, the cost, the time they occurred and the condition of the pavement. Monitoring will begin at the two-year mark and continue every two years.

It will likely be 10 years before engineers can make an educated guess about how well the pavement is holding up and 20 years before they have truly good idea.

"We'll be going out and taking additional testing above and beyond what we usually do," Bleech said. "We'll look at that information compared to what we designed for. It's like a cookie recipe. Grandma can make those really good chocolate chip cookies, but can I make them just as good?

"That's the same thing we do with these projects. We specify the ingredients and the contractor has to build to that. We design for specifications and the contractor has to meet the specifications, but sometimes the materials they use don't perform as well."

MDOT has estimated the 30-year pavement will cost about 50 percent more than the 20-year pavement, while the 50-year pavement will cost about 85 percent more. But the department won't know for at least 10 years if the estimates are accurate.

"Right now, we have the initial cost," Bleech said. "But we won't know the true cost until the end. Each project has its own cost associated with unit price. For example, a square yard of concrete in Flint will cost differently than a square yard of concrete in Lansing. The cost can sometimes be misleading."

One other variable nearly impossible to predict is what transportation will look like in 50 years.

"Will we be driving cars 50 years from now or will we be driving the Jetsons' flying car?" Bleech said. "If you build for 50 years and all of the sudden a major development comes in, you have to tear out the infrastructure because you didn't predict that era of transportation. But we have to do it based on our current knowledge."

CEG




Today's top stories

Fay Preps Way for Pittsburgh International Airport Modernization Project

Volvo CE Continues to Perform, Transform During Slower Q1 2024

American Bridge Co. Leads Conn.'s East Haddam Swing Bridge Project

Growing Interest in Construction Careers Among Younger People Means Jobs Filled, Deadlines Met

Pettibone Celebrates 75th Anniversary of Cary-Lift

Common Ground Alliance Hosts Conference & Expo in Colorado On Preventing Utility Damages

Powerco Hosts Mecalac Road Show Event in Clinton, N.J.

Site Prep Inc. of NC Adds Milling Services to Its Existing Highway Infrastructure Capabilities


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA