Money Doubts Delay Work on Century-Old Jersey Rail Bridge

Mon October 29, 2018 - Northeast Edition #22
Associated Press


The century-old Portal North Bridge over the Hackensack River
(Governor Chris Christie's Office/Tim Larsen photo)
The century-old Portal North Bridge over the Hackensack River (Governor Chris Christie's Office/Tim Larsen photo)

NEWARK, N.J. (AP) Preliminary work continues on a key choke point on the rail corridor into New York as a funding dispute delays the start of full construction.

Workers were scheduled to put up a 200-ft. utility pole Oct. 20 at the century-old Portal North Bridge over the Hackensack River. The pole will carry power lines to support trains passing into and out of New York.

The bridge causes delays for thousands of rail travelers when it gets stuck open after boats pass under. It's scheduled to be replaced at a cost of roughly $1.7 billion.

The project awaits federal funding to move to the construction phase. Officials had hoped to begin construction by late this year, but federal transportation officials have feuded with project sponsors over the federal government's share of the cost.




Today's top stories

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Muddy Water Dredging Christens Marlin Class Dredge

Indiana Officials Mark Start of 2024 Construction Season, Promote Safety

Leica Geosystems Launches its First Machine Smart Antenna — Leica iCON gps 120


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA