World Trade Center cost rises by $4B over 4 years

Fri February 10, 2012 - National Edition
Chris Hawley - ASSOCIATED PRESS


NEW YORK (AP) The agency building the new World Trade Center has let costs get out of control, with the estimated price tag soaring nearly $4 billion over the last four years, auditors said Tuesday.

Navigant Consulting said the project is now expected to cost $14.8 billion, 35 percent more than the last estimate, of $11 billion, in 2008.

New York Gov. Andrew Cuomo and New Jersey Gov. Chris Christie ordered the review of the World Trade Center site’s owner, the Port Authority of New York and New Jersey, after the agency’s board voted to raise bridge and tunnel tolls in August.

The auditors said the Port Authority, which runs area transit hubs including Kennedy and LaGuardia airports, is ”a challenged and dysfunctional organization suffering from a lack of consistent leadership ... insufficient cost controls and a lack of transparent and effective oversight of the World Trade Center program that has obscured full awareness of billions of dollars in exposure to the Port Authority.’

The Port Authority has lost millions of dollars in revenue because of lower traffic at the ports, airports and river crossings it operates, and the World Trade Center has suffered a number of setbacks since rebuilding began after the Sept. 11, 2001, terror attacks destroyed its Twin Towers.

The company that is laying steel for the main tower has run into financial problems. A mistake in the design means the Port Authority will have to spend millions of dollars on temporary loading docks for the building. And the builders of the Sept. 11 museum are fighting with the agency over construction costs.

The Port Authority’s new director, Patrick Foye, said Tuesday the agency was taking the auditing firm’s recommendations seriously and would begin an overhaul of its structure.




Today's top stories

North Causeway Bridge Offers Innovation, Congestion Relief for Fort Pierce, Fla., Motorists

Missouri's $284M Chester Bridge Under Construction

Mecalac Offers Telescopic Wheel Loader to Improve Stability, Mobility in Material Handling Applications

Chicago Bears Announce Plans for New Enclosed Stadium

Oshkosh Corporation to Acquire AUSA

Webuild Ready to Rebuild Collapsed Baltimore Bridge

Crews Complete Covington, Georgia Community Project

Alabama AGC Announces BUILDSouth Award Winners








aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA