Wadsworth Brothers Targets Year-End Completion of UDOT's I-15 Shepard Lane Interchange
Wadsworth Brothers is nearing completion of UDOT’s $151 million I-15 Shepard Lane Interchange project in Farmington, Utah, set for year-end finish....
Read story
A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.
Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.
Wadsworth Brothers is nearing completion of UDOT’s $151 million I-15 Shepard Lane Interchange project in Farmington, Utah, set for year-end finish....
Read story
Skanska USA is nearing completion of the $105M Cordilleras Behavioral Health Facility in Redwood City, featuring 100,000 sq ft. of net-zero energy buildings....
Read story
Trinity Green LLC and Atlanta Demolition LLC are set to complete the demolition of the former Wellstar Atlanta Medical Center campus by late 2026. This massive project involves extensive asbestos abatement and careful coordination while preparing the site for future mixed-use redevelopment....
Read story
The $86.1M Route 18 upgrade in East Brunswick, N.J., includes pavement rehab, drainage improvements, adaptive traffic signals and pedestrian safety features. Construction spans 4.14 mi. with new sidewalks, utilities and stormwater systems. Expected completion is late 2027, easing congestion and enhancing safety for drivers and pedestrians....
Read story
Ferrovial’s Webber nears completion of the $365 million Interstate 10 widening project in Colorado County, Texas. The upgrade expands 12 mi. from two to three lanes each way, replaces 18 bridges and enhances safety and drainage. Expected to finish July 2027, it will improve traffic flow and serve as a vital hurricane evacuation route connecting Houston Austin and San Antonio....
Read story
The $91 million Dutch Point Viaduct rehabilitation on I-91 southbound in Hartford began in 2025 and will extend the bridge’s lifespan by 25 years. Led by J.F. White Contracting, the project upgrades structural elements, replaces the deck and parapets, and improves load capacity while maintaining traffic flow through strategic closures and coordination....
Read story
Webber LLC is halfway through the $189.8 million Texas Department of Transportation U.S. 59 upgrade from Shepherd to Cleveland, enhancing safety and supporting a future Interstate 69 designation. The project includes bridges, frontage roads and main lane expansion, using advanced materials and equipment to ensure durability and improve traffic flow while accommodating hurricane evacuation needs....
Read story
Suncore is nearing completion of the Utah Department of Transportation's $91.1 million Interstate 15 Hamilton Fort rebuild in Iron County, Utah. The project adds a northbound climbing lane upgrades the Hamilton Fort interchange with a roundabout and reconstructs the northbound bridge. It is designed to improve safety traffic flow and support freight tourism on this key corridor. Completion is expected in late fall....
Read story
North Georgia Concrete leads the $100M Russell Creek Reservoir project in Dawson County Ga, replacing an outdated dam with a modern 110-ft structure. The new reservoir will hold 1.37 billion gallons of water to improve supply reduce flood risks and support growth. Construction includes advanced engineering, environmental safeguards and public amenities, slated for completion in 2027....
Read story
TxDOT is widening nearly 20 mi. of U.S. 87 in Hartley and Moore counties from two lanes to four to improve safety and increase capacity. The $99 million project includes new lanes, drainage upgrades, and road rebuilding, benefiting heavy truck traffic. Construction began in February 2026 and is expected to finish by 2030....
Read story
Pulice - a Flatiron Dragados company is set to complete the $45.6 million Mesa Gateway Airport Runway 12R-30L reconstruction project ahead of schedule and below budget. The project rebuilds the 10,401-ft. runway with new concrete, asphalt shoulders, lighting and drainage, enhancing safety and operations at this key commercial airport....
Read story
Security Paving Co. is completing a $23.2 million rehabilitation of 1 mi. of Interstate 5 in Burbank and Los Angeles with five 55-hour weekend closures. The project uses advanced planning and Cat equipment to replace concrete pavement, improve safety and ride quality and meet Caltrans’ 40-year design lifespan goals while maximizing productivity and safety....
Read story
J. Lee Milligan is upgrading a 2.5-mile section of U.S. 60 in Hereford, Texas, in a $44 million Texas Department of Transportation project. Improvements include asphalt resurfacing, ADA sidewalk upgrades, drainage enhancements and safety features. The project started in March 2026 and is set for completion in late 2029 to improve traffic flow and road durability....
Read story
VTrans is nearing completion of the $31.7M Colchester Exit 17 overhaul, improving safety and traffic flow at I-89 Exit 17 and Chimney Corner. The project includes a new U.S. 2 bridge, ramp upgrades, added turning lanes and bike lanes to reduce congestion and enhance mobility, funded by the Federal Highway Administration....
Read story
Pulice Construction is progressing on TxDOT’s $320 million project to widen and reconstruct 6 mi. of I-10 in Colorado County Texas. The upgrade includes expanded lanes new bridges and improved safety features to support growing traffic and hurricane evacuation, with completion expected by January 2029....
Read story
Ames Construction is replacing two aging bridges on U.S. 60 near Superior, Ariz., with a $70M ADOT project. The new Queen Creek Bridge and Waterfall Canyon box culverts will improve safety and traffic flow. Construction began in 2024 and is expected to finish by 2028, addressing geological challenges and increasing future traffic capacity....
Read story
The Webber–United JV is advancing Phases 4 and 5 of the $620M I-16/I-75 interchange project in Macon Georgia. These phases include widening highways, upgrading ramps and bridges, and improving traffic flow. Expected to finish by 2026, the project enhances safety regional freight movement and local commutes on this busy corridor....
Read story
TxDOT's $53.2 million Brazos River bridge project on I-69 in Sugar Land is nearly 60% complete. The phased demolition and reconstruction address riverbank erosion by extending the bridge 700 feet north. SER Construction leads, aiming for completion in November 2027 while maintaining traffic flow and ensuring safety throughout the process....
Read story
VTrans is rehabilitating the Quechee Gorge Bridge in Hartford, Vt., with Harrison & Burrowes. The $25M project includes extensive maintenance and suicide prevention measures. Scheduled for completion in fall 2026, the bridge will see structural improvements and widened walkways, enhancing safety....
Read story
Texas FM 1960 widening project nears completion, easing congestion in Lake Houston area. $128M project widened roadway from 4 to 6 lanes with new overpass bridge and improved traffic control plans. Challenges included utility relocation and contaminated soil, facing delays but maintaining safety and progress in construction....
Read storyGet weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.
Construction Equipment Guide
470 Maryland Drive
Fort Washington, PA 19034
800-523-2200
Construction Equipment Guide covers the nation with its four regional newspapers, offering construction and industry news and information along with new and used construction equipment for sale from dealers in your area. Now we extend those services and information to the internet. Making it as easy as possible to find the news and equipment that you need and want.
Contents Copyrighted 2026, by Construction Equipment Guide, which is a Registered Trademark, registered in the U.S. Patent Office. Registration number 0957323. All rights reserved, nothing may be reprinted or reproduced (including framing) in whole or part without written permission from the publisher. All editorial material, photographs, drawings, letters, and other material will be treated as unconditionally assigned for publication and copyright purposes and are subject to Construction Equipment Guide’s unrestricted right to edit and comment editorially. Contributor articles do not necessarily reflect the policy or opinions of this publication.
Read our privacy policy here.
Mastodon