Darien, Conn., Officials Approves Great Island Road Design, But Key Questions Remain

Thu December 07, 2023 - Northeast Edition
CT Examiner


In an attempt to open Darien, Conn.'s Great Island to the public under an "aggressive" timeline, officials in the coastal town approved a new design for the estate's access road at the end of November despite lingering questions about its costs and scope.

Following Darien's $85 million purchase of the 60-acre property earlier this year, then-First Selectman Monica McNally vowed to open Great Island to the public next summer. Now leading the committee charged with opening and designing the island, she urged officials to approve a new entrance road to meet that deadline.

"This is what we need to do to get people onto the island," said McNally, a selectman and chair of the Great Island Advisory Committee.

At the Nov. 28 committee meeting, engineers with Redniss & Mead, a Stamford-based land surveying firm hired by the town, presented a design which would widen the existing 16-ft.-wide entry road to 22 ft. to accommodate two-way traffic.

It was the only time members would publicly review the plan before sending it to the Darien Planning and Zoning Commission, Environmental Protection Commission, and the Architectural Review Board for approval, according to CT Examiner, a statewide online news service.

Despite unanswered questions about cost, construction and the future of the road, the committee unanimously recommended it for review to keep with the tight timeline.

"We are in this aggressive schedule to make sure that we can get under construction in the springtime," Ed Gentile, the city's public works director, told committee members.

The Great Island access road begins at a four-way intersection with Pear Tree Point Road, Goodwives River Road, and Rings End Road, before ending at a traffic circle which leads visitors into the property.

Under the design, the town would construct a new 5-ft.-wide sidewalk, remove and replant trees to provide a buffer for nearby residential properties, and shift the road to avoid overlap with a privately owned portion of the island.

"We're not just widening the driveway," explained Craig Flaherty, principal engineer with Redniss & Mead, "[but] replacing the driveway and moving it over."

Several Project Unknowns Remain

Before Darien bought Great Island, it was subdivided and owned separately by two wealthy families, the Steinkrauses and the Zieglers, for more than a century, noted CT Examiner. The Steinkraus family sold its property — which includes numerous houses, a horse stable and a boat dock — to Darien in May, and the Ziegler family is in the process of selling its portion to a private buyer.

Flaherty said the access road abuts the Ziegler property to the west, meaning that all construction, including the road widening, new sidewalk, and vegetation removal, must occur on the east side of the road. To offset impacts on the two private properties to the roadway's east, the town would plant new trees in their yards.

But when newly elected First Selectman Jon Zagrodzky asked the engineers about the cost of construction, Flaherty said he had not yet prepared an estimate. However, he warned officials of an arduous construction process.

"There's a lot of scope here between the roadway, the curbs, the walls, the drainage, the utilities, the landscaping, the light poles, the electrical for the light poles," Flaherty elaborated. "I'm going through this kind of starting at $1 million."

He admitted, though, that he was "a really bad estimator, and we should leave it to the market to give you better estimates."

In addition to the cost, the potential for two-way traffic throughout the rest of the island is also unknown.

While the immediate entry road will be expanded, Flaherty said the remainder of the 60-acre island is still too narrow for two-way access. The rest of the road would be maintained as a one-way loop that begins and ends at the traffic circle in the "near term," he added.

That led Great Island Advisory Committee member Jeffrey Taebel to question what the narrow roads could mean for alternative means of access. If the planned sidewalk ends at the traffic circle, he asked, how would pedestrians and cyclists safely traverse the rest of Great Island?

Flaherty answered by saying that the rest of the roadway is beyond his firm's scope.

Surveyor Awaiting Great Island Master Plan

CT Examiner reported that over the next month, various town bodies will review and vote on Darien's pending purchase of the traffic circle, currently owned by the Ziegler family. Once the almost $800,000 purchase is approved, the town will own all of the roads needed for public access to Great Island and can fully design the roadways and sidewalks.

"We're best served right now to get what we need approved by solely focusing on just what we can do on the property that we control today," Flaherty explained.

Aside from the pending sale, he said his surveying firm is waiting on Darien officials to outline a comprehensive plan for the property before drafting additional plans for road widening or sidewalks.

As of the beginning of December, the town did not have an overarching plan for the future of the island, according to CT Examiner. While officials undertook an envisioning process prior to purchasing the land, Zagrodzky has said it is up to the advisory committee to hire an architecture company to create a development plan.




Today's top stories

Two Firms Give Burned Highway New Life

Latest Case Launches Help Construction, Utility Contractors Maneuver Tight Labor Markets, Congested Job Sites

Contractors' Plate Full On Interstate 35 in Texas

Skanska Awarded Contract to Develop Offshore Wind Port at South Brooklyn Marine Terminal

Micron Announces Agreement to Build Factory in Boise, Idaho

Leica Geosystems Launches its First Machine Smart Antenna — Leica iCON gps 120

Brightline Breaks Ground On $3B Vegas-to-California Rail

Oregon to Deploy First-of-Its-Kind, In-Cab Safety Alerts


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA