Construction on the I-64 Fort Hill “Eugene A. Carter Memorial” Bridge recently began in Charleston, W.Va. for preparation of major upcoming bridge and highway restoration.
Triton Construction Inc. — the West Virginia native contractor awarded the $74.5 million job — began removing the existing median barrier, constructing median crossovers and installing temporary barriers a just few short weeks ago in early October 2026.
The 50-year-old bridge received minor maintenance repairs to the bridge throughout the years, including minor structural repairs, deck patching, paint and the installation of a new roadway surface. But with approximately 100,000 vehicles using the bridge daily, however, the West Virginia Department of Transportation (WVDOT) recognized the need for major rehabilitation to the bridge in 2025, after noticing major road decay and massive potholes. Subsequently, emergency repairs and asphalt overlay occurred in late 2025 and, shortly after, WVDOT announced the full-deck replacement in January 2026.
Three Phases of Fort Hill Bridge Project
With the design, funding and project awarded earlier in 2026, construction is now under way. While the two temporary crossovers between the Montrose Drive and Oakwood Road interchange as well as between the Lee Street and Begley Avenue interchange are under way, the WVDOT plans to begin major construction by early next year and has the project broken down into three major phases.
Major repairs to the bridge include structural work, bridge deck replacement, structural steel repair to the bridge's arch, barrier wall replacement and repair work to the concrete piers. In addition, Triton will replace bridge deck and barrier walls to the four ramps providing access to the bridge.
During this first phase, all traffic will shift eastbound while Triton repairs the westbound side, as well as the Oakwood eastbound entrance ramp, Virginia Street westbound entrance ramp and I-64 westbound to Oakwood Road ramp. As of now, phase one is expected to run from January 2027 to July with anticipation of beginning phase two in July and running through until December.
After completing the westbound repairs, traffic will begin using the I-64 westbound section while the eastbound side undergoes repair in phase two. As the Oakwood entrance ramp eastbound will remain closed, the I-64 eastbound to Virginia Street ramp and Virginia Street entrance ramp to I-64 westbound will also close for repair.
Finally, phase three of this project includes removing the temporary barriers and crossovers created, construction of the new median barrier and final pavement markings and signage installation. This will complete the renovations and is expected to occur in the spring of 2028.
WVDOT Prioritizes Fort Hill Bridge Project
Although the initiated program by WVDOT includes approximately 50 additional projects to the Charleston Metropolitan area, the nearly $75 million Fort Hill Bridge project acts as the largest project in the area and currently one of the largest in the state, among the ongoing $3.35 billion Corridor-H and upcoming $135 million I-79 Chaplin Hill Gateway projects. Also, the Fort Hill Bridge is recognized as the most heavily traveled bridge in the state and acts as a crucial passthrough and a vital pathway to downtown Charleston.
Knowing the importance of the bridge, State Transportation Secretary Todd Rumbaugh said, “The WVDOT considers the I-64 Fort Hill Bridge Rehabilitation Project the top priority for the Charleston area and is working closely with our project partners to minimize the impact to the traveling public while also providing a safe work zone for the contractor.”
In addition, the WVDOT's site stated, “In addition to the signed detour routes, WVDOT also recognizes that there are other options to cross the Kanawha River and is looking at strategic improvements, prior to this construction project, to help aid the flow of traffic in and around the Charleston area. These improvements including over 6 miles of paving on I-64, WV 25, and US 60; Patrick Street Bridge repairs; and upgrades at 110 traffic signals along the detour and anticipated diversion routes.”
With careful planning, implementing multiple construction phases, road closures during nights and weekends, as well as using effective detours to the fullest, the WVDOT hopes to mitigate the traffic congestion despite the highly trafficked area.











