List Your Equipment  /  Dealer Login

Tight Environmental Restrictions Mark Haverhill Bridge $102M Reconstruction

Thu June 06, 2019 - Northeast Edition #12
Ken Liebeskind -CEG Correspondent


An aerial view of trestle construction to provide access for Stage 1 bridge construction.
An aerial view of trestle construction to provide access for Stage 1 bridge construction.
An aerial view of trestle construction to provide access for Stage 1 bridge construction. Trestle construction on the north side of the Merrimack River to provide access for Stage 1 bridge construction. The contractor performs in-water work from a barge to drive piles. Drilled shaft installation, including a permanent steel casing. South abutment pile driving for Stage 1 northbound bridge construction.

A four-year project to widen and replace bridges for Interstate 495 north and south over the Merrimack River in Haverhill, Mass., began in September and will be completed in May 2022.

The northbound portion of the bridge will be rebuilt before the existing portion is demolished and will be followed by the completion of the southbound portion.

The plan is to construct a new three-span, continuous superstructure and the supporting piers/abutments and demolish existing bridges and remove substructures 2 ft. below the mudline.

Drilled shaft installation, including a permanent steel casing.

This project is replacing and widening existing bridges carrying Interstate 495 northbound and southbound over the Merrimack River in Haverhill to address structural and functional deficiencies. The bridge was built in 1961 and Mass DOT completed deck and steel repairs in August 2017 to ensure the bridges remain operational throughout replacement construction. The project area extends from approximately Exit 48 south of the bridges to approximately Exit 49 north of the bridges. Mass DOT will maintain three lanes of travel in each direction on I-495 North and South throughout construction with the exception of temporary off-peak lane closures and traffic shifts during demolition and construction.

The $102 million project, with 80 percent of the cost funded by the federal government and 20 percent by the state of Massachusetts, began with a temporary trestle installed and shafts drilled for the two pier and abutment foundations.

"There are tight environmental restrictions and we can only be in the water in the winter, so we built the trestle to get the foundations complete," said Matthew McCue, the project executive of SPS New England, the contractor that is overseeing the job. "Building the trestle was highly unusual for a highway project, but it's complete so now we're on to substructure work and preparing for beam erection."

The goal is to maintain a 30-ft. high by 70-ft. wide navigation channel of the river during construction and final condition.

The contractor performs in-water work from a barge to drive piles.

The job will be completed in three phases. The first involves construction of the northbound bridge, which should be completed in September. The second involves demolition of the current northbound bridge, which should be completed in November. Construction will resume in August, 2020, when a southbound crossover to the southbound section will be implemented. Then southbound demolition will be completed before construction of the new southbound bridge begins.

Maxwell Huber, a Massachusetts Department of Transportation spokesperson, said the northbound bridge will be partially built so that northbound traffic can be shifted onto it before the northbound bridge is demolished. Once the northbound bridge is complete, traffic in both directions will be shifted to it, while the old southbound bridge is demolished and the new southbound bridge is constructed.

The design-build project, which also includes HNTB, the design firm, was initiated to address structural and functional deficiencies of a bridge that is 58 years old and in dire need of replacement, according to McCue.

The bridge was built in 1961 with deck and steel repairs completed in 2017 to ensure the bridges remain operational during replacement construction.

South abutment pile driving for Stage 1 northbound bridge construction.

The bridges also will be widened to improve vehicle safety. The existing bridge is 52 ft. across for both north and south sections. The new northbound bridge will be 79.5 ft. across and the new southbound bridge will be 71.5 ft. across, according to Huber.

SPS will build a temporary cross over to get southbound traffic through the median during the first two phases of the project.

The construction equipment used on the job includes flexi floats, which are positioned in the river to support a 275-ton lattice boom crawler crane. The Terex HC275 is being used on the job along with 150-ton cranes.

A Soilmec R930 drill shaft for foundation work also is being used, along with 35-ton off road dump trucks and 10,000-lb. excavators, according to McCue.

Elements of the project also include roadway realignment, safety, signage and pavement marking improvements, landscape restoration and wetland mitigation.

The project will minimize temporary environmental vehicular impacts and temporary navigational lighting to USCG standards will be installed during construction in the water.

The timeline for the Haverhill Bridge replacement project includes three main stages:

  • Stage 1, Northbound bridge construction started in September, 2018 and will be completed September, 2019.
  • Stage 2, Northbound bridge demolition and phase two of the Northbound bridge construction starts September, 2019 and will be completed August, 2020.
  • Stage 3, Southbound bridge demolition and construction begins August, 2020 and will be completed September, 2021. Median restoration proceeds from September 2021 to June 2022 when the bridge restoration will be complete.

CEG




Today's top stories

Fay Preps Way for Pittsburgh International Airport Modernization Project

Volvo CE Continues to Perform, Transform During Slower Q1 2024

American Bridge Co. Leads Conn.'s East Haddam Swing Bridge Project

Growing Interest in Construction Careers Among Younger People Means Jobs Filled, Deadlines Met

Pettibone Celebrates 75th Anniversary of Cary-Lift

Common Ground Alliance Hosts Conference & Expo in Colorado On Preventing Utility Damages

Powerco Hosts Mecalac Road Show Event in Clinton, N.J.

Site Prep Inc. of NC Adds Milling Services to Its Existing Highway Infrastructure Capabilities


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA