List Your Equipment  /  Dealer Login

Population Growth Sparks $340M Treasure Valley Project

Tue August 27, 2019 - West Edition #18
Lori Tobias – CEG Correspondent


The Idaho Transportation Department (ITD) has kicked off a $340 million project on the largest highway in the state.
The Idaho Transportation Department (ITD) has kicked off a $340 million project on the largest highway in the state.
The Idaho Transportation Department (ITD) has kicked off a $340 million project on the largest highway in the state. The primary work will involve widening the Interstate, adding or modifying existing bridges, overpasses and interchanges. More than 31 million trips occur on I-84, with two-thirds of those taking place between Ada and Canyon Counties. The project is a continuation of an expansion project that got underway a decade ago, but was halted during the recession. Work was able to resume after the state legislature gave IDT the go-ahead to pursue bonding against future federal government funding through the Grant Anticipation Revenue Vehicle (GARV). The Interstate is the primary commuter route, and also an important freight route and the lifeblood of Idaho’s agriculture community.  The work is happening over 11 miles of I-84 in Ada and Canyon Counties, an area known as the Treasure Valley, the population hub of the state. The overall project is expected to continue through 2021 and 2022.

The Idaho Transportation Department (ITD) has kicked off a $340 million project on the largest highway in the state. The work is happening over 11 miles of I-84 in Ada and Canyon Counties, an area known as the Treasure Valley, the population hub of the state. It is the fastest growing area in Idaho, which is the largest growing state in the United States.

More than 31 million trips occur on I-84, with two-thirds of those taking place between Ada and Canyon Counties.

"It's all about size," said Jake Melder, ITD spokesman. "I-84 is just not big enough. Idaho is experiencing unprecedented growth and we're now finding this Interstate is insufficient to carry the demands we have."

The Interstate is the primary commuter route, and also an important freight route and the lifeblood of Idaho's agriculture community. The primary work will involve widening the Interstate, adding or modifying existing bridges, overpasses and interchanges.

"There is going to be one at Northside that is kind of a superstructure," Melder said. "That's going to be the biggest construction package we put out, and it should be going out in the coming weeks.

The overall project includes:

Karcher Overpass Specs

  • 276-ft., 7-in. long bridge
  • 43-ft. wide
  • 17-ft. minimum clearance of I-84 below

Four interchanges:

  • Franklin Boulevard Interchange (IC) (Nampa) — minor ramp modifications
  • Northside Blvd IC — complete rebuild from diamond configuration to single point urban interchange (SPUI)
  • Karcher/Midland IC — ramp modifications and add a SB lane on bridge
  • Franklin Road IC (Caldwell) — minor ramp modifications

Major bridges over I-84:

  • Karcher Road Overpass — complete replacement to allow additional I-84 lanes
  • Middleton Road Overpass — complete replacement to allow additional I-84 lanes
  • Ustick Road Overpass — complete replacement to allow additional I-84 lanes

Major Bridges on I-84 (referenced facilities run under the Interstate):

  • Union Pacific Railroad (east of Northside IC)
  • Mason Creek (west of Franklin Blvd IC)
  • Linden Street (east of Franklin Road IC)

The project is a continuation of an expansion project that got underway a decade ago, but was halted during the recession. Work was able to resume after the state legislature gave IDT the go-ahead to pursue bonding against future federal government funding through the Grant Anticipation Revenue Vehicle (GARV).

"That mechanism, we think, is going to be a wiser use of taxpayer funds because construction costs are on the rise," Melder said. "We've been able to get an excellent rate on our bonds and that means getting the work done sooner and getting the work done cheaper. Improved transportation means an improved economy. It's an excellent way of utilizing taxpayer funds."

One of the big challenges facing work crews is that the Interstate is already congested and at capacity. But ITD has made a commitment to not close lanes during commuting hours. To that end, crews worked last year to create extra wide shoulders where traffic can be shifted during construction.

"A lot of these bridges were built in the ‘60s and most don't accommodate the additional lanes underneath them, so we're going to be adding an additional travel lane and an auxiliary lane," Melder said. "Right now, with the bridge work that is being done and, again why we have these expanded shoulders, we're able to shift the lanes of travels. The abutment work on ends of bridges is not impactful on traffic. But we do have to have overnight closures, and when we're setting the bridge deck, we will have to close traffic because we don't want to be setting over traffic."

The overall project is expected to continue through 2021 and 2022. CEG




Today's top stories

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Muddy Water Dredging Christens Marlin Class Dredge

Indiana Officials Mark Start of 2024 Construction Season, Promote Safety

Leica Geosystems Launches its First Machine Smart Antenna — Leica iCON gps 120


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA