List Your Equipment  /  Dealer Login

UDOT Completes More Than $1B in Projects

Tue December 29, 2020 - West Edition #1
Lori Tobias – CEG Correspondent


 UDOT highlighted six major projects, but the most notable is the $415 million widening and rebuilding of the I-15 technology corridor.  “We’ve accomplished a lot in 2020 and the work still presses on,” said John Gleason, UDOT public information officer.
 The largest project — I-15 technology corridor — featured the construction or reconstruction of 17 bridges. UDOT installed a new runaway truck ramp on U.S. 89 in Garden City, the first of its kind in the state. “We didn’t see any major hits in the construction schedule. That in and of itself was an accomplishment,” said John Gleason, UDOT public information officer.

In a year that saw its share of troubles, the Utah Department of Transportation (UDOT) is closing out on a high note — the completion of 135 projects valued at $1.05 billion.

"The fact that we were able to deliver all these projects on time and at budget is an accomplishment just because of all of the challenges we faced, here and around the world," said John Gleason, UDOT public information officer. "We thought the pandemic would have significant effects on construction and that we would have to shut down projects. That didn't happen. Other than a few minor delays here and there, we didn't see any major hits in the construction schedule. That in and of itself was an accomplishment."

UDOT highlighted six major projects, but the most notable is the $415 million widening and rebuilding of the I-15 technology corridor. The project, which got underway in May 2018 and finished this fall, included the widening of four lanes to six in each direction, the construction or reconstruction of 17 bridges, the first frontage road of its kind in the state, replacing asphalt with concrete and a new multi-use trail system connecting to nearby regional trails.

"People think of UDOT as the department of roads," Gleason said. "It's transportation, not only focussed on moving vehicles, but moving people. Everytime we look at these projects we look to see if there is something we can do to encourage walking or biking. We're trying to encourage people not only to drive, but to use other modes of transportation — walking, biking, public transit. As much growth as we are experiencing here in Utah, we're not going to be able to keep up with that growth simply by adding roads. So we're looking at other forms of transportation."

UDOT also installed a new runaway truck ramp on U.S. 89 in Garden City, the first of its kind in the state. The state-of-the-art ramp uses a series of cable nets to stop runaway trucks descending Logan Canyon. The project came after several accidents.

"Just about two and a half years ago, we had a semi that lost its brakes, or for whatever reason, crashed into a sporting goods store there; the driver was killed," Gleason said. "Later, we had within a matter of weeks, two more. We don't know why it didn't happen in years past. Any time we have a serious crash like that, we look into what we can do to improve safety. We began looking at a design and got funding secured pretty quickly. This is a cable system. If they do lose their brakes, when the truck enters, the cables wrap around the truck and slow it down until it comes to a complete stop."

Gleason noted that when a UDOT director was in Wyoming looking at a similar system, a truck lost its brakes and he was able to see the system in action. It saved the driver's life.

Other Highlights of 2020:

  • U.S. 40; Strawberry Passing Lanes — the project extended the westbound passing lanes on U.S. 40 near Strawberry Reservoir an additional 5 mi.; repaved 16 mi. and constructed a new wildlife undercrossing.
  • I-80; S.R. 201 to S.R. 36 Auxiliary Lane — improved traffic flow in western Salt Lake and eastern Toole Counties by adding a new exit-only lane on westbound I-80 between S.R. 201 and S.R. 36.
  • I-15; Exit 16 Interchange — widened 3 mi. of I-15 along with S.R. 9 under the freeway near Hurricane. Crews also replaced the two I-15 bridges over S.R. 9, redesigned the freeway on-ramps and improved storm drain systems.
  • S.R. 10; 3200 South to 1150 South — widened S.R. 10 south of Prince to add a center turn lane and wider shoulders. Crews also added new sidewalks, curbs and gutters; and upgraded the drainage system and underground utilities.

"We've accomplished a lot in 2020 and the work still presses on, Gleason said. "We have some big ones coming up. One is the widening and the reconstruction of U.S. 89 in Davis County. That's a really important road. Again, it's a place we are seeing a lot of growth and we need to make smart decisions for the future. We're adding express lanes on I-15 in Davis and Weaver Counties. We already have the longest express lanes in the country. We have three Bangerter Highway exchanges to make it more freeway-like. We've got a lot of projects in the hopper." CEG




Today's top stories

Blalock Crews Build TDOT's $67M Newport Bypass

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Equip Expo's Summer Giveaway Offers a Chance for Lifetime Trade Show Registration, Gift Card, Hotel Stay

Tennessee's Pugmill Systems LLC Expands Its Product Offerings to Include Concrete Plants

ASCENDUM Machinery Opens New Savannah, Ga., Facility


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA