List Your Equipment  /  Dealer Login

San Diego's Genesee Ave. Taking Shape

Traffic accommodations being made for Genesee Avenue Overpass in San Diego.

Mon January 23, 2017 - West Edition
Chuck Harvey


Caltrans photo
Work is progressing on a $105.2 million I-5 at Genesee Avenue Interchange Project.
Caltrans photo Work is progressing on a $105.2 million I-5 at Genesee Avenue Interchange Project.
Caltrans photo
Work is progressing on a $105.2 million I-5 at Genesee Avenue Interchange Project.  Caltrans photo
Crews will replace the existing six-lane Genesee Avenue overpass with a 10-lane bridge. Caltrans photo
Work is progressing on a $105.2 million I-5 at Genesee Avenue Interchange Project.  Caltrans photo
The University of California at San Diego has been involved in planning the project to ensure minimal disruption to the nearby campus during construction. Caltrans photo
Construction started in early 2015 and should wrap up in fall of 2017.  Stage 4 includes road and bridge construction; widening of Genesee Avenue; bike path construction; building of retaining walls; and construction of new ramps.

Work is progressing on a $105.2 million I-5 at Genesee Avenue Interchange Project where crews will replace the existing six-lane Genesee Avenue overpass with a 10-lane bridge that will accommodate greater traffic demands on the north coast of San Diego.

It is a city of San Diego project managed by the California Department of Transportation. The University of California at San Diego has been involved in planning the project to ensure minimal disruption to the nearby campus during construction.

Construction started in early 2015 and should wrap up in fall of 2017. Funding is provided through Federal Highway Administration, city of San Diego, Caltrans, San Diego Association of Governments (SANDAG) and University of California at San Diego programs.

The project is a part of a broader improvements plan for I-5 in San Diego's North Coast Corridor. In addition to replacing the overcrossing, the project includes widening the freeway access ramps, adding an auxiliary lane in the northbound direction on I-5 between Genesee Avenue and Roselle Street, and constructing a new separated bike path.

"It will improve east and west traffic flow on Genesee Avenue," said Arturo Jacobo, project manager of I-5 North Coast Corridor for the California Department of Transportation District 11.

The project will provide links to pubic transportation and employment centers, hospitals and the University of California at San Diego. In doing so, the project is expected to greatly improve the movement of people and goods through the area.

New Interchange Bicyclist, Pedestrian Friendly

In addition to providing more lanes, the new Genesee Avenue overpass will features bike lanes and sidewalks. The project includes widening the freeway access ramps at Genesee Avenue and Sorrento Valley Road, widening Genesee Avenue in both directions near I-5 to provide new through and turn lanes, and construction about 3 mi. (4.8 km) of bicycle paths in both directions from Roselle Street to Voigt Drive.

A bike path will be built along the west side of I-5. The path will link with the Sorrento Valley COASTER commuter train station with University of California at San Diego and area businesses.

The project will include native, drought-tolerant, self-sustaining landscaping. More than 640 native trees will be planted and will be irrigated with recycled water.

Flatiron West Is Contractor

Flatiron West Inc. of Chino, Calif., is contractor for the I-5, Genesee Avenue project.

The project has 22 subcontractors. Major names include AVAR Construction Inc. of Freemont, Calif.; Calmex Engineering Inc. of Bloomington, Calif.; Perry Electric of San Diego; Marina Landscaping of Anaheim, Calif.; Griffith Co. of Brea, Calif.; Gerdau Reinforcing Steel of San Diego; and Condon Johnson & Associates of Oakland.

Shahbaz Alvi is project engineer; Arturo Jacobo is project manager; Allan Kosup is corridor director; and Dave Pound is resident engineer.

About 150 workers are on the job each day. Crews work on both day and night schedules.

Five Stages of Construction

Stage 4 is under way. It includes road and bridge construction; widening of Genesee Avenue; bike path construction; building of retaining walls; and construction of new ramps.

Workers are demolishing the old Genesee Avenue overpass; installing drainage systems; and paving the southern half of the new Genesee Avenue overpass.

Stage 5 will feature construction of the other half of the new Genesee Avenue overpass, building of a pedestrian crossing and an asphalt-concrete rehab on I-5 at the location.

The project is currently on schedule and at budget.

Heavy Equipment Is in Full Operation

Cranes, excavators, bulldozers, backhoes, motorgraders and super 10 haul trucks are being utilized on this job.

Crews will apply 3,370 cu. yds. (2,576.5 cu m) of Portland cement concrete and 41,400 tons (37,557 t) of asphalt cement. Concrete and asphalt removed from the project is being ground up and recycled into class 2 base.

No dirt had to be brought in or removed to complete the project.

Impacts to Local Area

Motorists should expect overnight lane closures at times. Pedestrians will not be allowed within the project limits. Southbound bike access will be maintained via the I-5 shoulder.

A preconstruction community outreach program was developed to inform residents, businesses, motorists and the general public about the project's construction impacts. The communication plan includes a project website, a traffic demand management component, a 1-800 phone number and a single point of contact for answers to construction questions.

Project Will Increase Mobility

Planners report that the project will improve east and west traffic flow on Genesee Avenue. It also will improve access to and from I-5.

Planners expect the project to be important in job and population growth in the area. The project also makes it easier to build future carpool lanes on I-5. - CEG




Today's top stories

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Muddy Water Dredging Christens Marlin Class Dredge

Indiana Officials Mark Start of 2024 Construction Season, Promote Safety

Leica Geosystems Launches its First Machine Smart Antenna — Leica iCON gps 120


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA