Seattle Streetcar Construction Costs Jump to More Than $252M

Tue September 25, 2018 - West Edition #20
Associated Press


Seattle Mayor Jenny Durkan halted the project in March due to rising costs.
(SeattleDOT photo)
Seattle Mayor Jenny Durkan halted the project in March due to rising costs. (SeattleDOT photo)

SEATTLE (AP) The cost of a Seattle streetcar project previously put on hold due to rising costs has soared to $252 million.

The Seattle Times reported in a story on Aug. 31 that a newly released consultant's report cited the increase for a 1.2-mi. (2-km) stretch intended to connect two existing streetcar lines.

That's a cost increase of more than $100 million from the first estimate in 2015.

Seattle Mayor Jenny Durkan said it's disappointing that the proper work to determine costs wasn't done from the start when the project was being planned.

Durkin in March halted the project called the Center City Connector due to rising costs. Officials also started an investigation into the project's management.

For more information, visit seattletimes.com.




Today's top stories

Blalock Crews Build TDOT's $67M Newport Bypass

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Equip Expo's Summer Giveaway Offers a Chance for Lifetime Trade Show Registration, Gift Card, Hotel Stay

Tennessee's Pugmill Systems LLC Expands Its Product Offerings to Include Concrete Plants

ASCENDUM Machinery Opens New Savannah, Ga., Facility


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA