List Your Equipment  /  Dealer Login

Lattice Boom Crawler Crane Aids in Renovation of Motorway Bridge

Mon August 06, 2018 - National Edition
terex


Steil Kranarbeiten, a crane operating company from Trier, considered its CC 3800-1 crawler crane the best choice in the demolition of the old Illtal motorway bridge on the A1 at Eppelborn in Germany.
Steil Kranarbeiten, a crane operating company from Trier, considered its CC 3800-1 crawler crane the best choice in the demolition of the old Illtal motorway bridge on the A1 at Eppelborn in Germany.

Heavy loads, large equipment and limited space are usually not a good recipe for lifting operations. This was the situation in the demolition of the old Illtal motorway bridge on the A1 at Eppelborn in Germany, which had to give way to a modern structure. Steil Kranarbeiten, a crane operating company from Trier, considered its Terex CC 3800-1 crawler crane with Split Tray the best possible tool because of the very limited space.

The lack of space on the construction site proved to be a special challenge right from the start.

"The setup of the crane required a sophisticated logistics concept, whereby we delivered the parts just-in-time with 52 transports in order to install them immediately, because there was insufficient storage space for all parts on the construction site which was limited by a stream and a railway line. To make matters worse, rail traffic was maintained during the construction work," explained René Perlich, head of large cranes at Steil Kranarbeiten, whose team configured the CC 3800-1 for the upcoming lifts with a 256 ft. (72 m) SSL1 boom and 37.7 ft. (11.5 m) Superlift radius as well as 248 tons (225 t) of counterweight on the crane plus 358 tons (325 t) of Superlift counterweight.

Concrete had to be poured in the bank area first in order for the unstable soil around the stream to be able to support the CC 3800-1 safely. Subsequently, bongossi ties also were laid at the work area of the crane for even pressure distribution. This preparation work provided sufficient stability for the crane.

Unconventional Setup

The Steil team had to choose rather unconventional approaches even for the assembly of the Superlift mast and boom out of necessity. The Superlift system structure could not be installed in one piece on the crane as usual, since the required space of 118 ft. (36 m) on the construction site was simply not available.

"We had just about [65 feet] available to us", said Perlich, whose technicians therefore installed the superlift system "piece by piece."

The installation of the 236 ft. (72 m) long main boom was another challenge. It had to be set up over the stream due to lack of space.

After the crane was ready for lifting in the intended time frame, the actual work could begin. This proceeded according to the following plan: The bridge was initially divided into 23 to 69 ft. (7 up to 21-m)-long and 39 ft. (12-m)-wide segments, which were to be lifted one after the other by the CC 3800-1 and slewed behind it and lowered down. At the storage area, the bridge parts were later broken down further and transported by truck.

"The heaviest load was superstructure 2, which weighed in at around [380 tons]," said Perlich, who operated the crane himself. "And this lift definitely demonstrated that we were absolutely right in choosing our CC 3800-1. Unlike competing models, we still had a lifting capacity reserve of around 10 percent with this crane."

Split Tray Saves Time

Above all, the equipment features of the CC 3800-1 crane with the divisible Split Tray superlift system frame proved to be advantageous in Eppelborn, since the radius of the heavy parts created some challenges due to limited space on the construction site.

"We picked up the heavy loads with extremely wide radii of up to [118 feet] and then placed them behind the crane with a reduced radius of about [46 feet]," said Perlich.

The use of the Split Tray saved a lot of time due to the simple uncoupling of unnecessary counterweight. The assist crane was needed only after completing the lifts for stacking of the counterweights.

Thus the Steil team was able to handle this job quickly and exactly as planned despite the challenging conditions on site.

About Steil Kranarbeiten GmbH & Co. KG

"Heavy things made light" is the slogan behind Steil Kranarbeiten's comprehensive range of services. The company, which is certified as per DIN EN ISO 9001:2000 and Safety Certificate Contractors (SCC) standards, relies on a highly specialized fleet with modern machines, as well as a highly-qualified team. Its services include not only special-purpose crane, but also recovery and towing services for trucks and buses and industrial and company relocation services. The company is headquartered in Trier, and additional Steil branches are located in Wittlich and Saarwellingen in Germany, as well as in Frisange in Luxembourg.

The company's customer base includes well-known companies such as the Bitburger brewery, BASF, Saarstahl, Deutsche Steinkohle, Dillinger Hütte, and all important wind turbine manufacturers.

For more information, visit www.steil-kranarbeiten.de

About Terex

Terex Corporation is a global manufacturer of lifting and material processing products and services delivering lifecycle solutions that maximize customer return on investment. Major Terex brands include Terex, Genie, Powerscreen and Demag. Terex solutions serve a broad range of industries, including construction, infrastructure, manufacturing, shipping, transportation, refining, energy, utilities, quarrying and mining. Terex offers financial products and services to assist in the acquisition of Terex equipment through Terex Financial Services.

For more information, visit www.Terex.com.




Today's top stories

Growing Interest in Construction Careers Among Younger People Means Jobs Filled, Deadlines Met

Larry Young Paving Tackles Grade-Separated Interchange in Texas

Caltrans, Crews Working to Repair Highway Landslides

FIRSTGREEN Industries Launches ROCKEAT Electric Skid Steer Loader

'Tiltrotator Effect' Increases as Energy Consumption Goes Down

VIDEO: Birmingham, Ala., Awarded $14.5M Fed Grant to Revitalize Its 'Black Main Street'

Pettibone Celebrates 75th Anniversary of Cary-Lift

Fay Preps Way for Pittsburgh International Airport Modernization Project


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA