Create a CEG Account  /  CEG Login
☰



Tesla Gigafactory Making Quick Progress in Travis County

- West Edition #25
CEG

Bulldozers and other heavy construction equipment have been at work for weeks at the location of Tesla's future $1.1 billion electric vehicle factory in southeast Travis County.

The planned 4.5 million sq.-ft. factory will make Tesla's cybertrucks and Model Y electric crossover utility vehicles.

The site sits on 2,100 acres of land, just off Texas 130.

Tesla CEO Elon Musk first referred to the plant as “Cybertruck Gigafactory” since it’s also going to be the site where Tesla’s electric pickup truck is going to be produced.
(Joe Tegtmeyer photo)
Tesla CEO Elon Musk first referred to the plant as “Cybertruck Gigafactory” since it’s also going to be the site where Tesla’s electric pickup truck is going to be produced. (Joe Tegtmeyer photo)  

New footings were installed on the central “road,” new contractor trailers were erected; 9th & 10th columns were installed and many trucks delivered steel columns and beams.
(Joe Tegtmeyer photo)
New footings were installed on the central “road,” new contractor trailers were erected; 9th & 10th columns were installed and many trucks delivered steel columns and beams. (Joe Tegtmeyer photo)  

New footings were installed on the central “road,” new contractor trailers were erected; 9th & 10th columns were installed and many trucks delivered steel columns and beams.
(Joe Tegtmeyer photo)
New footings were installed on the central “road,” new contractor trailers were erected; 9th & 10th columns were installed and many trucks delivered steel columns and beams. (Joe Tegtmeyer photo)  

New footings were installed on the central “road,” new contractor trailers were erected; 9th & 10th columns were installed and many trucks delivered steel columns and beams.
(Joe Tegtmeyer photo)
New footings were installed on the central “road,” new contractor trailers were erected; 9th & 10th columns were installed and many trucks delivered steel columns and beams. (Joe Tegtmeyer photo)  

New footings were installed on the central “road,” new contractor trailers were erected; 9th & 10th columns were installed and many trucks delivered steel columns and beams.
(Joe Tegtmeyer photo)
New footings were installed on the central “road,” new contractor trailers were erected; 9th & 10th columns were installed and many trucks delivered steel columns and beams. (Joe Tegtmeyer photo)  

Construction crews install six large columns, steel structure for the second floor and the roof section is being constructed.
(Joe Tegtmeyer photo)
Construction crews install six large columns, steel structure for the second floor and the roof section is being constructed. (Joe Tegtmeyer photo)  

Travis County and the Del Valle school district helped lure the factory here by approving tax breaks sought by Tesla that are valued at a minimum of about $60 million combined. 
(Joe Tegtmeyer photo)
Travis County and the Del Valle school district helped lure the factory here by approving tax breaks sought by Tesla that are valued at a minimum of about $60 million combined. (Joe Tegtmeyer photo)  

Travis County and the Del Valle school district helped lure the factory here by approving tax breaks sought by Tesla that are valued at a minimum of about $60 million combined. 
(Joe Tegtmeyer photo)
Travis County and the Del Valle school district helped lure the factory here by approving tax breaks sought by Tesla that are valued at a minimum of about $60 million combined. (Joe Tegtmeyer photo)  

Travis County and the Del Valle school district helped lure the factory here by approving tax breaks sought by Tesla that are valued at a minimum of about $60 million combined. 
(Joe Tegtmeyer photo)
Travis County and the Del Valle school district helped lure the factory here by approving tax breaks sought by Tesla that are valued at a minimum of about $60 million combined. (Joe Tegtmeyer photo)  

Tesla CEO Elon Musk first referred to the plant as “Cybertruck Gigafactory” since it’s also going to be the site where Tesla’s electric pickup truck is going to be produced.
(Joe Tegtmeyer photo)
Tesla CEO Elon Musk first referred to the plant as “Cybertruck Gigafactory” since it’s also going to be the site where Tesla’s electric pickup truck is going to be produced. (Joe Tegtmeyer photo)  


Today's top stories

Beadier Construction Co. Nears Completion of I-15 Auxiliary Lane Project

Construction Equipment Guide's Richard McKeon Retires

Hunter Industries Progresses On I-37 Diverging Diamond Interchange

Wadsworth Brothers Nears End of Provo Bridge Project

W.Va. Begins Major Fort Hill Bridge Work

Lower Thames Crossing World's First Project to Use Volvo A40 Electric

The Operator's Guide to Compaction Fundamentals

California Board Invests $3.4B for 120 Transportation Projects





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.