List Your Equipment For Free  /  Seller Login

Pittsburgh's Andy Warhol Bridge Undergoes $25M Reno

Mon October 02, 2017 - Northeast Edition #20
Brenda Ruggiero


The three “Sister Bridges” that are part of the Pittsburgh, Pa., city skyline are undergoing a major rehabilitation project, and the Andy Warhol (7th Street) Bridge is the first to undergo the process.
The three “Sister Bridges” that are part of the Pittsburgh, Pa., city skyline are undergoing a major rehabilitation project, and the Andy Warhol (7th Street) Bridge is the first to undergo the process.
The three “Sister Bridges” that are part of the Pittsburgh, Pa., city skyline are undergoing a major rehabilitation project, and the Andy Warhol (7th Street) Bridge is the first to undergo the process. The Andy Warhol Bridge was the first self-anchored suspension bridge in United States. The project began on Aug. 8, 2016, and is currently on schedule to be complete by Nov. 17, 2017. The initial value of the project was $25,391,749.45, and the current value is reportedly $25,416,849.29. Funding comes from federal, state and county sources.

The three “Sister Bridges” that are part of the Pittsburgh, Pa., city skyline are undergoing a major rehabilitation project, and the Andy Warhol (7th Street) Bridge is the first to undergo the process. The other bridges are the Roberto Clemente (Sixth Street Bridge) and the Rachel Carson (Ninth Street Bridge). All three bridges are currently owned and maintained by Allegheny County.

The Andy Warhol Bridge is actually the second bridge to be placed at the site, replacing the 1884 Gustav Lindenthal Suspension Bridge, as mandated by the 1889 River and Harbor Act. It was the first self-anchored suspension bridge in United States, and construction began with wood pile driving in 1925 by American Bridge Company. Rivets and built-up plates also were used in the construction.

The project began on Aug. 8, 2016, and is currently on schedule to be complete by Nov. 17, 2017. The contract was awarded to Brayman Construction, Saxonburg, Pa., with Kevin Meade serving as the project manager.

The initial value of the project was $25,391,749.45, and the current value is reportedly $25,416,849.29. Funding comes from federal, state, and county sources.

The contract includes the following:

• Deck replacement;

• Total repainting of the superstructure in Aztec gold;

• Steel repairs (fascia connections, floor beam connections, stiffening girder, sidewalk brackets, and tower repairs);

• Installing sloped plate and curb to keep moisture from accumulating along existing stiffening girder;

• Installing new bridge lighting to match original light fixtures;

• Repairing buckle plates, refurbishing suspension tower bearings, replacing existing bearings/tie-down linkages at Piers 1 and 4;

• Repairing river pier footings and installing scour protection;

• Replacing expansion dams with neoprene strip seal dams;

• Pointing masonry joints in piers;

• Repairing/replacing utility conduits and bracing;

• Installing new scuppers and downspouting;

• Installing approach slabs and milling and overlaying existing roadway approach; and

• Converting bridge from four-lane section to three-lane section

“The first challenge was to erect a work platform beneath the bridge to allow access to perform painting and steel repairs,” said Aimie M. Downs, director of communications of Allegheny County.

“This platform had to be low enough to allow access beneath the stiffening girders but high enough to allow access to the numerous repairs to stringers and floorbeams.

“The main problem occurred in the 180-ft. wide navigation channel beneath midspan. The U.S. Coast Guard and Waterways Association required 40-ft. height clearance above normal pool elevation. Following several meetings with the Coast Guard, the contractor received approval to provide 39-ft. of clearance by adding additional support points to the work platform and by modifying his vacuuming procedures for spent abrasive blast material to minimize dead load sag. Notifications were issued to river traffic and the contractor monitored marine radio communication and provided daily updates on clearance height when river levels changed.”

Downs noted that the bridge has numerous areas that have tight access clearances. The first area is inside the stiffening girders, which have significant deterioration due to water and road salt entering via the curb plate along the roadway. This curb plate was removed to allow easier access, and a new sloped curb plate with waterproof access hatches is being installed to minimize the amount of standing water that may enter the stiffening girder.

Another reported tight area is inside the two towers. Each tower consists of two built-up H sections 4-ft. deep. The exposed ends of the tower have non-structural cover plates that have limited access openings. The painting contractor used specialized blasting nozzles and spray heads to successfully perform this work without entering this confined space.

“Keeping the bridge to current code requires some innovative solutions, especially when the bridge has undergone several past rehabs,” Downs said. “Maintaining the historical nature of the structure also requires items such as tension control bolts to mimic rivets and placement of caulking to reduce water infiltration through multiple plies of steel plates.”

Downs noted that since this project is the first of three sister bridges that will be rehabilitated, consideration must be given to how any repair decision will affect the remaining two bridges.

The Warhol Bridge and its two sister bridges are self-anchored suspension bridges. Downs noted this places the two longitudinal stiffening girders in compression and requires unique bearings at the ends of both girders.

“These unique bearings consist of an articulated arm that is pin connected to the stiffening girder and to an eye-bar anchorage system,” she said. “This configuration allows for thermal expansion/contraction of the bridge while resisting any vertical downward or uplift loads which are induced by traffic live loads on the bridge deck.”

The project is replacing all four bearings with new bearing assemblies that will have rock anchors to increase the tie-down capacity. This work also requires temporary support at the bearings, and the contractor developed an innovative method to utilize the new permanent anchors to provide temporary tie-down capacity before being transferred into permanent condition.

A unique aspect of the bridge noted by Downs is that the south tower is on roller pins that allow the tower to move as the entire bridge expands or contracts to temperature changes. These roller pins are contained in a grease box at the base of the tower. The grease will be removed and the roller pins steam cleaned. After the pins have been inspected, a new grease box will be installed and new grease added to ensure that the bridge can continue to properly adjust to temperature changes.

Major subcontractors for the project include Advantage Steel and Construction; Southern Road and Bridge; Power Contracting Co.; Steel Core Construction Inc.; and Specialty Water Services.

Major equipment used on the job for abrasive blasting of existing structural steel includes an ARS DC45 45,000 cfm dust collector; an ARS 54 recycling unit; and an ARS 56 recycling unit.

Equipment for bridge deck removal includes a Cat 336E L hydraulic excavator with slab crab bucket and a Cat 262 skid steer loader. For structural steel repairs, equipment includes a Shuttlelift CD 3300 8.5 ton carry deck (crane) and a Genie GTH-B44 telehandler.

The project includes 222,000 lbs. of epoxy coated reinforcing steel; more than 200 tons of repair steel; and 1,371 cu. yds. of deck concrete.

The Rachel Carson Bridge will be next in the process, taking about two years to complete, and the Roberto Clemente Bridge will be last, expected to be finished in 2021.

CEG


Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Protecting Delaware Memorial Bridge

Widespread Catastrophic Damage From Hurricane Awaits Repair Crews in SE States

Flatiron, Dragados JV Set to Finish Major Job in Corpus Christi

JCB Celebrates 20 Years of Engine Making

Robert H. Finke & Sons Holds Open House at New Colchester, Vt. Facility

Snyder Civil Leads Way to Provide Clean Water, Safe Communities, More

Today's Security Tech Helps Contractors Combat Jobsite Theft

Komatsu Company Stores East Holds Open House in Pennsylvania


 







39.04690 \\ -77.49030 \\ Ashburn \\ PA