List Your Equipment  /  Dealer Login

Speedy Gonzalez Zips Through Jobs With Ditch Witch Tools

Mon August 08, 2005 - West Edition
Construction Equipment Guide


Underground construction projects are more complex today than they once were, and utility contractors must be proficient in several disciplines to compete for the turnkey contracts that many project owners prefer.

Work must be done correctly and in accordance with specifications, even under difficult conditions when working against tight completion deadlines.

A recent fiber optic project completed in Phoenix, AZ, by Speedy Gonzalez Construction Inc. (SGC) is a good example. SGC was the primary contractor for construction of a 38-mile-long segment of AGL Networks’ Deer Valley North Loop. Based in Atlanta, AGL Networks constructs, owns and manages underground fiber optic networks that unite telecommunication service providers and their business customers.

The Deer Valley North Loop project is a part of AGL Networks’ 60-mile Phoenix network that circles primary commercial areas of Phoenix and Tempe, providing accessibility to the main COs, IXCs and carrier hotels. The network has new premium enhanced fiber available for custom configuration to customer-specified destinations.

SGC crews installed two 1.25-in. (3.17 cm) HDPE conduits and placed one cable with 144 fiber strands and one with 288 fiber count in the duct. The project also included 165, 3 by 5 ft. (.9 by 1.5 m) pull boxes, 40, 4 by 4 ft. (1.2 by 1.2 m) concrete vaults and restoration of all paved and landscaped surfaces that were disturbed during construction.

The project was broken into eight segments, said Salvador Gonzalez, owner of the company that bears his name.

The cable route passed through both residential and business areas and included four Arizona Department of Highway crossings, 54 crossings of major city streets, four canal crossings and crossed under four flood control channels.

Because of site conditions, 98 percent of the conduit placement was completed by horizontal directional drilling (HDD).

Directional drilling was the best, most cost efficient method for making street, highway and canal crossings, and greatly limited surface damage throughout other segments of the project, said Luis De La Cruz, SGC manager.

Drilling was completed with four Ditch Witch HDD units: a JT1720, two JT2720s and a JT4020.

Powered by an 85-hp (63.4 kW) diesel engine, the JT1720 develops 17,000 lbs. (7,711 kg) of pullback, 1,800 ft.-lbs. (8,006 N) of torque and spindle speeds to 200 rpm. The on-board fluid system can pump 25 gpm (94.6 Lpm) of drilling fluid.

The JT2720’s 125-hp (93.2 kW) turbocharged diesel engine and powerful hydraulics develop 27,000 lbs. (12,247 kg) of pullback, 3,200 ft.-lbs. (14,233 N) of torque, and spindle speeds to 225 rpm.

The 40,000-lbs. (16,143 kg) pullback JT4020 develops 5,000 ft.-lbs. (22,243 N) of spindle torque, and spindle speeds to 250 rpm. While still relatively compact, the model has plenty of power to pull in much larger conduit than was used on the North Loop project.

All three models are self-contained directional drilling systems mounted on rubber tracks. Built-in pipe racks hold enough drill pipe to complete most jobs, and automatic pipe makeup and breakout and pipe thread lubrication allow the operator to add or remove drill pipe without assistance from another crew member.

Hydraulic leveling and anchoring speed setup. All use Ditch Witch Electronics tracking equipment manufactured by The Charles Machine Works Inc., the same company that makes the Ditch Witch drilling equipment.

The project required 385 bores ranging in length from 150 to 600 ft. (45.7 to 182.8 m). Soil conditions ranged from ideal to wash cobble of various sizes. De La Cruz said all bores were drilled with standard slant-face Ditch Witch bits. Pilot holes did not require use of a reamer for enlargement for pulling in the small-diameter conduit.

When crossing or working close to existing buried utilities, pipe and cable that was physically exposed, crews confirmed its exact location before work proceeded. For potholing, SGC employed three FX30 Ditch Witch vacuum excavation units. Using high-pressure water, these “soft” excavation tools quickly make small potholes to uncover buried facilities. The units’ vacuum capabilities were used to keep work sites clear of drilling fluids.

The project was completed in 115 work days that included six-day work weeks.

“We worked nights only in areas where day time construction would hinder community activities,” said De La Cruz. “Most work around shopping centers, schools, and restaurants was done at night.”

Planning, permitting and coordination with various government agencies and other organizations was a complex task.

“At one time or another, we interfaced with 14 different agencies,” said De La Cruz. “Because the work was in urban areas, traffic control had to be implemented which required submission of control plans and their approval before work could proceed. And the job isn’t finished until each site has been completely restored.”

De La Cruz said success of any project depends on the cooperation of many people in many organizations, including those who support operations and help a contractor deliver promised services.

“Speedy Gonzalez Construction,” he emphasized, “is committed to completing work on schedule and within budget. To do that, we have qualified, dedicated employees, the right equipment, and the support of our suppliers.”

Because almost all of the project involved directional drilling, performance and support of HDD equipment was a critical factor.

“We could not have been so successful without the reliability of our Ditch Witch equipment and the support provided by our dealer, Ditch Witch of Southern Arizona,” said De La Cruz. “Ditch Witch is a true partner in helping us build our business in the underground utility construction market.”

SGC owner Gonzalez came to Arizona at the age of 16 and worked on his uncles’ farms. He entered utility construction as a laborer and in 1998 started his own company with three employees and one JT1720 drilling unit, which Gonzalez today affectionately calls “Abuelita,” meaning grandmother in Spanish. Today the company employs 60 men and women and has a fleet of specialized equipment for placement of wet and dry utilities.

“No job is too big or too small,” said Gonzalez. “We take great pride in addressing challenges, and when others say a job can’t be done, we find a way to do it. People are what make our company, and we are proud to say we have the hardest-working employees in the industry.” CEG




Today's top stories

Growing Interest in Construction Careers Among Younger People Means Jobs Filled, Deadlines Met

Larry Young Paving Tackles Grade-Separated Interchange in Texas

Caltrans, Crews Working to Repair Highway Landslides

FIRSTGREEN Industries Launches ROCKEAT Electric Skid Steer Loader

'Tiltrotator Effect' Increases as Energy Consumption Goes Down

VIDEO: Birmingham, Ala., Awarded $14.5M Fed Grant to Revitalize Its 'Black Main Street'

Pettibone Celebrates 75th Anniversary of Cary-Lift

Fay Preps Way for Pittsburgh International Airport Modernization Project








aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA