Ahwatukee Waterline Relocation Work for South Mountain Freeway Delayed

June 19, 2018 - West Edition #13
Construction Equipment Guide

The Arizona Department of Transportation and Connect 202 Partners had planned to complete the work in June to avoid connecting the new water main to city of Phoenix mains along Desert Foothills Parkway and 24th Street during summer months when water demand is greater.  (AZDOT photo)
The Arizona Department of Transportation and Connect 202 Partners had planned to complete the work in June to avoid connecting the new water main to city of Phoenix mains along Desert Foothills Parkway and 24th Street during summer months when water demand is greater. (AZDOT photo)

Work to relocate a water main located within the path of the Loop 202 South Mountain Freeway has been delayed, causing Liberty Lane traffic restrictions to remain in effect through this summer.

Since March, crews working for Connect 202 Partners, the freeway developer, have been digging trenches along Liberty Lane between Desert Foothills Parkway and 24th Street to install a specially designed 4-ft.-wide pipe that will run more than a mile.

This work has limited Liberty Lane traffic to eastbound traffic, with the westbound and center lanes closed.

The Arizona Department of Transportation and Connect 202 Partners had planned to complete the work in June to avoid connecting the new water main to city of Phoenix mains along Desert Foothills Parkway and 24th Street during summer months when water demand is greater. But the process of obtaining the pipe took several weeks longer than anticipated, and the first portion of the pipe was installed in late May.

Connect 202 Partners will need to connect the new water main this fall to avoid potential outages to residents.

The traffic restrictions will be lifted once installation is complete and Liberty Lane has been repaved.

For more information, visit SouthMountainFreeway.com.


Today's top stories

Seabrook Bridge Construction Moves Toward October 2028 Completion

Yuba Pass Gets Two Bridge Replacements

TxDOT Widens 20 Mi. of U.S. 87 to Improve Safety, Increase Capacity

Core Equipment Group Strengthens Leadership Team

Liebherr R 915 Compact G8, R 917 Compact G8, R 920 Compact G8 Excavators Now Available

Diamond Mowers Strengthens Dealer Support Through Demo Days, Champion Training Events

Volvo Increases Use of Recycled Materials in New Heavy-Duty Truck Models

E2 Systems Turns Wheel Loaders Into High-Production Material Placers


 





×

Stay Ahead of the Market

Get weekly equipment news, auction updates, and dealer insights — trusted by thousands of industry professionals.



39.96118 \\ -82.99879 \\ Columbus \\ OH \\ US \\ 43215