D.C. Mayor Unveils Design, Timeline for $441M Frederick Douglass Memorial Bridge

The bridge is part of the South Capitol Street Corridor Project, the largest public infrastructure project in Washington, D.C.’s history.

Wed August 16, 2017 - National Edition
Construction Equipment Guide


The new $441M bridge design includes three above-deck arches that capture the District’s arch history, two piers that will appear to float in the river, and four pedestrian overlooks.
The new $441M bridge design includes three above-deck arches that capture the District’s arch history, two piers that will appear to float in the river, and four pedestrian overlooks.
The new $441M bridge design includes three above-deck arches that capture the District’s arch history, two piers that will appear to float in the river, and four pedestrian overlooks. D.C.’s largest public infrastructure construction project in history will create jobs, improve connection between Anacostia and downtown.

Washington, D.C., Mayor Muriel Bowser has unveiled the design and timeline of the new Frederick Douglass Memorial Bridge. The bridge is part of the South Capitol Street Corridor Project, the largest public infrastructure project in Washington, D.C.'s history.

The project includes replacing the 68-year-old bridge and reconstructing the Suitland Parkway/I-295 interchange. The Mayor was joined by Congresswoman Eleanor Holmes Norton, District Department of Transportation (DDOT) Director Leif Dormsjo and members of the South Capitol Bridgebuilders team.

“Today, we are taking a huge step toward improving the District's infrastructure and building a safer, stronger DC,” said Bowser. “The Frederick Douglass Memorial Bridge and the entire South Capitol Street Corridor Project will create jobs for District residents and provide an iconic gateway between Anacostia and Downtown D.C. When completed, this will be a tremendous structure and a fitting memorial for a remarkable American icon.”

The new Frederick Douglass Memorial Bridge will be built approximately 100 ft. from the current bridge. Other project elements include:

• creating new traffic ovals east and west of the river that connect South Capitol Street, Suitland Parkway and Anacostia Drive and South Capitol Street, Potomac Avenue and Q Street, SW, respectively;

• improving drainage and storm water management; and

• reconstructing the Suitland Parkway/Interstate 295 interchange, which includes replacing the I-295 bridges over Howard Road, Suitland Parkway and Firth Sterling Avenue.

In addition, the new bridge design includes three above-deck arches that capture the District's arch history, two piers that will appear to float in the river, and four pedestrian overlooks.

“After fighting for more than a decade to secure more than $200 million in federal funding to build a new Frederick Douglass Memorial Bridge, what a relief it is to see that work come to a head with today's contract announcement and design unveiling,” said Norton. “South Capitol Street is a vital gateway to the nation's capital and a gateway to greater opportunities for DC neighborhoods east of the Anacostia River. As we prepare to commemorate the bicentennial of Fredrick Douglass' birth next year, now is the perfect time to celebrate moving forward on this memorial bridge named in his honor.”

“The South Capitol Corridor Project promises to significantly improve the mobility of the more than 70,000 vehicles, bicyclists, and pedestrians who cross the Frederick Douglass Memorial Bridge each day,” said Dormsjo. “The new bridge will simultaneously enhance the District's transportation infrastructure, boost the local economy, and support the ongoing revitalization of the Anacostia Waterfront and development on both sides of the river.”

The South Capitol Street Corridor Project will be completed in two phases, and the District has signed a $441 million contract with South Capitol Bridgebuilders — a joint venture of Archer Western Construction LLC and Granite Construction Company, with AECOM as the lead designer — for phase one of the project. HNTB is assisting DDOT with the program management and construction management.

The District achieved special Federal Highway Administration approval to require that the contractor ensure 51 percent of all new project-related jobs are performed by D.C. residents. Additionally, the contractor must subcontract at least 13 percent of the total contract value for design and 22 percent of the total contract value for construction to certified disadvantaged business enterprises (DBE), far outpacing DBE goal setting for previous capital projects.

“I welcome the announcement of a design and contract award for the new Frederick Douglass Memorial Bridge, an important step in improving accessibility to the District of Columbia for Fifth District commuters,” said Congressman Steny H. Hoyer (MD-05). “I was pleased to help secure funding for the new bridge through the Congressional appropriations process. The South Capitol Street Corridor Project is vital to efforts to strengthen our local economy, and the new Frederick Douglass Memorial Bridge will help continue to revitalize the surrounding neighborhood. I thank Mayor Bowser for her leadership on this project, and I look forward to continuing to work with District officials to see this project to completion.”

The South Capitol Street Corridor Project is one in a series of transportation, environmental, economic, community, and recreation projects developed by the larger Anacostia Waterfront Initiative (AWI) Program. From the Tidal Basin to the city's northeast border with Maryland, the 30-year, $10 billion AWI Program is transforming the shores of the Anacostia River into a world-class waterfront and enriching nearby communities.

Construction is expected to begin at the end of 2017 and last through 2021.

For more information, visit newfrederickdouglassbridge.com and anacostiawaterfront.org.




Today's top stories

VIDEO: Hawkins Takes On Nebraska's $130M I-80 Expansion

Webber Ahead of Plans On I-10 Widening in Texas

HEVI H Series: A Transformative Opportunity for Dealers in Electric Construction Equipment

Volvo Holiday Lights, Fan Voting Begin

Progress Continues On $250M Columbus LOT Project

VIDEO: Norwalk, Conn.'s Fire-Damaged I-95 Overpass Reopens Early, $3.2M Under Budget

Wolf America Introduces New Wheel Loaders to U.S. Market

Vermeer BorePlan Enhances HDD Planning, Execution, Documentation