List Your Equipment  /  Dealer Login

Yazoo River Canal Widening Work Nears Completion

Mon January 28, 2008 - Southeast Edition
Eric Brown -VICKSBURG POST


VICKSBURG, Miss. (AP) The widening of the Yazoo River Diversion Canal, a project long seen as a must to keep the Port of Vicksburg viable for business expansion but historically plagued by funding and other delays, is now scheduled to be complete by the end of February.

The completion date for the $5.3 million endeavor, which has been on the drawing board for more than 10 years, is a month later than had been predicted this summer.

Phillip Hollis, a senior project manager with the U.S. Army Corps of Engineers had predicted last summer a January conclusion. He said high river stages delayed the initial dredging of the canal this summer, and recently, high waters have threatened progress again.

“It [the high river stage] has definitely been a factor, but we’re still currently dredging,” he said. “It’s just one of those things that you have to expect to deal with.”

Hollis said the newer of the project’s two dredges has been able to continue operation since the river stage has stayed below 31 ft. The highest river stage during recent high waters was 28.6 ft., on Dec. 28 and 29.

The second dredge won’t be used until the river stage is 21 ft. or lower.

Both dredges are being operated by the Cleveland, Miss.-based 4-H Construction with assistance from Inland Dredging of Dyersburg, Tenn.

Lester Cruse, port captain at Magnolia Marine Transport, declined to predict when the 21-ft. mark might be reached.

“It’s a tough thing to predict,” Cruse said Jan. 10. “All of this water is coming down from flooding around the Ohio River, and that’s expected to slow down sometime soon. But then again, it’s supposed to rain up around Memphis soon. You just never know.”

Delays in the canal-widening project go back well beyond the recent high waters.

Officials began looking to widen the canal in the early 1990s, when the tonnage moving to and from the Mississippi River and E.W. Haining Industrial Center increased from 3 million to 5 million tons. A lack of funding kept the project on the drawing board.

Then in 2006, the Vicksburg Board of Mayor and Aldermen unanimously voted to begin acquiring land for the widening, but all three bids from construction companies came in too high. Such options as going back to Congress to lobby for more money or scaling back the project by deleting work north of the Glass Bayou became possibilities.

Finances for the undertaking began improving in October when the county, agreeing to pay $56,168 more of the $3.6 million total cost, helped bridge a funding gap of about $150,000, depending on the city of Vicksburg securing funds from Community Development Block Grant sources for its share, which it did just days later.

The project continued to take shape in January 2007, when Warren County supervisors informally gave District 5 Supervisor Richard George, board president, authority to release $15,000 to $18,000 being held in escrow to close the purchase on the 7.23 acres (2.9 ha) of land in anticipation of widening the canal.

The canal’s construction also received a boost in February when President Bush signed a $464 billion spending bill that closed out 2006’s unfinished budget business, which helped cover a $615,000 shortfall in the project if Congress failed to act on the resolution.

Finally in March, the bid for the canal-widening project was awarded to 4-H Construction.

Construction crews have been in motion along the canal since early July, beginning with clearing the landscape on Desoto Island. The dredging began a few weeks later.

Hollis said dredging the canal includes excavating the canal’s soil with the dredges’ cutter heads, and then pumping the soil to the mouth of the canal and into the Mississippi River.

He said the project calls for the expansion of the canal dug by the Corps about 105 years ago.

The 150-ft.-wide (48 m) canal will be widened to 250 ft. (76.2 m) from the canal’s junction with the Mississippi River to Glass Bayou, about 1.5 mi. (2.4 km) north. Then from Glass Bayou to the Vicksburg Harbor, which is a little less than a mile, the canal would gradually decrease to 200 ft. (61 m) wide.

“The project’s purpose is to allow four-barge tows to travel the canal in all river conditions, which is not the case right now,” Hollis said.

Tows generally can push one or two barges on the canal now, depending on the river stage.

Hollis said traffic in the canal has not been disrupted by the dredging and should not be during the remainder of the work.




Today's top stories

Growing Interest in Construction Careers Among Younger People Means Jobs Filled, Deadlines Met

Larry Young Paving Tackles Grade-Separated Interchange in Texas

Caltrans, Crews Working to Repair Highway Landslides

FIRSTGREEN Industries Launches ROCKEAT Electric Skid Steer Loader

'Tiltrotator Effect' Increases as Energy Consumption Goes Down

VIDEO: Birmingham, Ala., Awarded $14.5M Fed Grant to Revitalize Its 'Black Main Street'

Pettibone Celebrates 75th Anniversary of Cary-Lift

Fay Preps Way for Pittsburgh International Airport Modernization Project








aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA