List Your Equipment  /  Dealer Login

Work More Than Half Done to Open N.C. Ferry Channel

Tue February 19, 2013 - Southeast Edition
Construction Equipment Guide


MANNS HARBOR, N.C. (AP) The contractor dredging the channel used for the Hatteras-Ocracoke ferry run is more than halfway done with the project.

A statement from the ferry division of the N.C. Department of Transportation said the contractor hired by the U.S. Army Corps of Engineers has removed 102,723 cu. yds. (78,537 cu m) of material to a required depth of 10 ft. (3 m). The department said that amounts to 65 percent.

Operations on the Dredge Richmond were halted Jan. 30 and 31 due to high winds.

Shoaling in the channel has been an ongoing issue, but Hurricane Sandy, two back-to-back nor’easters and several winter storms have contributed to the problem. DOT has said it could be several weeks before the dredging takes care of the problem and the route returns to a normal schedule.




Today's top stories

Blalock Crews Build TDOT's $67M Newport Bypass

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Equip Expo's Summer Giveaway Offers a Chance for Lifetime Trade Show Registration, Gift Card, Hotel Stay

Tennessee's Pugmill Systems LLC Expands Its Product Offerings to Include Concrete Plants

ASCENDUM Machinery Opens New Savannah, Ga., Facility








aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA