List Your Equipment For Free  /  Seller Login

Tampa Airport Sees $2B Expansion

Mon August 14, 2017 - Southeast Edition #17
Cindy Riley


As part of the largest renovation to Tampa International Airport since it opened in 1971, construction crews in Florida are continuing work on Phase I of a massive master plan expansion.
(Aerial Innovations Inc. photo)
As part of the largest renovation to Tampa International Airport since it opened in 1971, construction crews in Florida are continuing work on Phase I of a massive master plan expansion. (Aerial Innovations Inc. photo)
As part of the largest renovation to Tampa International Airport since it opened in 1971, construction crews in Florida are continuing work on Phase I of a massive master plan expansion.
(Aerial Innovations Inc. photo) At an estimated cost of  $971 million,  the first phase includes a 2.6 million sq.-ft. rental car center, a 1.4-mi. automated people mover, a main terminal/concessions overhaul  and smaller support projects.
(Tampa International Airport photo) The work is part of a more than $2 billion, long-term renovation and expansion that will improve the passenger experience over the next 10 years.
(Tampa International Airport photo) A rendering of the automated people mover station at the main terminal and outdoor terrace.
(Tampa International Airport rendering )

As part of the largest renovation to Tampa International Airport since it opened in 1971, construction crews in Florida are continuing work on Phase I of a massive master plan expansion. At an estimated cost of $971 million, the first phase includes a 2.6 million sq.-ft. rental car center, a 1.4-mi. automated people mover, a main terminal/concessions overhaul and smaller support projects.

“We broke ground in November 2014, and expect to be finished next year,” said Danny Valentine, Tampa International Airport spokesman. “We have a lot of construction across our campus, but we are an airport first, and providing a high level of customer service for our passengers is a top priority.”

The work is part of a more than $2 billion, long-term renovation and expansion that will improve the passenger experience over the next 10 years. It also will allow the airport to ultimately double its passenger traffic to 34 million. For staff, anticipating potential customer issues is crucial.

“Whenever possible, we try to minimize construction impacts,” said Valentine. “This is done through the use of additional signage, as well as additional guest service representatives. We also try to keep construction behind walls and out of sight or schedule the work during off-hours, including overnight when fewer guests are around.”

During the expansion, areas within the main terminal and surrounding roadways have been affected. Valentine noted that travelers don't seem overly concerned about closures, delays and other inconveniences.

“We've performed well,” said Valentine. “We continue to rank among the top airports in America in terms of customer satisfaction, as we did prior to construction. We track passenger satisfaction internally with our WiFi construction survey. Every time a passenger logs on, we ask them to complete a survey. The survey shows that only about three percent of passengers are moderately to heavily impacted by construction.”

For airport officials, keeping visitors out of harm's way is crucial.

“The airport has a robust safety program, in addition to safety programs by each of our design-builders,” said Valentine. “We have quite a bit of work around passengers, for example, in our main terminal and on our roadways.

“We do extensive pre-task planning, and make sure all parties are at the table to discuss potential issues.”

Planning for future generations of travelers was another major consideration.

“We expect our passenger numbers to continue to grow into the future and we want to be ready for them. When we started this project, we were at our near capacity on many of our roadways, curbsides and in our main terminal. Since then, our passenger numbers have increased, and we are expecting to hit record passenger numbers this year. The Tampa Bay region is growing as a whole, and it's important that the airport, a major economic engine, continues to grow with it,” said Valentine.

“It's a tremendously exciting period for Tampa International Airport. We are getting better every day and taking big strides. This project will continue TPA's legacy of innovation and customer service.”

The 270,000 sq. ft. undergoing renovations on the third floor of the main terminal is the equivalent of four-and-a-half football fields. More than 55,000 sq. ft. will be added to the terminal, including more than 23,000 sq. ft. for new outdoor terraces.

The project includes the renovation of two dozen of the airport's elevators, and the replacement of 1,112 linear feet of escalators. Crews also are placing approximately 114,000 sq. ft. of new tile flooring.

The rental car facility will be large enough to hold more than 5,300 vehicles at a time. The center features eight 25,000 gal. fuel tanks and 30 car washing stations At its peak, it can handle 1,541 rentals and 1,650 returns per hour.

An estimated 200,000 cu. yds. of concrete, which amounts to 25,000 truckloads, is required to build the automated people mover and rental car center. The facilities will be built with 14,000 tons of steel, including 9,000 tons of rebar and 5,000 tons of structural steel.

The automated people mover features 7,300 ft. of track on its way from the main terminal to the rental car center. A typical trip is expected to take about four minutes. The initial people mover is designed to carry 2,700 passengers per hour, although it could handle up to 6,500 per hour in the future.

In late 2011, Tampa International Airport officials began the process of updating the master plan for the airport's 3,300-acre campus. The final plan, approved in 2013, outlines three phases of expansion and allows a “build as demand dictates” approach to growth, with phases based on passenger volume.

The project is expected to create or save nearly 9,000 construction-related jobs. To date, more than four million total hours have been worked on Phase I. Understandably, coordinating all the work taking place is no small task, and staying on course is critical.

“The project baseline schedule was very compressed from day one,” said Tom Skinner, project director, TIA ConRAC & APM Infrastructure Projects. “The overall schedule allowed 10 months to clear and relocate the more than 40-acre ConRAC site and the 1.4 miles APM Guideway alignment of existing improvements, followed by 12 months to construct the four-level, cast-in-place 2.6 million sq.-ft. ConRAC structure and the cast-in-place APM Guideway. We have the remaining 12 months to complete the exterior enclosures and interior finishes for the four APM stations and the ConRAC CSB/Cores/QTA.

“The identification of existing underground utilities was a very painstaking process, as the airport's as-built information was not guaranteed. That drove a lot of soft dig work scope upfront to allow for the design to relocate. The overall length of the APM Guideway and square footage of the ConRAC were two very daunting cast-in-place concurrent work scopes to complete in a 12-month duration. The exterior enclosure and finish-out was and continues to be performed under joint access conditions with the APM System supplier's installation work scope.”

The rental car center is the second largest aspect of the early activity on site. Also included in Phase 1 work is the construction of 69 new shops and restaurants in the main terminal and at the airsides, as well as the renovation of the main terminal transfer level and various ancillary support projects.

“We have completed major site work, building foundations, structure and exterior enclosures. The ongoing work scopes currently being performed include interior finishes, equipment start-up and testing, final site work/grading, landscape and irrigation, site paving, initial punch lists and building code official final acceptance inspections.”

Amid the assortment of cranes, lifts and other heavy machinery on site, crews are incorporating a variety of materials during Phase I work, including concrete curbed asphalt pavement with some CIP paving, cast-in-place concrete and structural steel structures and foundations, glazed aluminum curtainwall, metal panel, precast, CMU exterior enclosures, metal standing seam roofs, tile and terrazzo flooring, metal ceilings, phenolic and resin wall panels, chillers and cooling towers.

Approximately 250,000 cu. yds. of dirt will be moved during Phase I construction. The confirmation of the location of all the existing UG utilities and improvements, as well as the ConRAC and APM Guideway structures is considered the most time-consuming part of the work.

Skinner said that despite a good deal of rain, weather has not really been a factor

“This project took a lot of communication and coordination between the four design builders and the airport's operations and end users. Realizing that this was an airport first and a construction project second sometimes made the work very challenging. Hillsborough County Aviation Authority has done everything reasonably possible to allow the construction to proceed efficiently and sequentially, notwithstanding this realization.”

In mid-July, the airport made way for a dozen train cars designed for the new SkyConnect. All 12 cars, as well as a maintenance vehicle, were placed onto the guideway by crane. The SkyConnect will connect TPA's main terminal to the economy garage and new rental car center. The system will open to the public in early 2018, after extensive testing.

“The SkyConnect builds on Tampa International Airport's legacy of innovation and customer service,” said Joe Lopano, airport CEO. “The train will allow the airport to continue to grow in its existing footprint, while taking millions of vehicles off our roadways and giving rental car customers access to more options than ever before.”

Officials marked the arrival of the SkyConnect cars with an event at Port Tampa Bay. Speakers included airport and port officials, along with Florida Gov. Rick Scott, Tampa Mayor Bob Buckhorn, Japan Consul General Ken Okaniwa and Aviation Authority Chairman Robert Watkins.

Gov. Scott said Florida recently became the second highest state in the country for total airline passenger traffic, partly because of a $1 billion investment in state funding to the airports, including TPA.

“As the airport continues renovations, these trains will help accommodate the millions of future passengers that Tampa International Airport will welcome.”

Mitsubishi Heavy Industries built the SkyConnect cars at its factory in Japan. Each train car cost approximately $1.9 million and is designed to last 25 years. The SkyConnect trip from the main terminal to the rental car center will include a stop at the economy parking garage. The facility will include kiosks for obtaining boarding passes and checking bags.

The car exteriors feature birds commonly found in the Tampa Bay region. The airport team worked with the Audubon Society to select the images.

“These train cars feature the latest technology and a design concept unlike any we've seen before,” said Darin Friedmann, vice president and general manager of Mitsubishi Heavy Industries America's Transportation Systems Division. “Tampa International Airport has a long history with automated people-movers as the first airport in the world to incorporate the system into their design. We are thrilled to continue to build upon that legacy.”

A second phase of the expansion project includes express curbside drop-off for passengers without checked bags, along with the commercial development of 17 acres of airport property. The centerpiece of the next phase is the commercial development, which includes plans for up to two hotels, an eight-story, 240,000-sq.-ft. office building, a 20,000-sq.-ft. retail strip and a gas station with a convenience store. The gateway also includes a large atrium, pedestrian connections to area trails and commercial curb sides for transit and ground transportation.

Phase II also includes widening the George Bean Parkway, which is the main artery in and out of the airport, as well as adding a new exit lane and a new airport energy plant.

Site preparation for the development is scheduled to start in mid-2018, with construction launching in 2019, pending board approvals. The project will run until 2023.

A $798 million Phase III is expected to begin in 2023, and includes a new Airside D with 16 gates capable of handling both domestic and international flights. This phase would finish in 2026.

Tampa International Airport is located six miles west of downtown Tampa, in Hillsborough County, and is publicly owned by Hillsborough County Aviation Authority. Recognized for its architecture and Landside/Airside design of a central terminal connected by people movers to satellite air terminals and gates, the airport was known as Drew Field Municipal Airport until 1952.

The airport is served by more than twenty major air carrier airlines, four regional airlines and two air cargo carriers. It currently serves 85 non-stop destinations throughout North America, Central America, the Caribbean and Europe. Tampa International is one of only two airports in the United States to host regularly scheduled charters to four Cuban cities, including Havana and Santa Clara. The airport handled nearly 19 million passengers in 2016, making it among the 30 busiest airports by passenger movements in North America.

CEG




Today's top stories

Rebuilding Process Begins Post-Helene

KCI, MoDOT Work to Improve I-55 Near St. Louis

ODOT's I-75 Rehabilitation Currently On Time, Budget

Associated Equipment Distributor's Former Chairman Craig Drury Urges Senate to Reconsider Broad Approach to Right to Repair

Mecalac Launches Range of Hammers, Revolutionizing Efficiency On Working Sites

New Holland Construction Unveils E90D Midi Excavator

JCB Launches Biggest X Series Crawler Excavator With 370X

Alabama AGC Honors 2024 Winners of 40 Under 40 in Construction Awards


 







39.04690 \\ -77.49030 \\ Ashburn \\ PA