List Your Equipment  /  Dealer Login

Northern Vertex Updates Activities at Moss Gold Mine

Tue August 15, 2017 - West Edition #17
Construction Equipment Guide


Northern Vertex Mining Corp.'s Moss Mine project located near Bullhead City, Ariz.
Northern Vertex Mining Corp.'s Moss Mine project located near Bullhead City, Ariz.

Northern Vertex Mining Corp. presents the following update on construction activities at its 100 percent owned Moss Mine project located near Bullhead City, Ariz.

Kenneth Berry, president and CEO, stated: “Under the guidance of Dr. David Stone, project manager; Joseph Bardswich, P.Eng, president, Golden Vertex; M3 Engineering; Golder and Associates; and N.A. Degerstorm, we continue to achieve considerable progress at the Moss Gold/Silver Mine and significantly de-risk the project both technically and financially. Additional, key contracts recently awarded demonstrate the ongoing progress toward our goal of pouring gold in Q4, 2017.”

Key Contracts Recently Executed:

• Concrete contract was awarded to Great Basin Industrial of Kaysville, Utah;

• Heap leach civil works was awarded to N.A. Degerstrom of Spokane, Wash.;

• Heap leach and pond liner installations awarded to American Environmental Group of Richfield, Ohio;

• Heap leach and pond liners have been purchased from Agru America of Fernley, Nev.;

• Diesel generators have been purchased from Empire Cat of Mesa, Ariz.; and

• Overland conveyor, grasshopper conveyors and radial stacker purchased Superior Industries of Prescott, Ariz.

Civil Works Complete

The project site has seen a significant transformation in the past few months with the completion of the site civil works for the crusher pad, ROM pad, laydown yard, Merrill Crowe facility, and ancillary roads. This work was performed by N.A. Degerstrom of Spokane, Wash.

Concrete Work

The concrete works encompass the Merrill Crowe and Refinery facilities, the crusher foundations and the diesel power station.

Heap Leach Civil Works

The heap leach earthworks commenced in early June and clearing and grubbing operations in the leach pad are well under way. Excavation and fill for grading in the West Event pond is essentially complete and this area is ready to receive liners.

Liners Installation

Lining of the West Event pond is expected to commence in early July when the first liner shipments are received. Portions of the heap leach pad were ready for lining in mid-July. The current schedule shows completion of the leach pad and pond liners by early September.

Crushing Plant Fabrication, Delivery Confirmed

The company also reports that Goodfellow Crushers and their partners KPI/JCI are making excellent progress on the fabrication of the Moss crushing plant. The initial plant components were scheduled for delivery in mid-July, with the final components on site by mid-August.

Powerline, Access Road ROW Progress

Two Right of Way (ROW) permit applications were submitted to the BLM for construction of a power-line partially on federal lands, and for eliminating vertical and horizontal curves and blind spots on the Moss Mine Access Road by widening onto adjacent federal lands.

The applications will be reviewed by the BLM team and items of environmental concern will be identified and then assessed for potential impacts. The major factors driving the applications are the elimination of diesel emissions to the atmosphere from on-site generators, and the increase in traffic safety for persons using the public County Access Road.

The applications were supported by a preliminary power-line design by Amec Foster Wheeler, Phoenix, Ariz., office and completed road reconstruction plans by Civil Works Engineering LLC of Kingman, Ariz. The Mohave County Engineering Department has approved the road re-construction plans and both city and county engineering have approved in principle the powerline design concept.

Sale of Waste Rock

The sale of mine waste rock for use as concrete aggregates has commenced in partnership with Tri-R Construction of Mohave Valley, Ariz. At present Tri-R is hauling 500 tons per day to a local concrete supplier, and the demand is growing for use as riprap and other commercial uses.

For more information, visit northernvertex.com.




Today's top stories

Blalock Crews Build TDOT's $67M Newport Bypass

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Equip Expo's Summer Giveaway Offers a Chance for Lifetime Trade Show Registration, Gift Card, Hotel Stay

Tennessee's Pugmill Systems LLC Expands Its Product Offerings to Include Concrete Plants

ASCENDUM Machinery Opens New Savannah, Ga., Facility


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA