List Your Equipment  /  Dealer Login

DelDOT Constructs State's First Bulb-Tee Girder Bridge

Mon January 22, 2018 - Northeast Edition #2
Brenda Ruggiero


The $28.3 million contract calls for the construction of a new bridge over the Christina River to the Wilmington Riverfront and U.S. 13.
The $28.3 million contract calls for the construction of a new bridge over the Christina River to the Wilmington Riverfront and U.S. 13.
The $28.3 million contract calls for the construction of a new bridge over the Christina River to the Wilmington Riverfront and U.S. 13. The first spliced prestressed bulb-tee girder bridge in Delaware is currently being built near Wilmington under the direction of the Delaware Department of Transportation (DelDOT). The project creates a new multi-modal crossing of the Christina River to add another access point to Wilmington Riverfront attractions. It also will improve access to U.S. 13, I-495, and I-95. The project began in May 2017, and will continue through the spring of 2019. According to Jason N. Hastings, M.C.E., P.E., state bridge engineer of DelDOT, it is currently on schedule. The contract was awarded to RE Pierson Construction Company of Woodstown, N.J., with Nick Hetrick in charge. The bridge will include two 12-ft. travel lanes and shoulders, as well as a 14-ft. wide bicycle/pedestrian path. The path will connect to the Riverfront walkway and other bicycle/pedestrian facilities in the area. The aesthetic nature of the bridge was another issue. According to Jason N. Hastings, M.C.E., P.E., state bridge engineer of DelDOT, it is currently on schedule.

The first spliced prestressed bulb-tee girder bridge in Delaware is currently being built near Wilmington under the direction of the Delaware Department of Transportation (DelDOT).

The project creates a new multi-modal crossing of the Christina River to add another access point to Wilmington Riverfront attractions. It also will improve access to U.S. 13, I-495, and I-95.

The project began in May 2017, and will continue through the spring of 2019. According to Jason N. Hastings, M.C.E., P.E., state bridge engineer of DelDOT, it is currently on schedule.

The $28.3 million contract calls for the construction of a new bridge over the Christina River to the Wilmington Riverfront and U.S. 13. The contract was awarded to RE Pierson Construction Company of Woodstown, N.J., with Nick Hetrick in charge.

The bridge will include two 12-ft. travel lanes and shoulders, as well as a 14-ft. wide bicycle/pedestrian path. The path is will connect to the Riverfront walkway and other bicycle/pedestrian facilities in the area.

“There are several challenges associated with the project,” Hastings said. “In an effort to reduce the contract costs to the department, RE Pierson worked with Hardesty and Hanover and with the assistance of DelDOT and RK&K to redesign the foundations to 30 in. and 24 in. prestressed concrete pile (from drilled shafts). Driving pile of that dimension and length (up to 100 ft.) requires specialized equipment, which R.E.P. has experience with.”

Another challenge noted by Hastings was the erection and setting of the spliced prestressed bulb-tee girders, which required additional supports, detailed erection design and plans, splicing design, and post tensioning.

“The existing ground conditions required the implementation of several different ground improvement and mitigation techniques,” Hastings said. “These included a sizable surcharge area — quarantined for 150 days; the use of lightweight foamed concrete as abutment backfill; the use of expanded polystyrene as an embankment material; and the installation of controlled modulus columns — rigid inclusions to support the weight of one of the approach embankments.”

The aesthetic nature of the bridge was another issue noted by Hastings. This includes the extensive use of Formliner concrete on all of the exposed bridge elements. It will be stained to look like natural rock. There also is an extensive decorative lighting package.

“The project is located on a brownfield site, where the challenges of working with and managing potentially contaminated soil, debris and groundwater takes extensive daily coordination with various stakeholders,” Hastings noted. “The project's location is adjacent to a highly-populated urban business district that requires coordination and cooperation from all stakeholders to ensure that construction does not disrupt or detract from their operations.”

Hastings reported that the project includes 12,100 cu. yds. of excavation, 22,000 cu. yds. of borrow import for the embankment, 3,500 cu. yds. of concrete, and 800,000 lbs. of rebar.

In addition, there are 69 – 24 in. prestressed concrete piles averaging 80 ft. in length and 52 – 30 in. prestressed concrete piles averaging 100 ft. in length.

Also included are 1,300 cu. yds. of expanded polystyrene embankment; 1,900 sq. yds. of CMC rigid inclusion ground improvements; 340 linear ft. of MSE wall; and 8,000 sq. ft. of Formliner.

CEG




Today's top stories

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

Volvo CE Continues to Perform, Transform During Slower Q1 2024

American Bridge Co. Leads Conn.'s East Haddam Swing Bridge Project

Pettibone Celebrates 75th Anniversary of Cary-Lift

Common Ground Alliance Hosts Conference & Expo in Colorado On Preventing Utility Damages

Going Beyond Diversity: Star Equipment's Rental Advantage

Volvo CE Launches Updated L30, L35 Compact Wheel Loaders


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA